Inspection Status: Not Ready

Inspection History: COT - HCME - Mechanical Above Ceiling

Permit Number - TC-COM-0423-00982

Inspection Description - COT - HCME - Mechanical Above Ceiling

Inspection Status - Not Ready

Date Description Inspector Results Comments
04/11/2024 COT - HCME - Mechanical Above Ceiling Not Ready
04/25/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 4/25/24: mechanical above ceiling approved in rooms: 156,159,160,161,156b corridor,162,163,164,155,154, North East main corridor. Ok to lay tile in progress area.
04/30/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 4/25/24: mechanical above ceiling approved in rooms: 156,159,160,161,156b corridor,162,163,164,155,154, North East main corridor. Ok to lay tile in progress area.

4/30/24: mechanical above ceiling approved in rooms: 157,158,168,167,165,103,106,118,119,117,120,115,121,113,112,110,109,108. Ok to lay tile in progress areas.
05/03/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 4/25/24: electrical, plumbing and mechanical above ceiling approved in rooms: 156,159,160,161,156b corridor,162,163,164,155,154, North East main corridor. Ok to lay tile in progress area. All grid ceiling areas completed at first floor except rooms (129,145,150).
05/17/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 4/25/24: electrical, plumbing and mechanical above ceiling approved in rooms: 156,159,160,161,156b corridor,162,163,164,155,154, North East main corridor. Ok to lay tile in progress area. All grid ceiling areas completed at first floor except rooms (129,145,150).
5/17/24: 2nd floor rooms 203,204,208,209,210, 1st floor room 126 north half ok to lay tile, south half of 126 ok to lay tile on south and east borders of drop ceiling (pending hood duct).
05/22/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 4/25/24: electrical, plumbing and mechanical above ceiling approved in rooms: 156,159,160,161,156b corridor,162,163,164,155,154, North East main corridor. Ok to lay tile in progress area. All grid ceiling areas completed at first floor except rooms (129,145,150).
5/17/24: 2nd floor rooms 203,204,208,209,210, 1st floor room 126 north half ok to lay tile, south half of 126 ok to lay tile on south and east borders of drop ceiling (pending hood duct).
5/22/24: room 207 mechanical above ceiling complete.
05/28/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 4/25/24: electrical, plumbing and mechanical above ceiling approved in rooms: 156,159,160,161,156b corridor,162,163,164,155,154, North East main corridor. Ok to lay tile in progress area. All grid ceiling areas completed at first floor except rooms (129,145,150).
5/17/24: 2nd floor rooms 203,204,208,209,210, 1st floor room 126 north half ok to lay tile, south half of 126 ok to lay tile on south and east borders of drop ceiling (pending hood duct).
5/22/24: room 207 mechanical above ceiling complete.
5/28/24: above ceiling complete in corridor 200,216,217A,213,214b
06/05/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 4/25/24: electrical, plumbing and mechanical above ceiling approved in rooms: 156,159,160,161,156b corridor,162,163,164,155,154, North East main corridor. Ok to lay tile in progress area. All grid ceiling areas completed at first floor except rooms (129,145,150).
5/17/24: 2nd floor rooms 203,204,208,209,210, 1st floor room 126 north half ok to lay tile, south half of 126 ok to lay tile on south and east borders of drop ceiling (pending hood duct).
5/22/24: room 207 mechanical above ceiling complete.
5/28/24: above ceiling complete in corridor 200,216,217A,213,214b
6/5/24: 227,228,229
06/21/2024 COT - HCME - Mechanical Above Ceiling Passed