Permit: TC-COM-0323-00800
Permit Details
Apply Date:
03/13/2023
Applicant:
City of Tucson
Description:
NEW MULTI-FAMILY DEVELOPMENT, BLDG 9, 48,753 SF, 48 UNITS AND INCLUDES DEMO - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING" PERMITS. BLDGS 1,2,4-8 & 10 ARE "COMMERCIAL ADDITION/ALTERATION" PERMITS".
Permit Reviews
Permit Number - TC-COM-0323-00800
Permit Status: Issued
Permit Description: NEW MULTI-FAMILY DEVELOPMENT, BLDG 9, 48,753 SF, 48 UNITS AND INCLUDES DEMO - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING" PERMITS. BLDGS 1,2,4-8 & 10 ARE "COMMERCIAL ADDITION/ALTERATION" PERMITS".
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/13/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/11/2023 | REQUIRES RESUBMIT |
06/12/2023 | COMMERCIAL REVIEW - FULL v.4 | 06/16/2023 | REQUIRES RESUBMIT |
04/24/2023 | COMMERCIAL REVIEW - FULL v.3 | 05/26/2023 | REQUIRES RESUBMIT |
06/27/2023 | RESTAMP - COMMERCIAL v.1 | 07/03/2023 | APPROVED |
12/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/17/2024 | APPROVED |
06/27/2023 | COMMERCIAL REVIEW - FULL v.5 | 06/27/2023 | APPROVED |
04/11/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/11/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0323-00800
Permit Status: Issued
Permit Description: NEW MULTI-FAMILY DEVELOPMENT, BLDG 9, 48,753 SF, 48 UNITS AND INCLUDES DEMO - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING" PERMITS. BLDGS 1,2,4-8 & 10 ARE "COMMERCIAL ADDITION/ALTERATION" PERMITS".
Total Outstanding Activity Conditions - 12
Date | Name |
---|---|
06/16/2023 | SPECIAL INSPECTION FOR Prefabricated Wood Elements IS REQUIRED |
06/16/2023 | SPECIAL INSPECTION FOR Structural Steel IS REQUIRED |
12/23/2024 | AIR BALANCING REPORT IS REQUIRED. |
12/23/2024 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
12/23/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
12/23/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
12/23/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
12/23/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
12/23/2024 | This project requires the completion of a Fire Construction Permit PRIOR TO FINALING this permit. |
12/23/2024 | Verify that Permit #P23SD00041 - Milagro on Oracle - Public Sewer is issued and all fees are paid – Waste water receipt |
12/23/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
12/23/2024 | Prior to project being finalized applicant must provide new water easement recordation information |
Conditions
Permit Number - TC-COM-0323-00800
Permit Status: Issued
Permit Description: NEW MULTI-FAMILY DEVELOPMENT, BLDG 9, 48,753 SF, 48 UNITS AND INCLUDES DEMO - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING" PERMITS. BLDGS 1,2,4-8 & 10 ARE "COMMERCIAL ADDITION/ALTERATION" PERMITS".
Date | Description | Comments |
---|---|---|
04/26/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
06/16/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0323-00800
Permite Description: NEW MULTI-FAMILY DEVELOPMENT, BLDG 9, 48,753 SF, 48 UNITS AND INCLUDES DEMO - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING" PERMITS. BLDGS 1,2,4-8 & 10 ARE "COMMERCIAL ADDITION/ALTERATION" PERMITS".
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/28/2023 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | Elevator shaft. Elevator walls 2nd lift at 16'. Okay to grout per special inspection report. 11/16/2023 11/17/23: Elevator shaft, elevator walls 3rd lift at 24'. Okay to grout per special inspection report. 11/28/23: Elevator shaft, elevator walls 4th lift at 32'. Okay to grout per special inspection report. |
11/16/2023 | COT - HCEL - Grounding/Bonding | N/A | Not Ready | |
04/11/2024 | COT - HCBU - Framing | N/A | Partial Pass | Level #1, room units and,common areas. |
01/17/2025 | COT - HCEL - Electrical Final | N/A | Not Ready | |
01/17/2025 | COT - LCME - Mechanical Final | N/A | Not Ready | |
01/17/2025 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
01/17/2025 | ENGR Engineering Final | N/A | Partial Pass | Okay for level 4 TCO |
01/17/2025 | COT - LCBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0323-00800
Permit Description: NEW MULTI-FAMILY DEVELOPMENT, BLDG 9, 48,753 SF, 48 UNITS AND INCLUDES DEMO - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING" PERMITS. BLDGS 1,2,4-8 & 10 ARE "COMMERCIAL ADDITION/ALTERATION" PERMITS".
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/11/2024 | COT - LCBU - Preslab | Passed | Ok to place concrete when vapor barrier is in place. | |
04/26/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
04/26/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
04/26/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
04/26/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
05/02/2024 | COT - BULD - SWG Clearance | Passed | ||
05/21/2024 | COT - HCBU - Framing | Passed | ||
07/25/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
07/25/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
07/25/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
07/25/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
07/25/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
07/25/2024 | COT - HCEL - Electrical Progress | Passed | ||
09/11/2024 | COT - HCEL - Electrical Underground | Passed | 9/11/24: buildings 3,9,10 secondary conduit coming from transformer | |
11/12/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. BUILDING #9. (Distribution A) Generator, Elevator, Lighting, 9408,9401,9402,9403,9404,9405,9406,9413,9411,9412,9410,9409. (Distribution B) 9407,9313,9312,9311,9310,9309,9308,9307,9306,9305,9304,9303. (Distribution C) 9301,9211,9210,9209,9208,9207,9206,9205,9204,9203,9202,9302. (Distribution D) 9201,9118,9117,9116,9115,9114,9112,9113,9111,9110,9109,9108. 11/12/2024 |
|
12/17/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
01/22/2025 | COT - FCON - Alarm - Final | Passed | ||
01/22/2025 | COT - FCON - Sprinkler - Final | Passed | ||
01/22/2025 | COT - HCEL - Electrical Final | Passed | ||
01/22/2025 | COT - FCON - Fire - Final | Passed | ||
01/22/2025 | COT - LCME - Mechanical Final | Passed | ||
01/22/2025 | COT - LCPL - Plumbing Final | Passed | ||
01/22/2025 | ENGR Engineering Final | Passed | ||
01/22/2025 | TRSP - ROW - Final/Close-Out | Passed |
Scheduled Inspections
Scheduled Inspections - TC-COM-0323-00800
Status: Issued
Description: NEW MULTI-FAMILY DEVELOPMENT, BLDG 9, 48,753 SF, 48 UNITS AND INCLUDES DEMO - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING" PERMITS. BLDGS 1,2,4-8 & 10 ARE "COMMERCIAL ADDITION/ALTERATION" PERMITS".
Scheduled Date | Description | Entered By | Entered Date |
---|---|---|---|
02/03/2025 | COT - LCBU - Building Final | Scheduled |