Inspection Status: Not Ready

Inspection History: COT - LCBU - Preslab  

Permit Number - TC-COM-0323-00800

Inspection Description - COT - LCBU - Preslab  

Inspection Status - Not Ready

Date Description Inspector Results Comments
01/04/2024 COT - LCBU - Preslab   Not Ready Contractor cancelled. Will reschedule for 5 January.
01/11/2024 COT - LCBU - Preslab   Passed Ok to place concrete when vapor barrier is in place.
10/04/2023 COT - LCBU - Preslab   Canceled
10/06/2023 COT - LCBU - Preslab   Partial Pass Exterior perimeter footings (F2, F3), 10 each interior shear wall footings SW3 at GL: 1 - 11/East and West end footings
10/11/2023 COT - LCBU - Preslab   Partial Pass 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans.
10/17/2023 COT - LCBU - Preslab   Partial Pass Column footings at Northeast to Southeast area: 3 each C1 - F6, C7 - F11, 2 Each at C5 - F8, C3 - F10, C4 - F9, C2 - F7. Elevator pit at Northeast portion of building. Ok to place concrete in progress areas.
10/20/2023 COT - LCBU - Preslab   Partial Pass North stem wall at 12” x 6” x approximately 150’. Ok to place concrete in progress areas.
10/27/2023 COT - LCBU - Preslab   Partial Pass 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans.
10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116)
11/09/2023 COT - LCBU - Preslab   Partial Pass 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans.
10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116)
11/9/23: reinforcement per plan, Anchor bolts per plan on shear walls, footing F5 grid line C1- C14.
11/15/2023 COT - LCBU - Preslab   Partial Pass Underground plumbing for building #9, waste lines at 2” - 6”. Ok to cover progress areas.
11/21/2023 COT - LCBU - Preslab   Partial Pass 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans.
10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116)
11/9/23: reinforcement per plan, Anchor bolts per plan on shear walls, footing F5 grid line C1- C14.
11/21/23: reinforcement per plan, Center stem wall rebar grid line B 1-15
11/29/2023 COT - LCBU - Preslab   Not Ready 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans.
10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116)
11/9/23: reinforcement per plan, Anchor bolts per plan on shear walls, footing F5 grid line C1- C14.
11/21/23: reinforcement per plan, Center stem wall rebar grid line B 1-13
11/29/23: Not ready
11/30/2023 COT - LCBU - Preslab   Partial Pass 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans.
10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116)
11/9/23: reinforcement per plan, Anchor bolts per plan on shear walls, footing F5 grid line C1- C14.
11/21/23: reinforcement per plan, Center stem wall rebar grid line B 1-13
11/29/23: Not ready
11/30/23: vapor barrier and expansion joints installed per plan, reinforcement per plan at Footing 2 for 4" concrete slab.
12/07/2023 COT - LCBU - Preslab   Partial Pass Detail #110 page S501 Interior footings at grid line 11, 8, and 5 At C1 - B. Okay for concrete placement. 12/7/2023