Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Preslab
Permit Number - TC-COM-0323-00800
Inspection Description - COT - LCBU - Preslab
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/04/2024 | COT - LCBU - Preslab | Not Ready | Contractor cancelled. Will reschedule for 5 January. | |
01/11/2024 | COT - LCBU - Preslab | Passed | Ok to place concrete when vapor barrier is in place. | |
10/04/2023 | COT - LCBU - Preslab | Canceled | ||
10/06/2023 | COT - LCBU - Preslab | Partial Pass | Exterior perimeter footings (F2, F3), 10 each interior shear wall footings SW3 at GL: 1 - 11/East and West end footings | |
10/11/2023 | COT - LCBU - Preslab | Partial Pass | 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans. | |
10/17/2023 | COT - LCBU - Preslab | Partial Pass | Column footings at Northeast to Southeast area: 3 each C1 - F6, C7 - F11, 2 Each at C5 - F8, C3 - F10, C4 - F9, C2 - F7. Elevator pit at Northeast portion of building. Ok to place concrete in progress areas. | |
10/20/2023 | COT - LCBU - Preslab | Partial Pass | North stem wall at 12” x 6” x approximately 150’. Ok to place concrete in progress areas. | |
10/27/2023 | COT - LCBU - Preslab | Partial Pass | 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans. 10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116) |
|
11/09/2023 | COT - LCBU - Preslab | Partial Pass | 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans. 10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116) 11/9/23: reinforcement per plan, Anchor bolts per plan on shear walls, footing F5 grid line C1- C14. |
|
11/15/2023 | COT - LCBU - Preslab | Partial Pass | Underground plumbing for building #9, waste lines at 2” - 6”. Ok to cover progress areas. | |
11/21/2023 | COT - LCBU - Preslab | Partial Pass | 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans. 10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116) 11/9/23: reinforcement per plan, Anchor bolts per plan on shear walls, footing F5 grid line C1- C14. 11/21/23: reinforcement per plan, Center stem wall rebar grid line B 1-15 |
|
11/29/2023 | COT - LCBU - Preslab | Not Ready | 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans. 10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116) 11/9/23: reinforcement per plan, Anchor bolts per plan on shear walls, footing F5 grid line C1- C14. 11/21/23: reinforcement per plan, Center stem wall rebar grid line B 1-13 11/29/23: Not ready |
|
11/30/2023 | COT - LCBU - Preslab | Partial Pass | 10/11/23: Column footings @ G.L E/1-13, & G.L B1 reinforcement per plans. 10/27/23: Elevator pit stem walls reinforcement per plan. (S501/117, S501/116) 11/9/23: reinforcement per plan, Anchor bolts per plan on shear walls, footing F5 grid line C1- C14. 11/21/23: reinforcement per plan, Center stem wall rebar grid line B 1-13 11/29/23: Not ready 11/30/23: vapor barrier and expansion joints installed per plan, reinforcement per plan at Footing 2 for 4" concrete slab. |
|
12/07/2023 | COT - LCBU - Preslab | Partial Pass | Detail #110 page S501 Interior footings at grid line 11, 8, and 5 At C1 - B. Okay for concrete placement. 12/7/2023 |