Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
01/22/2024 COT - HCBU - Framing Partial Pass Partial pass. Deck nailing at second floor approved. 1/22/2024
02/13/2024 COT - HCBU - Framing Partial Pass Partial pass. Deck nailing at third floor approved. 2/13/2024
03/01/2024 COT - HCBU - Framing Partial Pass
03/15/2024 COT - HCBU - Framing Partial Pass Roof area, Ok to dry-in roof system
03/19/2024 COT - HCBU - Framing Partial Pass North wall, 10 hold-downs were drilled and epoxied as required. Special inspection for epoxy work.
04/11/2024 COT - HCBU - Framing Partial Pass Level #1, room units and,common areas.
04/15/2024 COT - HCBU - Framing Canceled Inspection performed on 12 April.
04/24/2024 COT - HCBU - Framing Partial Pass Level #3 Room units and public areas. Ok to insulate and cover walls.
05/02/2024 COT - HCBU - Framing Partial Pass Framing at 4th level approved. 5/2/2024
05/21/2024 COT - HCBU - Framing Passed