Permit: TC-COM-0224-00338
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
6690 S ALVERNON WY UNIT 150
Address NEW:
6690 S ALVERNON WY UNIT 150
Apply Date:
02/21/2024
Applicant:
burak bekat
Description:
Tenant improvement of existing warehouse space. New use consists of beer keg sanitation, storage and associated office spaces (F-2, S-2 & B). Type VB construction. Privately funded.
Permit Reviews
Permit Number - TC-COM-0224-00338
Permit Status: Complete
Permit Description: Tenant improvement of existing warehouse space. New use consists of beer keg sanitation, storage and associated office spaces (F-2, S-2 & B). Type VB construction. Privately funded.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/02/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/03/2024 | APPROVED |
| 05/21/2024 | COMMERCIAL REVIEW - FULL v.4 | 05/23/2024 | REQUIRES RESUBMIT |
| 06/05/2024 | RESTAMP - COMMERCIAL v.1 | 06/06/2024 | APPROVED |
| 11/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/18/2024 | APPROVED |
| 04/03/2024 | COMMERCIAL REVIEW - FULL v.2 | 05/09/2024 | REQUIRES RESUBMIT |
| 05/24/2024 | COMMERCIAL REVIEW - FULL v.5 | 05/30/2024 | REQUIRES RESUBMIT |
| 05/31/2024 | COMMERCIAL REVIEW - FULL v.6 | 06/05/2024 | APPROVED |
| 05/14/2024 | COMMERCIAL REVIEW - FULL v.3 | 05/20/2024 | REQUIRES RESUBMIT |
| 11/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/06/2024 | APPROVED |
| 02/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/25/2025 | APPROVED |
| 02/27/2024 | COMMERCIAL REVIEW - FULL v.1 | 03/28/2024 | REQUIRES RESUBMIT |
| 06/12/2024 | RESTAMP - COMMERCIAL v.1 | 06/17/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0224-00338
Permit Status: Complete
Permit Description: Tenant improvement of existing warehouse space. New use consists of beer keg sanitation, storage and associated office spaces (F-2, S-2 & B). Type VB construction. Privately funded.
| Date | Description | Comments |
|---|---|---|
| 02/27/2024 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 06/04/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 11/06/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 02/27/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/04/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 06/04/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 06/04/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 06/04/2024 | Post-Installed Anchor Inspection Report is required. | |
| 11/06/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 11/06/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 06/04/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00338
Permite Description: Tenant improvement of existing warehouse space. New use consists of beer keg sanitation, storage and associated office spaces (F-2, S-2 & B). Type VB construction. Privately funded.
Total Outstanding Inspections - 14
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/16/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Column line D & C. Grid line 8 & 10. Pallets #119. Big slab per plans and details okay for concrete placement. 7/16/2024 |
| 07/16/2024 | COT - HCBU - Preslab | N/A | Partial Pass | Column line D & C. Grid line 8 & 10. Pallets #119. Big slab per plans and details okay for concrete placement. 7/16/2024 |
| COT - FCON - Fire - Final | N/A | Not Ready | subs need to call in their permits. | |
| 09/09/2024 | COT - FCON - Sprinkler - Final | N/A | Not Ready | subs need to call in their permits |
| COT - FCON - Alarm - Final | N/A | Not Ready | subs need to call in their permits | |
| 09/09/2024 | COT - HCBU - Framing | N/A | Re-inspection required | South office floor plan. Pending points of attachment to walls on exterior metal framing. Along with kickers. 9/9/2024 |
| 09/19/2024 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | Partial pass. Hard-lid areas only. Room #'s 102, 105(soffit area), 110, 111, 112, 114, 117. Okay to proceed progress areas. 9/19/2024 |
| 09/19/2024 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | Partial pass. Hard-lid areas only. Room #'s 102, 105(soffit area), 110, 111, 112, 114, 117. Okay to proceed progress areas. 9/19/2024 |
| 12/31/2024 | BULD - Electrical Clearance | N/A | Not Ready | |
| 11/19/2024 | COT - HCBU - Building Final | N/A | Partial Pass | Okay for level 2 TCO for warehouse area. Room #120, #121, and #120. Barriers around office areas. Under construction. 9/11/2024 11/15/24: not ready 11/19/24: Ok for level 4 TCO for entire building. |
| 11/19/2024 | COT - HCEL - Electrical Final | N/A | Partial Pass | Okay for level 2 TCO for warehouse area. Room #120, #121, and #120. Barriers around office areas. Under construction. 9/11/2024 11/15/24: not ready 11/19/24: Ok for level 4 TCO for entire building. |
| 11/19/2024 | COT - HCME - Mechanical Final | N/A | Partial Pass | Okay for level 2 TCO for warehouse area. Room #120, #121, and #120. Barriers around office areas. Under construction. 9/11/2024 11/15/24: not ready 11/19/24: Ok for level 4 TCO for entire building. |
| 11/19/2024 | COT - HCPL - Gas Final | N/A | Partial Pass | Okay for level 2 TCO for warehouse area. Room #120, #121, and #120. Barriers around office areas. Under construction. 9/11/2024 11/15/24: not ready 11/19/24: Ok for level 4 TCO for entire building. |
| 11/19/2024 | COT - HCPL - Plumbing Final | N/A | Partial Pass | Okay for level 2 TCO for warehouse area. Room #120, #121, and #120. Barriers around office areas. Under construction. 9/11/2024 11/15/24: not ready 11/19/24: Ok for level 4 TCO for entire building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00338
Permit Description: Tenant improvement of existing warehouse space. New use consists of beer keg sanitation, storage and associated office spaces (F-2, S-2 & B). Type VB construction. Privately funded.
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/20/2024 | COT - HCEL - Electrical Underground | Passed | 6/20/24: electrical underground at conference room 105 for 2 floor boxes passed ok to proceed. | |
| 09/09/2024 | ENGR Engineering Final | Passed | Approved for TCO2 | |
| 09/09/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 09/09/2024 | COT - HCBU - Preslab | Passed | ||
| 09/10/2024 | COT - FCON - Fire - Final | Passed | ||
| 11/18/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 11/18/2024 | COT - FCON - Alarm - Final | Passed | ||
| 09/19/2024 | COT - HCBU - Framing | Passed | ||
| 10/03/2024 | COT - BULD - SWG Clearance | Passed | clearance for Southwest Gas. 10/3/2024 | |
| 10/03/2024 | COT - HCPL - Gas Pressure Test | Passed | ||
| 11/04/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
| 11/04/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 11/04/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 11/04/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 11/04/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 11/04/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 11/04/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 11/18/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 02/01/2025 | BULD - Electrical Clearance | Passed | 2/1/25: ECO VERBAL TEP CLEARANCE FOR 6690 S ALVERNON WY UNIT 150, SENT IT AT 7;30am | |
| 02/14/2025 | COT - HCBU - Building Final | Passed | ||
| 02/14/2025 | COT - HCEL - Electrical Final | Passed | ||
| 02/14/2025 | COT - HCME - Mechanical Final | Passed | ||
| 02/14/2025 | COT - HCPL - Gas Final | Passed | ||
| 02/14/2025 | COT - HCPL - Plumbing Final | Passed |