Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Intermediate

Date Description Inspector Results Comments
06/20/2024 COT - HCEL - Electrical Intermediate Partial Pass 6/20/24: electrical underground at conference room 105 for 2 floor boxes passed ok to proceed.
07/24/2024 COT - HCEL - Electrical Intermediate Partial Pass Partial pass. Storage room #121 and support room #120. Electrical in walls and one vent pipe for floor drain (support room). Okay to proceed progress areas. 7/24/2024
08/12/2024 COT - HCEL - Electrical Intermediate Partial Pass Partial pass. Room #'s #120,#121#, and #122 electrical in walls approved. Okay to proceed progress areas. 8/12/2024
08/22/2024 COT - HCEL - Electrical Intermediate Partial Pass Total of 6 conduits. X3 2 1/2” x2 3” and x1 2” schedule 40 for new switch gear. Tapping into existing distribution board. (SES 3B) 8/22/2024
09/09/2024 COT - HCEL - Electrical Intermediate Partial Pass South office floor plan.
Room numbers 101- 118 all electrical in wall in place. Okay to proceed progress areas. 9/9/2024
11/04/2024 COT - HCEL - Electrical Intermediate Passed