Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 06/20/2024 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
6/20/24: plumbing underground passed ok to backfill. Shading required |
| 07/24/2024 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Partial pass. Storage room #121 and support room #120. Electrical in walls and one vent pipe for floor drain (support room). Okay to proceed progress areas. 7/24/2024 |
| 09/09/2024 |
COT - HCPL - Plumbing Intermediate |
|
Re-inspection required |
Plumbing needs supports secure all Mickey Mouse straps to studs. Secure vertical piping. |
| 09/11/2024 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
#102,#109,#110,#111,#112,#113,#114,#117,#118, all plumbing in walls and above approved. Okay to proceed progress areas. 9/11/2024 |
| 11/04/2024 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
|