Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
06/20/2024 COT - HCPL - Plumbing Intermediate  Partial Pass 6/20/24: plumbing underground passed ok to backfill. Shading required
07/24/2024 COT - HCPL - Plumbing Intermediate  Partial Pass Partial pass. Storage room #121 and support room #120. Electrical in walls and one vent pipe for floor drain (support room). Okay to proceed progress areas. 7/24/2024
09/09/2024 COT - HCPL - Plumbing Intermediate  Re-inspection required Plumbing needs supports secure all Mickey Mouse straps to studs. Secure vertical piping.
09/11/2024 COT - HCPL - Plumbing Intermediate  Partial Pass #102,#109,#110,#111,#112,#113,#114,#117,#118, all plumbing in walls and above approved. Okay to proceed progress areas. 9/11/2024
11/04/2024 COT - HCPL - Plumbing Intermediate  Passed