Permit: TC-COM-0224-00334
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
10048 E OLD VAIL RD
Address NEW:
10048 E OLD VAIL RD
Apply Date:
02/20/2024
Applicant:
Abraham Vazquez
Description:
Proposed Development consists of a 3,305 S.F. Restaurant with drive-thru, with parking and landscape areas.
Permit Reviews
Permit Number - TC-COM-0224-00334
Permit Status: Complete
Permit Description: Proposed Development consists of a 3,305 S.F. Restaurant with drive-thru, with parking and landscape areas.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/13/2024 | COMMERCIAL REVIEW - FULL v.5 | 01/09/2025 | APPROVED |
| 09/25/2024 | COMMERCIAL REVIEW - FULL v.3 | 10/30/2024 | REQUIRES RESUBMIT |
| 11/05/2024 | COMMERCIAL REVIEW - FULL v.4 | 11/29/2024 | REQUIRES RESUBMIT |
| 02/26/2024 | COMMERCIAL REVIEW - FULL v.1 | 03/26/2024 | REQUIRES RESUBMIT |
| 08/12/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/14/2025 | APPROVED |
| 08/08/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/11/2025 | APPROVED |
| 09/12/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 09/15/2025 | APPROVED |
| 01/15/2025 | RESTAMP - COMMERCIAL v.1 | 01/19/2025 | APPROVED |
| 02/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/05/2025 | APPROVED |
| 09/08/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/11/2025 | REQUIRES RESUBMIT |
| 04/01/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/03/2025 | APPROVED |
| 07/31/2024 | COMMERCIAL REVIEW - FULL v.2 | 08/30/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0224-00334
Permit Status: Complete
Permit Description: Proposed Development consists of a 3,305 S.F. Restaurant with drive-thru, with parking and landscape areas.
| Date | Description | Comments |
|---|---|---|
| 02/26/2024 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 09/26/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 09/26/2024 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. | |
| 09/26/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
| 09/26/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 02/26/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 09/26/2024 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
| 09/26/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 09/26/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 09/11/2025 | Post-Installed Anchor Inspection Report is required. | |
| 02/26/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 09/26/2024 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 09/26/2024 | SPECIAL INSPECTION FOR ??? IS REQUIRED | |
| 09/26/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 09/26/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 09/26/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
| 09/26/2024 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 09/26/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. | |
| 09/26/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. | |
| 09/26/2024 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00334
Permite Description: Proposed Development consists of a 3,305 S.F. Restaurant with drive-thru, with parking and landscape areas.
Total Outstanding Inspections - 17
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - FCON - Sprinkler - Final | N/A | Not Ready | Inspected riser sweep only, ductile iron riser needed sleeve. | |
| 08/08/2025 | COT - HCBU - Sustainability | N/A | Not Applicable | 8-8-25: not applicable |
| 05/14/2025 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 3-10-25, not ready. 5/14/25: plumbing in wall approved ok to proceed with insulation. |
| 08/08/2025 | COT - HCBU - Masonry Pregrout | N/A | Not Applicable | 8-8-25: not applicable |
| 08/05/2025 | COT - HCBU - Building Final | N/A | Partial Pass | 8/5/2025 partial pass. All corrections were made. Pending special condition reports and other inspections. |
| 04/01/2025 | COT - HCPL - Sewer | N/A | Partial Pass | 3-17-25, 8" sewer tie in located on southeast corner of site. Okay to backfill approximately 70' section with shading materials. Contractor will schedule pressure test later this week 3-20-25, 70' of 8" sewer line up to manhole verified at 3psi. Other section of sewer line on opposite side of manhole at approximately 80' is okay to backfill with shading materials and will be pressurized sometime next week. 3-25-25, base of manhole poured. The 8" line from the manhole will be pressurized later this week together with a pressure test for the grease trap. 4/1/25: sewer grease and vent. |
| 03/11/2025 | COT - HCPL - Rough Soil | N/A | Partial Pass | 3-11-25, underground plumbing under test & as per approved plans. Okay to backfill with shading material. Main water together with HCS connection will be inspected at a later date. |
| 08/08/2025 | COT - HCBU - Stem Wall/Retaining Wall | N/A | Not Applicable | 8-8-25: not applicable |
| 08/08/2025 | COT - HCBU - TCO | N/A | Partial Pass | 8-8-25: okay for Level 1 TCO. |
| 07/07/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Canceled | 7-7-25: reschedule inspection under development permit. |
| 05/09/2025 | COT - HCBU - Framing | N/A | Re-inspection required | Plumbing in walls not approved. 5/9/2025 |
| 03/13/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 3-13-25, electrical conduits for kitchen and BMS (lighting ) panels verified per plans. Okay to backfill at progress areas. |
| 04/01/2025 | COT - HCPL - Yard Water Line | N/A | Partial Pass | 4/1/25: Water line 1 1/2" Domestic water entry at building under pressure ok to backfill. |
| 05/06/2025 | COT - HCME - Mechanical Progress | N/A | Partial Pass | 5/5/25: spark test at sewer manhole 1 approved, vacuum test at manhole 1 approved. |
| 05/06/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 5/5/25: spark test at sewer manhole 1 approved, vacuum test at manhole 1 approved. |
| COT - FCON - Alarm - Final | N/A | Not Ready | ||
| COT - FCON - Fire - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00334
Permit Description: Proposed Development consists of a 3,305 S.F. Restaurant with drive-thru, with parking and landscape areas.
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/30/2025 | COT - HCBU - Roof Nailing | Passed | ||
| 06/03/2025 | COT - BULD - SWG Clearance | Passed | 6-3-25: gas pressure test verified. Okay for SWG to install meter-clearance issued. | |
| 07/30/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 07/30/2025 | COT - HCEL - Electrical Final | Passed | ||
| 08/08/2025 | COT - HCBU - Building Above Ceiling | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCPL - Gas Final | Passed | 8-8-25: gas final approved. | |
| 08/08/2025 | COT - HCME - Mechanical Final | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCEL - Electrical Intermediate | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCPL - Backwater Valve | Passed | 8-8-25: approved | |
| 08/08/2025 | COT - HCPL - Plumbing Progress | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCEL - Electrical Above Ceiling | Passed | 8-8-25: approved. | |
| 08/08/2025 | TRSP - ROW - Final/Close-Out | Passed | Work completed on private property | |
| 08/08/2025 | COT - HCBU - Exterior Clips/Sheathing | Passed | 8-8-25:exterior clips/sheathing approved. | |
| 08/08/2025 | COT - HCBU - Building Final | Passed | 8-8-25: building final approved. Note: See Pending Conditions. |
|
| 08/08/2025 | COT - HCPL - Sewer | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCPL - Rough Soil | Passed | 8-8-25: approved | |
| 08/08/2025 | COT - HCME - Mechanical Intermediate | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCPL - Gas Pressure Test | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 8-8-25: previously inspected and approved. | |
| 08/08/2025 | COT - HCBU - Framing | Passed | 8-8-25: framing inspection approved. | |
| 08/08/2025 | COT - HCEL - Electrical Progress | Passed | 8-8-25: electrical progress approved. | |
| 08/08/2025 | COT - HCEL - Grounding/Bonding | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCEL - Electrical Underground | Passed | 8-8-25: approved | |
| 08/08/2025 | COT - HCEL - Outdoor Lighting | Passed | 8-8-25: approved | |
| 08/08/2025 | COT - HCPL - Plumbing Roof Drains | Passed | 8-8-25: approved | |
| 08/08/2025 | COT - FCON - Hood System - Final | Passed | by w. motto | |
| 08/08/2025 | COT - HCBU - Preslab | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCPL - Plumbing Final | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCPL - Yard Water Line | Passed | 8-8-25: previously inspected and approved. | |
| 08/08/2025 | COT - HCME - Venting | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCPL - Plumbing Intermediate | Passed | 8-8-25: approved | |
| 08/08/2025 | COT - HCME - Mechanical Above Ceiling | Passed | 8-8-25: approved | |
| 08/08/2025 | COT - HCPL - Plumbing Above Ceiling | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCBU - Interior Shear Bracing | Passed | 8-8-25: approved. | |
| 08/08/2025 | COT - HCBU - Building Progress | Passed | 8-8-25: approved | |
| 08/08/2025 | PDSD Heavy Commercial Building Division Pre-Construction Meeting | Passed | 8-8-25: approved | |
| 08/19/2025 | COT - FCON - Alarm - Final | Passed | ||
| 08/19/2025 | COT - FCON - Fire - Final | Passed | ||
| 08/12/2025 | ENGR Engineering Final | Passed |