Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Sewer
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/17/2025 | COT - HCPL - Sewer | Partial Pass | 3-17-25, 8" sewer tie in located on southeast corner of site. Okay to backfill approximately 70' section with shading materials. Contractor will schedule pressure test later this week | |
| 03/20/2025 | COT - HCPL - Sewer | Partial Pass | 3-20-25, 70' of 8" sewer line up to manhole verified at 3psi. Other section of sewer line on opposite side of manhole at approximately 80' is okay to backfill with shading materials and will be pressurized sometime next week. | |
| 03/25/2025 | COT - HCPL - Sewer | Partial Pass | 3-25-25, base of manhole poured. The 8" line from the manhole will be pressurized later this week together with a pressure test for the grease trap. | |
| 04/01/2025 | COT - HCPL - Sewer | Partial Pass | 3-17-25, 8" sewer tie in located on southeast corner of site. Okay to backfill approximately 70' section with shading materials. Contractor will schedule pressure test later this week 3-20-25, 70' of 8" sewer line up to manhole verified at 3psi. Other section of sewer line on opposite side of manhole at approximately 80' is okay to backfill with shading materials and will be pressurized sometime next week. 3-25-25, base of manhole poured. The 8" line from the manhole will be pressurized later this week together with a pressure test for the grease trap. 4/1/25: sewer grease and vent. |
|
| 08/08/2025 | COT - HCPL - Sewer | Passed | 8-8-25: approved. |