Permit: TC-COM-0125-00197
Permit Details
Apply Date:
01/29/2025
Applicant:
Brandy Burke
Description:
Interior remodeling and expansion of existing building
Permit Reviews
Permit Number - TC-COM-0125-00197
Permit Status: Complete
Permit Description: Interior remodeling and expansion of existing building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/06/2025 | RESTAMP - COMMERCIAL v.1 | 08/11/2025 | APPROVED |
| 01/05/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/05/2026 | REQUIRES RESUBMIT |
| 01/09/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 01/12/2026 | APPROVED |
| 10/14/2025 | RESTAMP - COMMERCIAL v.1 | 10/16/2025 | APPROVED |
| 02/03/2025 | COMMERCIAL REVIEW - FULL v.1 | 02/26/2025 | REQUIRES RESUBMIT |
| 08/01/2025 | COMMERCIAL REVIEW - FULL v.3 | 08/04/2025 | REQUIRES RESUBMIT |
| 10/10/2025 | COMMERCIAL REVIEW - FULL REVISION v.3 | 10/14/2025 | APPROVED |
| 10/17/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/21/2025 | APPROVED |
| 02/06/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/09/2026 | APPROVED |
| 09/22/2025 | COMMERCIAL REVIEW - FULL REVISION v.2 | 10/07/2025 | REQUIRES RESUBMIT |
| 05/16/2025 | COMMERCIAL REVIEW - FULL v.2 | 06/20/2025 | REQUIRES RESUBMIT |
| 08/21/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 09/17/2025 | REQUIRES RESUBMIT |
| 08/05/2025 | COMMERCIAL REVIEW - FULL v.4 | 08/06/2025 | APPROVED |
| 10/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/29/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0125-00197
Permit Status: Complete
Permit Description: Interior remodeling and expansion of existing building
| Date | Description | Comments |
|---|---|---|
| 06/09/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 02/03/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/25/2025 | SPECIAL INSPECTION OF POST_INSTALLED ANCHORS IS REQUIRED. | |
| 02/03/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 02/25/2025 | SPECIAL INSPECTION OF STEEL CONSTRUCTION IS REQUIRED. | |
| 06/09/2025 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 02/25/2025 | WOOD "I" Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0125-00197
Permite Description: Interior remodeling and expansion of existing building
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/16/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 10/16/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 10/16/2025 | COT - LCPL - Gas Pressure Test | N/A | Not Applicable | |
| 10/16/2025 | COT - LCEL - Electrical Underground | N/A | Not Applicable | |
| 10/16/2025 | COT - LCEL - Grounding/Bonding | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0125-00197
Permit Description: Interior remodeling and expansion of existing building
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/29/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 08/29/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 08/29/2025 | COT - LCBU - Framing | Passed | ||
| 10/16/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 10/16/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 10/16/2025 | COT - LCPL - Rough Soil | Passed | ||
| 10/22/2025 | COT - LCBU - Preslab | Passed | 10-22-25: per S. Carrasco preslab approved. Okay for concrete placement at progress areas. | |
| 11/12/2025 | COT - LCBU - Roof Nailing | Passed | ||
| 11/19/2025 | COT - LCEL - Electrical Intermediate | Passed | Ok to insulate and sheet rock progress | |
| 12/09/2025 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 12/10/2025 | COT - LCME - Mechanical Intermediate | Passed | ||
| 01/15/2026 | COT - FCON - Fire - Final | Passed | ||
| 01/15/2026 | COT - FCON - Alarm - Final | Passed | ||
| 01/15/2026 | COT - LCBU - Building Final | Passed | Ok to make application for Certificate of Occupancy. | |
| 01/15/2026 | COT - LCEL - Electrical Final | Passed | ||
| 01/15/2026 | COT - LCME - Mechanical Final | Passed | Air balance test results were submitted. | |
| 01/15/2026 | COT - LCPL - Plumbing Final | Passed | Chlorination test results have been submitted. | |
| 01/15/2026 | COT - FCON - Sprinkler - Final | Passed | ||
| 01/15/2026 | COT - LCEL - Outdoor Lighting | Passed | ||
| 02/09/2026 | ENGR Engineering Final | Passed |