Inspection Status: Partial Pass
Inspection History: COT - LCPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 08/15/2025 |
COT - LCPL - Rough Soil |
|
Partial Pass |
8-15-25: plumbing underground not per approved plans. An RFI has been submitted to the city for review/approval. Underground plumbing verified under test at room's 110, 109, 109A & 112. Okay to backfill progress areas and continue with construction at own risk-pending RFI approval. |
| 09/19/2025 |
COT - LCPL - Rough Soil |
|
Partial Pass |
Domestic water line from building to main line. Ok to cover progress areas. |
| 10/16/2025 |
COT - LCPL - Rough Soil |
|
Passed |
|