Permit: TC-COM-0124-00185
Permit Details
Apply Date:
01/29/2024
Applicant:
Bryanne Simi
Description:
Tenant improvement to an existing building. we are relocating the TAA Police from the main airport building to this location and adding 5 covered parking spaces on the air side.
Permit Reviews
Permit Number - TC-COM-0124-00185
Permit Status: Issued
Permit Description: Tenant improvement to an existing building. we are relocating the TAA Police from the main airport building to this location and adding 5 covered parking spaces on the air side.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/06/2024 | RESTAMP - COMMERCIAL v.1 | 06/06/2024 | APPROVED |
06/04/2024 | COMMERCIAL REVIEW - FULL v.3 | 06/06/2024 | APPROVED |
12/09/2024 | COMMERCIAL REVIEW - FULL v.2 | 12/16/2024 | APPROVED |
04/08/2024 | COMMERCIAL REVIEW - FULL v.2 | 05/29/2024 | REQUIRES RESUBMIT |
11/15/2024 | COMMERCIAL REVIEW - FULL v.1 | 11/20/2024 | REQUIRES RESUBMIT |
07/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/22/2024 | APPROVED |
01/30/2024 | COMMERCIAL REVIEW - FULL v.1 | 02/28/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0124-00185
Permit Status: Issued
Permit Description: Tenant improvement to an existing building. we are relocating the TAA Police from the main airport building to this location and adding 5 covered parking spaces on the air side.
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
05/29/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
05/29/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
05/29/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
05/29/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
05/29/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0124-00185
Permit Status: Issued
Permit Description: Tenant improvement to an existing building. we are relocating the TAA Police from the main airport building to this location and adding 5 covered parking spaces on the air side.
Date | Description | Comments |
---|---|---|
01/30/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
05/29/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0124-00185
Permite Description: Tenant improvement to an existing building. we are relocating the TAA Police from the main airport building to this location and adding 5 covered parking spaces on the air side.
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/05/2024 | COT - HCBU - Framing | N/A | Partial Pass | 10/30/24: framing per plans at rooms 100,101,102,103,104,105,106,107,108,109,110,112,113,114,115,116,117,118,119,120,121,122,123,124,125,126,127,128,129. Ok to one side. Electrical in wall not complete missing grounding at multiple boxes and pending boxes being installed with conduit runs throughout, plumbing in wall at require plastic garments throughout, plumbing must be under test, access panels must be installed at shut off valves and A.V.V, pending completion of plumbing in walls and test. 12/5/24: partial pass for plumbing in wall. Multiple hangers at copper piping must be replaced or protection must be added to prevent contact between copper piping and dissimilar metals. |
12/05/2024 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 10/30/24: framing per plans at rooms 100,101,102,103,104,105,106,107,108,109,110,112,113,114,115,116,117,118,119,120,121,122,123,124,125,126,127,128,129. Ok to one side. Electrical in wall not complete missing grounding at multiple boxes and pending boxes being installed with conduit runs throughout, plumbing in wall at require plastic garments throughout, plumbing must be under test, access panels must be installed at shut off valves and A.V.V, pending completion of plumbing in walls and test. 12/5/24: partial pass for plumbing in wall. Multiple hangers at copper piping must be replaced or protection must be added to prevent contact between copper piping and dissimilar metals. Insulation required at hot water piping |
12/05/2024 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 10/30/24: framing per plans at rooms 100,101,102,103,104,105,106,107,108,109,110,112,113,114,115,116,117,118,119,120,121,122,123,124,125,126,127,128,129. Ok to one side. Electrical in wall not complete missing grounding at multiple boxes and pending boxes being installed with conduit runs throughout, plumbing in wall at require plastic garments throughout, plumbing must be under test, access panels must be installed at shut off valves and A.V.V, pending completion of plumbing in walls and test. 12/5/24: partial pass for plumbing in wall. Multiple hangers at copper piping must be replaced or protection must be added to prevent contact between copper piping and dissimilar metals. Insulation required at hot water piping |
12/05/2024 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 9/5/24: plumbing underground per plans and under test. Ok to proceed with backfill. 10/30/24: framing per plans at rooms 100,101,102,103,104,105,106,107,108,109,110,112,113,114,115,116,117,118,119,120,121,122,123,124,125,126,127,128,129. Ok to one side. Electrical in wall not complete missing grounding at multiple boxes and pending boxes being installed with conduit runs throughout, plumbing in wall at require plastic garments throughout, plumbing must be under test, access panels must be installed at shut off valves and A.V.V, pending completion of plumbing in walls and test. 12/5/24: partial pass for plumbing in wall. Multiple hangers at copper piping must be replaced or protection must be added to prevent contact between copper piping and dissimilar metals. Insulation required at hot water piping |
12/19/2024 | COT - HCME - Mechanical Progress | N/A | Partial Pass | 10/30/24: framing per plans at rooms 100,101,102,103,104,105,106,107,108,109,110,112,113,114,115,116,117,118,119,120,121,122,123,124,125,126,127,128,129. Ok to one side. Electrical in wall not complete missing grounding at multiple boxes and pending boxes being installed with conduit runs throughout, plumbing in wall at require plastic garments throughout, plumbing must be under test, access panels must be installed at shut off valves and A.V.V, pending completion of plumbing in walls and test. 12/5/24: partial pass for plumbing in wall. Multiple hangers at copper piping must be replaced or protection must be added to prevent contact between copper piping and dissimilar metals. 12/19/24: electrical in wall passed. Ok to cover up walls. 12/19/24: hard duct installed and sealed throughout. |
12/19/2024 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 10/30/24: framing per plans at rooms 100,101,102,103,104,105,106,107,108,109,110,112,113,114,115,116,117,118,119,120,121,122,123,124,125,126,127,128,129. Ok to one side. Electrical in wall not complete missing grounding at multiple boxes and pending boxes being installed with conduit runs throughout, plumbing in wall at require plastic garments throughout, plumbing must be under test, access panels must be installed at shut off valves and A.V.V, pending completion of plumbing in walls and test. 12/5/24: partial pass for plumbing in wall. Multiple hangers at copper piping must be replaced or protection must be added to prevent contact between copper piping and dissimilar metals. 12/19/24: electrical in wall passed. Ok to cover up walls. |