Permit: T22CM06380
Permit Details
Status:
In Review
Type:
Commercial Building
Address:
6335 E TANQUE VERDE RD
Address NEW:
6335 E TANQUE VERDE RD
Apply Date:
08/18/2022
Applicant:
Description:
Ground up enclosed 3 story climate controlled self storage facility with site improvements
Permit Reviews
Permit Number - T22CM06380
Permit Status: In review
Permit Description: Ground up enclosed 3 story climate controlled self storage facility with site improvements
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/18/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/19/2022 | COMPLETED |
| 10/10/2022 | RESUBMITTAL | 10/13/2022 | ACTIVE |
| 06/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/10/2024 | REQUIRES RESUBMIT |
| 03/01/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/27/2023 | REQUIRES RESUBMIT |
| 07/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/17/2024 | APPROVED |
| 05/05/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/07/2023 | APPROVED |
| 05/14/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/14/2024 | APPROVED |
| 06/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 06/20/2024 | REQUIRES RESUBMIT |
| 07/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.4 | 07/10/2024 | APPROVED |
| 06/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/17/2024 | REQUIRES RESUBMIT |
| 10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/23/2022 | APPROVED |
| 04/03/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/12/2023 | APPROVED |
| 05/22/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/23/2024 | APPROVED |
Conditions
Permit Number - T22CM06380
Permit Status: In review
Permit Description: Ground up enclosed 3 story climate controlled self storage facility with site improvements
| Date | Description | Comments |
|---|---|---|
| 05/13/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 05/13/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 05/13/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 07/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 05/13/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 05/13/2024 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 05/13/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: In Review
Permit Number: T22CM06380
Permite Description: Ground up enclosed 3 story climate controlled self storage facility with site improvements
Total Outstanding Inspections - 15
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | |
| 09/29/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Partial Pass | 9/29/23: 2nd layer of 5/8" type X rock on north wall of 2nd level 2-hour rated assembly. |
| 09/20/2023 | COT - HCPL - Sewer | N/A | Canceled | |
| 12/13/2023 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | 12/13/23: partial pass for south portion of west wall |
| 08/31/2023 | COT - HCBU - Framing | N/A | Partial Pass | Wanted masonry pre-grout. 6-20-23: East half of basement. 6-23-23: Basement complete. 7/31/23: framing & floor deck for east half of 2nd floor approved. March 30th: east half of basement slab approved to pour 4-4-23: Stem wall for elevator pit. 4-11-23: Basement walls; East half of South wall and South half of East wall. 4-18-23: North half of East wall. 4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete. 8/9/23: 1st floor framing for west half, 2nd floor deck for pre-slab at west half. 8/31/23: 2nd floor framing approved |
| 09/06/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | East half of third floor rebar along with wire mesh per key notes 31 and 32 page S3.3 okay for concrete placement. 9/6/2023 |
| 01/10/2024 | COT - HCPL - Plumbing Intermediate | N/A | Not Ready | 1/10/24: not ready |
| 03/14/2024 | COT - HCPL - Plumbing Above Ceiling | N/A | Not Applicable | |
| 07/28/2023 | COT - HCBU - Masonry Pregrout | N/A | Deferred | |
| 03/14/2024 | COT - HCEL - Electrical Intermediate | N/A | Not Ready | |
| 04/05/2024 | COT - LCME - Mechanical Progress | N/A | Partial Pass | Level one. |
| 10/17/2023 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | inspection on sewer and water supply 1st & 2nd floor restrooms, |
| 10/25/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Not Ready | |
| 05/21/2024 | COT - HCBU - Building Final | N/A | Not Ready | |
| 04/18/2024 | COT - HCBU - TCO | N/A | Partial Pass | Level Four TCO for majority of Level One, except or area between Stair One and Elevator. |
Completed Inspections
Permit Status: In Review
Permit Number: T22CM06380
Permit Description: Ground up enclosed 3 story climate controlled self storage facility with site improvements
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/16/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 06/20/2023 | COT - HCBU - Preslab | Passed | 6-20-23: East half of basement. | |
| 09/22/2023 | COT - HCPL - Yard Water Line | Passed | ||
| 09/22/2023 | COT - HCPL - Rough Soil | Passed | ||
| 10/25/2023 | COT - HCEL - Electrical Underground | Passed | ||
| 10/31/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
| 11/02/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 11/07/2023 | COT - HCPL - Sewer | Passed | ||
| 11/15/2023 | COT - HCEL - Electrical Progress | Passed | Transformer pad. | |
| 11/16/2023 | COT - HCBU - Roof Nailing | Passed | ||
| 11/29/2023 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
| 12/20/2023 | BULD - Electrical Clearance | Passed | Wiring from transformer to SES switchgear is in place by TEP. Electrician has completed grounding of SES and sub-panels. Wiring is pulled from SES to sub panels. Okay to energize system. ECO Clearance issued for service connection. | |
| 02/15/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 03/05/2024 | COT - HCBU - Framing | Passed | ||
| 03/07/2024 | COT - HCBU - Building Progress | Passed | Roof framing. | |
| 03/14/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 04/02/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
| 04/02/2024 | SITE - Zoning Final | Passed | ||
| 04/02/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
| 05/06/2024 | COT - HCEL - Electrical Final | Passed | ||
| 05/14/2024 | COT - FCON - Fire - Final | Passed | ||
| 05/28/2024 | COT - HCME - Mechanical Final | Passed | ||
| 05/28/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 05/28/2024 | COT - LCME - Mechanical Progress | Passed | ||
| 05/28/2024 | COT - HCPL - Plumbing Progress | Passed | ||
| 05/28/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 05/28/2024 | COT - HCBU - Building Final | Passed | ||
| 05/28/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 05/28/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
| 05/28/2024 | COT - HCBU - TCO | Passed | All work complete; recommend issuing C of O. | |
| 05/30/2024 | ENGR Engineering Final | Passed |