Inspection Status: Not Ready
Inspection History: COT - HCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 03/14/2024 |
COT - HCEL - Electrical Intermediate |
|
Not Ready |
|
| 04/02/2024 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Basement and Level One. |
| 05/28/2024 |
COT - HCEL - Electrical Intermediate |
|
Passed |
|
| 10/18/2023 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
10/18/23: rough electric in restroom on level 1 approved. |
| 12/20/2023 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
12/20/23: Electrical panels in electrical room are being pulled in from SES Gear. Will issue ECO Clearance so TEP can connect transformer to SES. |