Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCBU - Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/05/2024 | COT - HCBU - Framing | Passed | ||
| 05/11/2023 | COT - HCBU - Framing | Canceled | ||
| 06/20/2023 | COT - HCBU - Framing | Partial Pass | call Chris Leon 520-468-8511 is ok with same day fee | |
| 06/23/2023 | COT - HCBU - Framing | Partial Pass | 6-23-23: Basement complete. | |
| 07/31/2023 | COT - HCBU - Framing | Partial Pass | Wanted masonry pre-grout. 6-20-23: East half of basement. 6-23-23: Basement complete. 7/31/23: framing & floor deck for east half of 2nd floor approved. |
|
| 08/09/2023 | COT - HCBU - Framing | Partial Pass | March 30th: east half of basement slab approved to pour 4-4-23: Stem wall for elevator pit. 4-11-23: Basement walls; East half of South wall and South half of East wall. 4-18-23: North half of East wall. 4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete. 8/9/23: 1st floor framing for west half, 2nd floor deck for pre-slab at west half. |
|
| 08/31/2023 | COT - HCBU - Framing | Partial Pass | Wanted masonry pre-grout. 6-20-23: East half of basement. 6-23-23: Basement complete. 7/31/23: framing & floor deck for east half of 2nd floor approved. March 30th: east half of basement slab approved to pour 4-4-23: Stem wall for elevator pit. 4-11-23: Basement walls; East half of South wall and South half of East wall. 4-18-23: North half of East wall. 4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete. 8/9/23: 1st floor framing for west half, 2nd floor deck for pre-slab at west half. 8/31/23: 2nd floor framing approved |