Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCBU - Building Progress
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/14/2023 | COT - HCBU - Building Progress | Passed | ||
| 03/07/2024 | COT - HCBU - Building Progress | Passed | Roof framing. | |
| COT - HCBU - Building Progress | Partial Pass | 3-24-23: Floor for elevator pit. | ||
| 03/30/2023 | COT - HCBU - Building Progress | Partial Pass | March 30th: east half of basement slab approved to pour | |
| 04/04/2023 | COT - HCBU - Building Progress | Partial Pass | 4-4-23: Stem wall for elevator pit. | |
| 04/11/2023 | COT - HCBU - Building Progress | Partial Pass | 4-11-23: Basement walls; East half of South wall and South half of East wall. | |
| 04/18/2023 | COT - HCBU - Building Progress | Partial Pass | 4-18-23: North half of East wall. | |
| 04/19/2023 | COT - HCBU - Building Progress | Partial Pass | 4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete. | |
| 07/28/2023 | COT - HCBU - Building Progress | Canceled | ||
| 08/09/2023 | COT - HCBU - Building Progress | Partial Pass | March 30th: east half of basement slab approved to pour 4-4-23: Stem wall for elevator pit. 4-11-23: Basement walls; East half of South wall and South half of East wall. 4-18-23: North half of East wall. 4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete. 8/9/23: 1st floor framing for west half, 2nd floor deck for pre-slab at west half. |
|
| 09/06/2023 | COT - HCBU - Building Progress | Partial Pass | East half of third floor rebar along with wire mesh per key notes 31 and 32 page S3.3 okay for concrete placement. 9/6/2023 | |
| 09/08/2023 | COT - HCBU - Building Progress | Partial Pass | March 30th: east half of basement slab approved to pour 4-4-23: Stem wall for elevator pit. 4-11-23: Basement walls; East half of South wall and South half of East wall. 4-18-23: North half of East wall. 4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete. 8/9/23: 1st floor framing for west half, 2nd floor deck for pre-slab at west half. East half of third floor rebar along with wire mesh per key notes 31 and 32 page S3.3 okay for concrete placement. 9/6/2023 9/8/23: 3rd floor deck, west half approved. |