Permit: T22CM06380

Parcel: 13316030C

Inspection Status: Passed

Inspection History: COT - HCBU - Building Progress

Date Description Inspector Results Comments
02/14/2023 COT - HCBU - Building Progress Passed
03/07/2024 COT - HCBU - Building Progress Passed Roof framing.
COT - HCBU - Building Progress Partial Pass 3-24-23: Floor for elevator pit.
03/30/2023 COT - HCBU - Building Progress Partial Pass March 30th: east half of basement slab approved to pour
04/04/2023 COT - HCBU - Building Progress Partial Pass 4-4-23: Stem wall for elevator pit.
04/11/2023 COT - HCBU - Building Progress Partial Pass 4-11-23: Basement walls; East half of South wall and South half of East wall.
04/18/2023 COT - HCBU - Building Progress Partial Pass 4-18-23: North half of East wall.
04/19/2023 COT - HCBU - Building Progress Partial Pass 4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete.
07/28/2023 COT - HCBU - Building Progress Canceled
08/09/2023 COT - HCBU - Building Progress Partial Pass March 30th: east half of basement slab approved to pour

4-4-23: Stem wall for elevator pit.

4-11-23: Basement walls; East half of South wall and South half of East wall.

4-18-23: North half of East wall.

4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete.

8/9/23: 1st floor framing for west half, 2nd floor deck for pre-slab at west half.
09/06/2023 COT - HCBU - Building Progress Partial Pass East half of third floor rebar along with wire mesh per key notes 31 and 32 page S3.3 okay for concrete placement. 9/6/2023
09/08/2023 COT - HCBU - Building Progress Partial Pass March 30th: east half of basement slab approved to pour

4-4-23: Stem wall for elevator pit.

4-11-23: Basement walls; East half of South wall and South half of East wall.

4-18-23: North half of East wall.

4-19-23: Rebar reinforcement for floor slab and basement walls on west half of building is complete. Okay to pour concrete.

8/9/23: 1st floor framing for west half, 2nd floor deck for pre-slab at west half.

East half of third floor rebar along with wire mesh per key notes 31 and 32 page S3.3 okay for concrete placement. 9/6/2023

9/8/23: 3rd floor deck, west half approved.