Permit: T22CM05039
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
5225 E SPEEDWAY BL
Address NEW:
5225 E SPEEDWAY BL
Apply Date:
07/05/2022
Applicant:
Description:
The Proposed project is for a new drive thru car wash facility and exterior vacuum arches covered wi
Permit Reviews
Permit Number - T22CM05039
Permit Status: Complete
Permit Description: The Proposed project is for a new drive thru car wash facility and exterior vacuum arches covered wi
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/05/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/30/2022 | COMPLETED |
| 09/28/2022 | RESUBMITTAL | 10/13/2022 | COMPLETED |
| 07/07/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/07/2023 | REQUIRES RESUBMIT |
| 07/07/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/07/2023 | REQUIRES RESUBMIT |
| 10/16/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/19/2023 | APPROVED |
| 07/10/2023 | COMMERCIAL REVIEW - FULL v.3 | 08/08/2023 | APPROVED |
| 11/09/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/28/2022 | REQUIRES RESUBMIT |
| 01/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/10/2024 | APPROVED |
| 01/04/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/10/2023 | APPROVED |
Conditions
Permit Number - T22CM05039
Permit Status: Complete
Permit Description: The Proposed project is for a new drive thru car wash facility and exterior vacuum arches covered wi
| Date | Description | Comments |
|---|---|---|
| 10/12/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 10/12/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 10/12/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 10/12/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 10/12/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 10/12/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 10/12/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 10/12/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 10/12/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
| 01/10/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 01/10/2023 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05039
Permite Description: The Proposed project is for a new drive thru car wash facility and exterior vacuum arches covered wi
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/12/2022 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | {Activity date: 10/12/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECITON.} |
| 04/20/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | 4/20/2023: car wash will not be using natural gas at site. |
| 06/27/2023 | COT - HCEL - Electrical Underground | N/A | Canceled | |
| 05/11/2023 | zzzPDSD Building Division - Site Excavation/Layout/Rebar | N/A | Canceled | 5-11-23: Wanted Masonry pre-grout. |
| 06/26/2023 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 6-26-23: 4th lift, Building. |
| 09/28/2023 | COT - HCEL - Grounding/Bonding | N/A | Not Ready | |
| 09/28/2023 | COT - HCEL - Outdoor Lighting | N/A | Not Ready | |
| 10/11/2023 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 10/05/2023 | COT - HCME - Mechanical Final | N/A | Re-inspection required | 10/5/23: no access to roof equipment. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05039
Permit Description: The Proposed project is for a new drive thru car wash facility and exterior vacuum arches covered wi
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2023 | COT - HCPL - Rough Soil | Passed | ||
| 06/10/2023 | Building Inspection - Outside Normal Hours Building Inspection | Passed | 6/10/23: 2" water line needs to be ran to meter by city. connection to meter with back-flow preventer. ok to backfill | |
| 06/10/2023 | COT - LCPL - Yard Water Line | Passed | 6/10/23: 2" water line needs to be ran to meter by city. connection to meter with back-flow preventer. ok to backfill | |
| 07/25/2023 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 07/28/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
| 09/07/2023 | COT - HCPL - Sewer | Passed | Stub out 90' of sewer line to man hole. Okay to backfill. Shading required. 9/7/2023 | |
| 09/22/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | 9/22/23: office above ceiling approved. | |
| 09/22/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 09/27/2023 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 09/27/2023 | COT - HCPL - Plumbing Final | Passed | ||
| 09/28/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 09/28/2023 | COT - HCBU - Roof Nailing | Passed | ||
| 09/28/2023 | COT - HCEL - Electrical Underground | Passed | ||
| 09/28/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
| 09/28/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 09/28/2023 | COT - LCBU - Building Progress | Passed | ||
| 09/28/2023 | COT - LCBU - Framing | Passed | ||
| 09/28/2023 | COT - HCBU - Preslab | Passed | ||
| 09/28/2023 | zzzPDSD Building Division - Site Excavation/Layout/Rebar | Passed | ||
| 09/28/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
| 09/28/2023 | COT - HCBU - Masonry Pregrout | Passed | ||
| 09/28/2023 | COT - HCBU - Framing | Passed | ||
| 10/02/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
| 10/02/2023 | COT - HCEL - Outdoor Lighting | Passed | ||
| 10/11/2023 | COT - FCON - Fire - Final | Passed | ||
| 10/11/2023 | COT - HCBU - Building Final | Passed | ||
| 10/11/2023 | COT - HCEL - Electrical Final | Passed | ||
| 10/11/2023 | COT - HCME - Mechanical Final | Passed |