Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM00359
Permit Details
Apply Date:
01/18/2022
Applicant:
Brandon Filipp
Description:
Addition to Assisted Living Facility
Permit Reviews
Permit Number - T22CM00359
Permit Status: Complete
Permit Description: Addition to Assisted Living Facility
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/18/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 07/06/2022 | COMPLETED |
11/17/2023 | COMMERCIAL REVIEW - FULL v.1 | 11/20/2023 | REQUIRES RESUBMIT |
11/16/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/17/2023 | APPROVED |
11/20/2023 | RESTAMP - COMMERCIAL v.1 | 11/21/2023 | APPROVED |
04/20/2023 | COMMERCIAL REVIEW - FULL v.1 | 11/07/2023 | APPROVED |
11/08/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/16/2023 | REQUIRES RESUBMIT |
11/20/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/20/2023 | APPROVED |
11/07/2023 | RESTAMP - COMMERCIAL v.1 | 11/08/2023 | APPROVED |
Conditions
Permit Number - T22CM00359
Permit Status: Complete
Permit Description: Addition to Assisted Living Facility
Date | Description | Comments |
---|---|---|
11/07/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
06/27/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
06/27/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
06/27/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
06/27/2022 | SHOP DRAWINGS REQUIRED FOR PREFABRICATED TRUSSES. | |
11/07/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM00359
Permite Description: Addition to Assisted Living Facility
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/20/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | 3-20-23: N/A. |
03/20/2023 | COT - LCBU - Framing | N/A | Not Ready | |
03/10/2023 | COT - BULD - SWG Clearance | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
COT - FCON - Alarm - Final | N/A | Not Ready | Waiting for sub contractor to schedule Alarm Final. | |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Rough Soil | N/A | Not Ready | |
10/16/2023 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | 10/16/23: wrap exterior water lines with R-3 insulation and UV resistant tape, all exterior outlets required to be WR, remove ALL construction debris & materials from interior and exterior on site, type all panel schedules, flush floor drain at dining room, install all adjustable hand shower on a vertical bar per 608., Fire Dept and Site Engineering have not signed off. INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION. |
10/16/2023 | COT - LCME - Mechanical Final | N/A | Re-inspection required | 10/16/23: wrap exterior water lines with R-3 insulation and UV resistant tape, all exterior outlets required to be WR, remove ALL construction debris & materials from interior and exterior on site, type all panel schedules, flush floor drain at dining room, install all adjustable hand shower on a vertical bar per 608., Fire Dept and Site Engineering have not signed off. INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION. |
10/16/2023 | COT - LCEL - Electrical Final | N/A | Re-inspection required | 10/16/23: wrap exterior water lines with R-3 insulation and UV resistant tape, all exterior outlets required to be WR, remove ALL construction debris & materials from interior and exterior on site, type all panel schedules, flush floor drain at dining room, install all adjustable hand shower on a vertical bar per 608., Fire Dept and Site Engineering have not signed off. INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION. |
05/23/2023 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 5-23-23: Southwest wing. |
11/06/2023 | COT - LCBU - Building Final | N/A | Partial Pass | 11/6/23: OK to issue TCO level 4. |
10/16/2023 | COT - LCEL - Outdoor Lighting | N/A | Re-inspection required | 10/16/23: wrap exterior water lines with R-3 insulation and UV resistant tape, all exterior outlets required to be WR, remove ALL construction debris & materials from interior and exterior on site, type all panel schedules, flush floor drain at dining room, install all adjustable hand shower on a vertical bar per 608., Fire Dept and Site Engineering have not signed off. INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM00359
Permit Description: Addition to Assisted Living Facility
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/22/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 09/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
10/05/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/05/2022 | COT - LCBU - Preslab | Passed | {Activity date: 10/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/05/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 10/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
02/08/2023 | COT - LCBU - Roof Nailing | Passed | ||
03/20/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
03/20/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
04/26/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
04/26/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
04/26/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
04/26/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
04/26/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
04/26/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
04/26/2023 | COT - LCBU - Framing | Passed | ||
04/26/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
04/26/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
08/21/2023 | BULD - Electrical Clearance | Passed | Approved secondary conductors to building, ECO Clearance was called into TEP at 3:22 | |
10/31/2023 | COT - BULD - SWG Clearance | Passed | 10/31/23: SWG clearance issued. | |
11/06/2023 | COT - FCON - Fire - Final | Passed | ||
11/08/2023 | COT - FCON - Alarm - Final | Passed | ||
11/08/2023 | COT - FCON - Sprinkler - Final | Passed | ||
12/12/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | 12/12/23: fire walls are to schedule okay to texture and paint gypsum board | |
12/22/2023 | COT - LCPL - Rough Soil | Passed | ||
12/22/2023 | COT - LCPL - Plumbing Final | Passed | ||
12/22/2023 | COT - LCPL - Medical Gas Preconstruction Mtg | Passed | ||
12/22/2023 | COT - LCME - Mechanical Final | Passed | ||
12/22/2023 | COT - LCEL - Electrical Final | Passed | ||
12/22/2023 | COT - LCEL - Construction Power | Passed | n/a | |
12/22/2023 | COT - LCBU - Sustainability | Passed | ||
12/22/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
12/22/2023 | COT - LCBU - Building Final | Passed | 12/21/2023 approved for CofO. | |
12/22/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
12/22/2023 | COT - LCPL - Sewer | Passed |