Permit Details

Status:
Complete
Type:
Commercial Building
Address:
250 S VOZACK LN
Apply Date:
01/18/2022
Applicant:
Brandon Filipp
Description:
Addition to Assisted Living Facility

Permit Reviews

Permit Number - T22CM00359
Permit Status: Complete
Permit Description: Addition to Assisted Living Facility
Start Date Submittal Complete Date Status  
01/18/2022 3RD PARTY REVIEW - COMMERCIAL TI 07/06/2022 COMPLETED Review Details
11/17/2023 COMMERCIAL REVIEW - FULL v.1 11/20/2023 REQUIRES RESUBMIT Review Details
11/16/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 11/17/2023 APPROVED Review Details
11/20/2023 RESTAMP - COMMERCIAL v.1 11/21/2023 APPROVED Review Details
04/20/2023 COMMERCIAL REVIEW - FULL v.1 11/07/2023 APPROVED Review Details
11/08/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/16/2023 REQUIRES RESUBMIT Review Details
11/20/2023 COMMERCIAL REVIEW - FULL v.2 11/20/2023 APPROVED Review Details
11/07/2023 RESTAMP - COMMERCIAL v.1 11/08/2023 APPROVED Review Details

Conditions

Permit Number - T22CM00359
Permit Status: Complete
Permit Description: Addition to Assisted Living Facility
Date Description Comments
11/07/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
06/27/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
06/27/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
06/27/2022 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
06/27/2022 SHOP DRAWINGS REQUIRED FOR PREFABRICATED TRUSSES.
11/07/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM00359
Permite Description: Addition to Assisted Living Facility
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
03/20/2023 COT - LCBU - Firewall/Fire Barrier/Firestop N/A Not Applicable 3-20-23: N/A.
03/20/2023 COT - LCBU - Framing N/A Not Ready
03/10/2023 COT - BULD - SWG Clearance N/A Not Ready
10/26/2022 COT - FCON - Fire - Final N/A Not Ready
COT - FCON - Alarm - Final N/A Not Ready Waiting for sub contractor to schedule Alarm Final.
10/26/2022 COT - FCON - Sprinkler - Final N/A Not Ready
10/26/2022 COT - LCPL - Rough Soil N/A Not Ready
10/16/2023 COT - LCPL - Plumbing Final N/A Re-inspection required 10/16/23: wrap exterior water lines with R-3 insulation and UV resistant tape, all exterior outlets required to be WR, remove ALL construction debris & materials from interior and exterior on site, type all panel schedules, flush floor drain at dining room, install all adjustable hand shower on a vertical bar per 608., Fire Dept and Site Engineering have not signed off. INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION.
10/16/2023 COT - LCME - Mechanical Final N/A Re-inspection required 10/16/23: wrap exterior water lines with R-3 insulation and UV resistant tape, all exterior outlets required to be WR, remove ALL construction debris & materials from interior and exterior on site, type all panel schedules, flush floor drain at dining room, install all adjustable hand shower on a vertical bar per 608., Fire Dept and Site Engineering have not signed off. INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION.
10/16/2023 COT - LCEL - Electrical Final N/A Re-inspection required 10/16/23: wrap exterior water lines with R-3 insulation and UV resistant tape, all exterior outlets required to be WR, remove ALL construction debris & materials from interior and exterior on site, type all panel schedules, flush floor drain at dining room, install all adjustable hand shower on a vertical bar per 608., Fire Dept and Site Engineering have not signed off. INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION.
05/23/2023 COT - HCBU - Interior Shear Bracing N/A Partial Pass 5-23-23: Southwest wing.
11/06/2023 COT - LCBU - Building Final N/A Partial Pass 11/6/23: OK to issue TCO level 4.
10/16/2023 COT - LCEL - Outdoor Lighting N/A Re-inspection required 10/16/23: wrap exterior water lines with R-3 insulation and UV resistant tape, all exterior outlets required to be WR, remove ALL construction debris & materials from interior and exterior on site, type all panel schedules, flush floor drain at dining room, install all adjustable hand shower on a vertical bar per 608., Fire Dept and Site Engineering have not signed off. INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM00359
Permit Description: Addition to Assisted Living Facility
Total Completed Inspections - 33
Date Description Inspector Results Comments
09/22/2022 COT - LCEL - Electrical Underground Passed {Activity date: 09/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
10/05/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 10/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
10/05/2022 COT - LCBU - Preslab Passed {Activity date: 10/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
10/05/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 10/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
02/08/2023 COT - LCBU - Roof Nailing Passed
03/20/2023 COT - HCBU - Exterior Clips/Sheathing Passed
03/20/2023 COT - LCBU - Exterior Clips/Sheathing Passed
04/26/2023 COT - LCPL - Plumbing Intermediate Passed
04/26/2023 COT - LCEL - Electrical Above Ceiling Passed
04/26/2023 COT - LCPL - Plumbing Above Ceiling Passed
04/26/2023 COT - LCME - Mechanical Intermediate Passed
04/26/2023 COT - LCEL - Electrical Intermediate Passed
04/26/2023 COT - LCME - Mechanical Above Ceiling Passed
04/26/2023 COT - LCBU - Framing Passed
04/26/2023 COT - LCPL - Gas Pressure Test Passed
04/26/2023 COT - LCBU - Building Above Ceiling Passed
08/21/2023 BULD - Electrical Clearance Passed Approved secondary conductors to building, ECO Clearance was called into TEP at 3:22
10/31/2023 COT - BULD - SWG Clearance Passed 10/31/23: SWG clearance issued.
11/06/2023 COT - FCON - Fire - Final Passed
11/08/2023 COT - FCON - Alarm - Final Passed
11/08/2023 COT - FCON - Sprinkler - Final Passed
12/12/2023 COT - HCBU - Firewall/Fire Barrier/Firestop Passed 12/12/23: fire walls are to schedule okay to texture and paint gypsum board
12/22/2023 COT - LCPL - Rough Soil Passed
12/22/2023 COT - LCPL - Plumbing Final Passed
12/22/2023 COT - LCPL - Medical Gas Preconstruction Mtg Passed
12/22/2023 COT - LCME - Mechanical Final Passed
12/22/2023 COT - LCEL - Electrical Final Passed
12/22/2023 COT - LCEL - Construction Power Passed n/a
12/22/2023 COT - LCBU - Sustainability Passed
12/22/2023 COT - HCBU - Interior Shear Bracing Passed
12/22/2023 COT - LCBU - Building Final Passed 12/21/2023 approved for CofO.
12/22/2023 COT - LCEL - Outdoor Lighting Passed
12/22/2023 COT - LCPL - Sewer Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
CALCS_STRUCT1 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
CALCS_STRUCT2 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
CALC_MECH 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
ENERGY_ENVELOP 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
ENERGY_MECH 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PSA FOR STANTEC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-TUC_23_096_T22CM00359_TUCSON_ASSISTED_LIVING_RETREAT_ADDITION_REVISION_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
PATTISON ENGINEERING SPECIAL INSPECTION CERTIFICATE-2023-11-16_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-STANTEC_APPROVE_PLANS_V1.PDF DOCUMENTS VIEW
CONS-TUCSON ASSISTED LIVING REATREAT_REV3_V1.PDF DOCUMENTS VIEW
LETTER_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
CALC_MECH.PDF DOCUMENTS VIEW
CALCS_STRUCT1.PDF DOCUMENTS VIEW
CALCS_STRUCT2.PDF DOCUMENTS VIEW
ENERGY_ENVELOP.PDF DOCUMENTS VIEW
ENERGY_MECH.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
PSA FOR STANTEC.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
ENERGY_ENVELOP.PDF DOCUMENTS VIEW
CALCS_STRUCT2.PDF DOCUMENTS VIEW
CALCS_STRUCT1.PDF DOCUMENTS VIEW
CALC_MECH.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
ENERGY_MECH.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW
SIC.PDF DOCUMENTS VIEW
PSA FOR STANTEC.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW