Permit: T21CM05081
Permit Details
Apply Date:
06/17/2021
Applicant:
James Wright
Description:
HANGAR BAY FACILITY WITH OFFICES AND SHOP SPACE. SINGLE STORY PRE-FABRICATED BUILDING, INSULATED ST
Permit Reviews
Permit Number - T21CM05081
Permit Status: Complete
Permit Description: HANGAR BAY FACILITY WITH OFFICES AND SHOP SPACE. SINGLE STORY PRE-FABRICATED BUILDING, INSULATED ST
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/24/2022 | REVISION - - 1ST | 03/08/2022 | COMPLETED |
06/17/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/29/2021 | COMPLETED |
10/07/2021 | RESUBMITTAL | 10/22/2021 | COMPLETED |
11/10/2021 | RESUBMITTAL | 11/29/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM05081
Permite Description: HANGAR BAY FACILITY WITH OFFICES AND SHOP SPACE. SINGLE STORY PRE-FABRICATED BUILDING, INSULATED ST
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
03/16/2023 | COT - LCME - Mechanical Final | N/A | Partial Pass | awaiting air balance report |
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Sewer | N/A | Not Ready | |
04/27/2023 | COT - LCPL - Plumbing Roof Drains | N/A | Not Applicable | |
10/26/2022 | COT - LCEL - Outdoor Lighting | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM05081
Permit Description: HANGAR BAY FACILITY WITH OFFICES AND SHOP SPACE. SINGLE STORY PRE-FABRICATED BUILDING, INSULATED ST
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/27/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 12/27/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - CODE TMPP} | |
03/17/2022 | COT - LCBU - Preslab | Passed | {Activity date: 03/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
03/18/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 03/18/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved, Grounding conductor installed and attached to rebar footing.} | |
04/27/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 04/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved, Oil Interceptor and waste line installed and tested. Ok to backfill.} ; {Activity date: 03/03/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, Drain, waste, vent & Oil lines under foundation installed and tested ok to backfill progress areas. } ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, rough soil for mens and woman’s restrooms and floor sink at janitors room, okay to backfill progress areas.} ; {Activity date: 02/23/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, rough soil for Uni sex bathroom ok to backfill progress areas.} ; {Activity date: 02/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 4” grease main line installed and tested under foundation for future trench drains ok to backfill progress areas. } ; {Activity date: 02/08/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, 4” wasteline installed & tested under foundation heading East to West. Inspection required for branch lines at a further time.} |
|
06/13/2022 | COT - LCPL - Backwater Valve | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
07/12/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 07/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 06/30/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, no inspection required today see previous notes.} ; {Activity date: 04/05/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, underground conduit raceways for future evaporate coolers ok to backfill progress areas.} ; {Activity date: 03/31/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, underground conduits installed for site lighting ok to backfill progress areas. } ; {Activity date: 03/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, underground conduits installed for site lighting ok to backfill progress areas} ; {Activity date: 03/18/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, conduit raceways for site lighting ok to backfill progress areas.} ; {Activity date: 03/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for exterior communication lines from Gridline 6 heading south toward communication vault, okay to backfill} ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, branch lines from electric room to floor box, and from panel H3,L2 to aircraft receptacle, okay to backfill progress areas} ; {Activity date: 02/11/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, branch raceways under foundation ok to proceed with backfill.} ; {Activity date: 02/10/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, Branch raceways installed under foundation ok to backfill progress area @ Electrical room location.} ; {Activity date: 01/28/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 2-2 1/2” Raceways installed under foundation from Electrical room location to panels L3, H2 ok to backfill progress areas.} ; {Activity date: 01/26/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 2-4” Conduits under foundation from SES location to Electrical distribution room ok to backfill progress areas. } |
|
07/12/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 07/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 06/29/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, progress areas ok to proceed.} ; {Activity date: 06/24/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial the following rooms ok to tape progress areas (112,120,117,121,116,113).} ; {Activity date: 06/03/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, interior screw inspection for one side top out ok to proceed. } ; {Activity date: 06/02/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - correction required, install more Sheetrock screws in the field & edges.} |
|
08/12/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 08/12/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 06/13/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - PARTIAL, Electrical in wall inspection from GL 1-4,A-E ok to proceed} | |
08/12/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 08/12/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
08/12/2022 | COT - LCME - Mechanical Progress | Passed | {Activity date: 08/12/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
08/12/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 08/12/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/20/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Structural steel and bolt inspection complete. Ok to proceed with exterior sheathing.} | |
08/19/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - CODE} | |
09/06/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 07/27/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 07/26/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} ; {Activity date: 07/13/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, hard lid locations ok to proceed with Sheetrock. Mechanical ducts are all sealed and ok to insulate. } |
|
09/06/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 07/27/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 07/26/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} | |
09/06/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/19/2022; Status: Denied; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Denied. Not under test.} ; {Activity date: 07/27/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Not Ready} ; {Activity date: 07/26/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} | |
09/06/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
10/18/2022 | COT - LCPL - Gas Pressure Test | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
10/18/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
10/18/2022 | COT - LCBU - Sustainability | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
02/10/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
02/10/2023 | BULD - Electrical Clearance | Passed | ||
03/08/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
03/16/2023 | COT - LCEL - Electrical Final | Passed | ||
03/24/2023 | COT - FCON - Sprinkler - Final | Passed | ||
03/24/2023 | COT - FCON - Alarm - Final | Passed | ||
03/30/2023 | COT - LCPL - Plumbing Final | Passed | ||
03/30/2023 | COT - LCBU - Building Final | Passed | ||
04/20/2023 | COT - FCON - Fire - Final | Passed | ||
04/27/2023 | COT - LCME - Mechanical Final | Passed | ||
04/27/2023 | COT - LCBU - Framing | Passed | ||
04/27/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
04/27/2023 | COT - LCPL - Sewer | Passed | ||
04/27/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
04/27/2023 | COT - LCBU - Roof Nailing | Passed | ||
04/27/2023 | COT - LCEL - Outdoor Lighting | Passed |