Inspection Status: Passed
Inspection History: COT - LCPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 04/27/2022 |
COT - LCPL - Rough Soil |
DMUNIZ |
Approved |
Entered by VVERA1 - Approved, Oil Interceptor and waste line installed and tested. Ok to backfill. |
| 03/03/2022 |
COT - LCPL - Rough Soil |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, Drain, waste, vent & Oil lines under foundation installed and tested ok to backfill progress areas.
|
| 03/01/2022 |
COT - LCPL - Rough Soil |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial, rough soil for mens and woman’s restrooms and floor sink at janitors room, okay to backfill progress areas. |
| 02/23/2022 |
COT - LCPL - Rough Soil |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, rough soil for Uni sex bathroom ok to backfill progress areas. |
| 02/09/2022 |
COT - LCPL - Rough Soil |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, 4” grease main line installed and tested under foundation for future trench drains ok to backfill progress areas.
|
| 02/08/2022 |
COT - LCPL - Rough Soil |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, 4” wasteline installed & tested under foundation heading East to West. Inspection required for branch lines at a further time. |