Inspection Status: Passed
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 07/12/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Approved |
Entered by NGARCIA3 - Approved |
| 06/30/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, no inspection required today see previous notes. |
| 04/05/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, underground conduit raceways for future evaporate coolers ok to backfill progress areas. |
| 03/31/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, underground conduits installed for site lighting ok to backfill progress areas.
|
| 03/25/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, underground conduits installed for site lighting ok to backfill progress areas |
| 03/18/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, conduit raceways for site lighting ok to backfill progress areas. |
| 03/14/2022 |
COT - LCEL - Electrical Underground |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial for exterior communication lines from Gridline 6 heading south toward communication vault, okay to backfill |
| 03/01/2022 |
COT - LCEL - Electrical Underground |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial, branch lines from electric room to floor box, and from panel H3,L2 to aircraft receptacle, okay to backfill progress areas |
| 02/11/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, branch raceways under foundation ok to proceed with backfill. |
| 02/10/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, Branch raceways installed under foundation ok to backfill progress area @ Electrical room location. |
| 01/28/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial,
2-2 1/2” Raceways installed under foundation from Electrical room location to panels L3, H2 ok to backfill progress areas. |
| 01/26/2022 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, 2-4” Conduits under foundation from SES location to Electrical distribution room ok to backfill progress areas.
|