Inspection Status: Not Ready
Inspection History: COT - LCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCEL - Electrical Intermediate |
|
Not Ready |
|
| 06/29/2022 |
COT - LCEL - Electrical Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, West exterior wall ok to insulate. Secondary conduit from existing transformer to new transformer ok to backfill.
|
| 06/17/2022 |
COT - LCEL - Electrical Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, see previous notes |
| 06/10/2022 |
COT - LCEL - Electrical Intermediate |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - PARTIAL, Electrical in walls for south hangar ok to proceed. |
| 06/03/2022 |
COT - LCEL - Electrical Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, NORTH & SOUTH exterior walls ok to place insulation.
|
| 06/02/2022 |
COT - LCEL - Electrical Intermediate |
DMUNIZ |
Correction Required |
Entered by NGARCIA3 - corrections required, Secure MC cable 12” from every box and every 4’ where needed. |
| 12/27/2021 |
COT - LCEL - Electrical Intermediate |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial,clear TEP TMPP for construction trailer. |
| 02/10/2023 |
COT - LCEL - Electrical Intermediate |
|
Passed |
|