Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
5050 E VALENCIA RD
Apply Date:
06/11/2021
Applicant:
Description:
New Construction

Permit Reviews

Permit Number - T21CM04901
Permit Status: Complete
Permit Description: New Construction
Start Date Submittal Complete Date Status  
01/21/2022 RESUBMITTAL 02/03/2022 COMPLETED Review Details
03/18/2022 RESUBMITTAL 04/01/2022 COMPLETED Review Details
04/28/2022 REVISION - - 1ST 06/14/2022 COMPLETED Review Details
06/11/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 07/20/2021 COMPLETED Review Details
06/23/2022 REVISION - - 1ST 07/18/2022 COMPLETED Review Details
07/30/2021 RESUBMITTAL 09/08/2021 COMPLETED Review Details
08/04/2022 REVISION - - 2ND 08/04/2022 COMPLETED Review Details
09/09/2021 RESUBMITTAL 10/19/2021 COMPLETED Review Details
11/01/2021 RESUBMITTAL 11/22/2021 COMPLETED Review Details
12/27/2021 RESUBMITTAL 01/10/2022 COMPLETED Review Details
03/01/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 03/06/2023 REQUIRES RESUBMIT Review Details
03/14/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.3 03/14/2023 APPROVED Review Details
01/23/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/01/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T21CM04901
Permit Status: Complete
Permit Description: New Construction
Date Description Comments
03/22/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
03/22/2022 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
04/01/2022 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
03/22/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/01/2022 This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm
03/22/2022 SHOP DRAWINGS REQUIRED FOR HOOD SUPRESSION
03/22/2022 SHOP DRAWINGS REQUIRED FOR WOOD TRUSSES
04/01/2022 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS.

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM04901
Permite Description: New Construction
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - LCBU - Framing N/A Not Ready
10/26/2022 COT - LCBU - Preslab N/A Not Ready
10/26/2022 COT - LCBU - Exterior Clips/Sheathing N/A Not Ready
10/26/2022 COT - LCPL - Yard Water Line N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready
10/26/2022 COT - LCEL - Electrical Above Ceiling N/A Not Ready
10/26/2022 COT - LCPL - Backwater Valve N/A Not Ready
02/01/2023 COT - HCBU - CofO N/A Not Ready Temp C of O issued level 4 in error. The public is not allowed to enter walk in or the drive thru for food.

Completed Inspections

Permit Status: Complete
Permit Number: T21CM04901
Permit Description: New Construction
Total Completed Inspections - 31
Date Description Inspector Results Comments
08/10/2022 COT - LCEL - Electrical Underground Passed {Activity date: 08/10/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 08/04/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, under foundation raceways installed.
} ; {Activity date: 07/21/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA}
09/01/2022 COT - LCBU - Roof Nailing Passed {Activity date: 09/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
09/09/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 09/09/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Rebar and electric at light poles.} ; {Activity date: 09/01/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
Partial pending new asbuilt drawing is submitted to Tucson P & D for 10 exterior light pole footings and base.} ; {Activity date: 08/04/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, interior footing ok for concrete placement.} ; {Activity date: 07/22/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - PARTIAL, Exterior continuous footings & columns ok for concrete placement.} ; {Activity date: 06/27/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} ; {Activity date: 06/23/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not ready,}
09/09/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 09/09/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Rebar and electric at light poles.}
09/16/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 09/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/15/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE
Nail plate NMC within 1 1/4" of edge of framing
KO’s missing}
09/16/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 09/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/15/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE
Incorrect nail plates over vents
Air-admittance valve concealed in wall}
09/19/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 09/19/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved. Ok to insulate hard duct.} ; {Activity date: 09/15/2022; Status: Not Applicable; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NA}
10/11/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 10/11/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Approved}
11/04/2022 COT - LCBU - Building Above Ceiling Passed
10/26/2022 COT - FCON - Alarm - Final Passed
10/26/2022 COT - FCON - Sprinkler - Final Passed
11/04/2022 COT - LCEL - Electrical Progress Passed For electrical power. The TEP clearance code is ECO.
01/12/2023 COT - LCME - Mechanical Final Passed
01/12/2023 COT - LCPL - Plumbing Final Passed
01/12/2023 COT - LCEL - Electrical Above Ceiling Passed
01/12/2023 COT - LCPL - Backwater Valve Passed
01/12/2023 COT - LCBU - Building Progress Passed
01/12/2023 COT - LCBU - Sustainability Passed
01/12/2023 COT - LCME - Mechanical Progress Passed
01/12/2023 COT - LCPL - Plumbing Roof Drains Passed
01/12/2023 COT - LCPL - Rough Soil Passed
01/12/2023 COT - FCON - Hood System - Final Passed
01/12/2023 COT - LCEL - Outdoor Lighting Passed
01/12/2023 COT - LCPL - Plumbing Above Ceiling Passed
01/12/2023 COT - LCPL - Sewer Passed
01/12/2023 COT - LCPL - Plumbing Progress Passed
01/12/2023 COT - LCME - Kitchen Hood Passed
01/20/2023 COT - LCBU - Building Final Passed building is complete ready for occupancy.
01/20/2023 COT - LCEL - Electrical Final Passed labels have been installed on electrical panels.
02/01/2023 COT - FCON - Fire - Final Passed
02/10/2023 COT - HCBU - CofO Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
SPECIAL_INSPECTION_CERTIFICATE_DARK SKY_V1.PDF DOCUMENTS VIEW
WHATABURGER VALENCIA RD, SIC-2023-01-18_V1 (5)-2023-03-14_V1.PDF DOCUMENTS VIEW
WHATABURGER 1280 TUSCON AZ TAB REPORT_V2.PDF DOCUMENTS VIEW
WHATABURGER AT 5050 W. VALENCIA RD - CAPTURE - CONTAINMENT REPORT_V1.PDF DOCUMENTS VIEW
23A0463_1 TURNER 01 20 2023 1620_V1.PDF DOCUMENTS VIEW
TCO T21CM04901.PDF DOCUMENTS VIEW
TCO T21CM4901.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
CO2 MONITORING.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
COMCHECK_ELECTRICAL.PDF DOCUMENTS VIEW
COMCHECK_ENVELOPE.PDF DOCUMENTS VIEW
COMCHECK_MECHANICAL.PDF DOCUMENTS VIEW
GENERAL CONTRACTOR LETTER.PDF DOCUMENTS VIEW
COMM SUBMITTAL REQUIREMENTS.PDF DOCUMENTS VIEW
GEOTECH REPORT.PDF DOCUMENTS VIEW
H&K HOODS UL SAMPLE LABEL.PDF DOCUMENTS VIEW
H&K UL LISTINGS FOR HOODS.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
REVISION NARRATIVE.PDF DOCUMENTS VIEW
REV2_ROOF CALCS.PDF DOCUMENTS VIEW
SPEC_FRY HOOD SIDE VIEW ZERO CLEARANCE.PDF DOCUMENTS VIEW
SPEC_DOUBLE SIDED 6' GRILL HOOD.PDF DOCUMENTS VIEW
SPEC_WALL MOUNTED HOOD TEN BANK.PDF DOCUMENTS VIEW
S-ROOF LAYOUT REV2.PDF DOCUMENTS VIEW
STATE OF AZ - BOND EXEMPTION CERTIFICATE.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
WTB1496 DOUBLE SIDE HOOD FOR 6FT GRILLS 9 FT CEILING.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW
REV1_PLANS.PDF CONSTRPLANS VIEW