Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
12/29/2020
Applicant:
Description:
Proposed construction of 229,320 sf shell building and associated site work

Permit Reviews

Permit Number - T20CM09215
Permit Status: Complete
Permit Description: Proposed construction of 229,320 sf shell building and associated site work
Start Date Submittal Complete Date Status  
01/18/2022 REVISION - - 1ST 01/31/2022 COMPLETED Review Details
02/22/2021 RESUBMITTAL 03/22/2021 COMPLETED Review Details
03/30/2021 RESUBMITTAL 04/15/2021 COMPLETED Review Details
04/23/2022 REVISION - - 2ND 05/26/2022 COMPLETED Review Details
06/03/2022 REVISION - - 2ND 06/21/2022 COMPLETED Review Details
09/01/2022 REVISION - - 2ND 09/05/2022 COMPLETED Review Details
12/29/2020 COMMERCIAL - NEW 02/04/2021 COMPLETED Review Details
03/07/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/09/2023 APPROVED Review Details

Conditions

Permit Number - T20CM09215
Permit Status: Complete
Permit Description: Proposed construction of 229,320 sf shell building and associated site work
Date Description Comments
01/21/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
01/21/2021 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
01/21/2021 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
01/21/2021 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
01/21/2021 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
01/21/2021 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
01/21/2021 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
01/21/2021 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
01/21/2021 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
01/21/2021 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM09215
Permite Description: Proposed construction of 229,320 sf shell building and associated site work
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - HCBU - Preslab N/A Not Ready
10/26/2022 COT - HCEL - Electrical Intermediate N/A Not Ready
10/26/2022 COT - HCBU - Excavation/Rebar/Zoning N/A Not Ready
10/26/2022 COT - HCBU - Framing N/A Not Ready
10/26/2022 COT - HCEL - Grounding/Bonding N/A Not Ready
10/26/2022 COT - HCBU - Interior Shear Bracing N/A Not Ready
10/26/2022 COT - HCEL - Electrical Underground N/A Not Ready
10/26/2022 COT - HCBU - Building Progress N/A Not Ready
10/26/2022 COT - FCON - Alarm - Final N/A Not Ready
10/26/2022 COT - HCPL - Plumbing Final N/A Not Ready
10/26/2022 COT - FCON - Underground Flush N/A Not Ready
01/13/2023 COT - FCON - Sprinkler - Final N/A Partial Pass CG: The north two risers and the south two risers flow switches need to activate the water flow bell.
01/20/2023 COT - FCON - Fire - Final N/A Partial Pass Exit lighting on east side of building (4) lights. FDC caps, sprinkler coverage under mezzanine in electrical room. OK to obtain TCO

Completed Inspections

Permit Status: Complete
Permit Number: T20CM09215
Permit Description: Proposed construction of 229,320 sf shell building and associated site work
Total Completed Inspections - 36
Date Description Inspector Results Comments
03/18/2022 COT - HCPL - Sewer Passed {Activity date: 03/18/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved
Negative vacuum test for Manhole 4 PASS.
Negative vacuum test for Manhole 5 PASS} ; {Activity date: 03/16/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - partial, Air test for main line from Manhole 4-5 PASS, Mandril PASS} ; {Activity date: 03/15/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Correction for mainline from manhole 4-5 complete and ok to backfill.

} ; {Activity date: 03/10/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, no inspection today see previous notes

} ; {Activity date: 03/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial ,Air pressure test and Mandril results For Private Sewer Main. (Manhole 5 to public manhole, air test PASS, Mandril PASS) (Manhole 5-4 air test PASS, Mandril FAIL correction required), (Manhole 4-3 Air test PASS, Mandril PASS),(Manhole 3-2 Air test PASS, Mandril PASS),( Manhole 2-1 air test PASS, Mandril PASS)} ; {Activity date: 03/07/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, Sewer main from public manhole to private manhole ok to backfill progress areas.} ; {Activity date: 03/02/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, sewer main from MH1-MH2 ok to backfill progress areas.

} ; {Activity date: 02/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, 8” main from man hole 2-3 ok to backfill progress areas.

} ; {Activity date: 02/18/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Inspection of 8” main line from manhole 4-5 ok to backfill progress areas}
07/01/2022 COT - HCPL - Rough Soil Passed {Activity date: 07/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/07/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - partial, Sewer main from public manhole to private manhole ok to backfill progress areas.
} ; {Activity date: 03/02/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, sewer main from MH1-MH2 ok to backfill progress areas.} ; {Activity date: 02/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, 8” main from man hole 2-3 ok to backfill progress areas.} ; {Activity date: 02/23/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Main line installed from MH3-MH4 ok to backfill progress areas.} ; {Activity date: 02/18/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, see previous notes} ; {Activity date: 11/24/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, South building Waste lines under slab to exterior two way clean outs installed and tested. Ok to backfill progress areas.} ; {Activity date: 11/10/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 4”-6” SANITARY WASTE line under slab Approved from (GL 1-12. A-E) ok to backfill progress.

}
07/01/2022 COT - HCPL - Yard Water Line Passed {Activity date: 07/01/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 06/30/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, 3" main line installed with tracer line, test required.}
08/08/2022 COT - HCBU - Roof Nailing Passed {Activity date: 08/08/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/01/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, ROOF deck nail inspection to GL 16 ok to proceed.

} ; {Activity date: 07/21/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Deck nail inspection for progress @ North end ok to proceed.
}
09/19/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 09/19/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - CODE ECO}
09/19/2022 COT - HCEL - Construction Power Passed {Activity date: 09/19/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved. The TEP clearance code ECO..}
09/29/2022 COT - HCPL - Gas Pressure Test Passed {Activity date: 09/29/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved}
09/29/2022 COT - HCPL - Plumbing Intermediate Passed {Activity date: 09/29/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 06/30/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready.}
12/20/2022 COT - HCBU - Preslab Passed
12/20/2022 COT - HCEL - Electrical Intermediate Passed
12/20/2022 COT - HCBU - Excavation/Rebar/Zoning Passed
12/20/2022 COT - HCBU - Framing Passed
12/20/2022 COT - HCEL - Grounding/Bonding Passed
12/20/2022 COT - HCBU - Interior Shear Bracing Passed
12/20/2022 COT - HCEL - Electrical Underground Passed
12/20/2022 COT - HCBU - Building Progress Passed
12/20/2022 COT - HCEL - Electrical Above Ceiling Passed
12/20/2022 COT - HCBU - Building Above Ceiling Passed
12/20/2022 COT - HCEL - Temporary Service Passed
12/20/2022 COT - HCME - Mechanical Intermediate Passed
12/20/2022 COT - HCBU - Stem Wall/Retaining Wall Passed
12/23/2022 COT - HCME - Mechanical Final Passed
12/23/2022 COT - HCBU - Firewall/Fire Barrier/Firestop Passed
12/23/2022 COT - HCBU - Sustainability Passed
12/23/2022 COT - HCEL - Outdoor Lighting Passed
12/23/2022 COT - HCPL - Plumbing Roof Drains Passed
01/13/2023 COT - FCON - Alarm - Final Passed
01/20/2023 COT - HCPL - Plumbing Final Passed Exterior shell of building is complete. Ready for future tenant improvement work to begin.
01/20/2023 COT - HCEL - Electrical Final Passed Exterior shell of building is complete. Ready for future tenant improvement work to begin.
01/20/2023 COT - FCON - Underground Flush Passed Approved on premit T22FC00062 11/9/22
01/20/2023 FCON – OH Piping & Hydro Passed
01/25/2023 COT - FCON - Pump - Final Passed
01/25/2023 COT - FCON - Sprinkler - Final Passed
01/25/2023 COT - HCBU - Building Final Passed contractor is waiting on final approval from fire dept and site inspections.
11/21/2023 COT - FCON - Fire - Final Passed
03/08/2023 COT - FCON - Underground Pressure Passed Permit t22FC00062 passed on 01/25/2022

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
JOISTS SHOPS AND CALCS.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
REV1_JOB CARD.PDF DOCUMENTS VIEW
REV1_PERMIT.PDF DOCUMENTS VIEW
REV1_PLAN SET.PDF DOCUMENTS VIEW
REV2_PLAN SET.PDF DOCUMENTS VIEW
REVISION APPLICATION.PDF DOCUMENTS VIEW
REVISION NARRATIVE.PDF DOCUMENTS VIEW
STRUC CALCS.PDF DOCUMENTS VIEW
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
TAC2A - SPECIAL INSPECTION CLOSEOUT-2023-02-27_V1.PDF DOCUMENTS VIEW
TUCSON AIRPORT CENTER-210151 (CHLORINATION REPORT)-2023-02-27_V1.PDF DOCUMENTS VIEW
'PERMIT.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
COMMERCIAL CHECKLIST.PDF DOCUMENTS VIEW
COMCHECK.PDF DOCUMENTS VIEW
GCL.PDF DOCUMENTS VIEW
PLAN_SET.PDF CONSTRPLANS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERTIFICATE 2021-06-14.PDF DOCUMENTS VIEW
DEQ_FUGITIVEDUSTPERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW