Inspection Status: Not Ready
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - HCBU - Preslab |
|
Not Ready |
|
| 08/24/2022 |
COT - HCBU - Preslab |
ESTEVENS |
Partial Approval |
Entered by VVERA1 - Partial. Shearwalls. |
| 01/21/2022 |
COT - HCBU - Preslab |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, rebar installed and inspected from GL- 17-22 ok for concrete placement. |
| 01/14/2022 |
COT - HCBU - Preslab |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, rebar mat installed @ building slab from GL10-16. Note: ensure all splices are tied correctly and rebar is elevated on chairs prior to concrete placement, special inspection required.
|
| 01/12/2022 |
COT - HCBU - Preslab |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, Ok for concrete placement from GL 7-10 |
| 01/04/2022 |
COT - HCBU - Preslab |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, rebar mat installed @ building slab from GL1-6. Note: ensure all splices are tied correctly and rebar is elevated on chairs prior to concrete placement, special inspection required. |
| 12/20/2022 |
COT - HCBU - Preslab |
|
Passed |
|