Inspection Status: Passed
Inspection History: COT - HCPL - Sewer
| Date |
Description |
Inspector |
Results |
Comments |
| 03/18/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Approved |
Entered by VVERA1 - Approved
Negative vacuum test for Manhole 4 PASS.
Negative vacuum test for Manhole 5 PASS |
| 03/16/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - partial, Air test for main line from Manhole 4-5 PASS, Mandril PASS |
| 03/15/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, Correction for mainline from manhole 4-5 complete and ok to backfill.
|
| 03/10/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, no inspection today see previous notes
|
| 03/09/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial ,Air pressure test and Mandril results For Private Sewer Main. (Manhole 5 to public manhole, air test PASS, Mandril PASS) (Manhole 5-4 air test PASS, Mandril FAIL correction required), (Manhole 4-3 Air test PASS, Mandril PASS),(Manhole 3-2 Air test PASS, Mandril PASS),( Manhole 2-1 air test PASS, Mandril PASS) |
| 03/07/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - partial, Sewer main from public manhole to private manhole ok to backfill progress areas. |
| 03/02/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, sewer main from MH1-MH2 ok to backfill progress areas.
|
| 02/25/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, 8” main from man hole 2-3 ok to backfill progress areas.
|
| 02/18/2022 |
COT - HCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, Inspection of 8” main line from manhole 4-5 ok to backfill progress areas |