Permit: T20CM09215

Parcel: 14042021A

Inspection Status: Passed

Inspection History: COT - HCPL - Sewer 

Date Description Inspector Results Comments
03/18/2022 COT - HCPL - Sewer  DMUNIZ Approved Entered by VVERA1 - Approved Negative vacuum test for Manhole 4 PASS. Negative vacuum test for Manhole 5 PASS
03/16/2022 COT - HCPL - Sewer  DMUNIZ Partial Approval Entered by VVERA1 - partial, Air test for main line from Manhole 4-5 PASS, Mandril PASS
03/15/2022 COT - HCPL - Sewer  DMUNIZ Partial Approval Entered by NGARCIA3 - Partial, Correction for mainline from manhole 4-5 complete and ok to backfill.
03/10/2022 COT - HCPL - Sewer  DMUNIZ Partial Approval Entered by VVERA1 - Partial, no inspection today see previous notes
03/09/2022 COT - HCPL - Sewer  DMUNIZ Partial Approval Entered by NGARCIA3 - Partial ,Air pressure test and Mandril results For Private Sewer Main. (Manhole 5 to public manhole, air test PASS, Mandril PASS) (Manhole 5-4 air test PASS, Mandril FAIL correction required), (Manhole 4-3 Air test PASS, Mandril PASS),(Manhole 3-2 Air test PASS, Mandril PASS),( Manhole 2-1 air test PASS, Mandril PASS)
03/07/2022 COT - HCPL - Sewer  DMUNIZ Partial Approval Entered by NGARCIA3 - partial, Sewer main from public manhole to private manhole ok to backfill progress areas.
03/02/2022 COT - HCPL - Sewer  DMUNIZ Partial Approval Entered by VVERA1 - Partial, sewer main from MH1-MH2 ok to backfill progress areas.
02/25/2022 COT - HCPL - Sewer  DMUNIZ Partial Approval Entered by NGARCIA3 - Partial, 8” main from man hole 2-3 ok to backfill progress areas.
02/18/2022 COT - HCPL - Sewer  DMUNIZ Partial Approval Entered by NGARCIA3 - Partial, Inspection of 8” main line from manhole 4-5 ok to backfill progress areas