Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
04/30/2020
Applicant:
Justin Smith
Description:
NEW HOTEL

Permit Reviews

Permit Number - T20CM02722
Permit Status: Complete
Permit Description: NEW HOTEL
Start Date Submittal Complete Date Status  
01/20/2022 RESUBMITTAL 02/01/2022 COMPLETED Review Details
02/14/2022 RESUBMITTAL 02/23/2022 COMPLETED Review Details
03/17/2022 RESUBMITTAL 03/18/2022 COMPLETED Review Details
04/19/2022 RESUBMITTAL 04/20/2022 COMPLETED Review Details
04/20/2022 RESUBMITTAL 04/29/2022 COMPLETED Review Details
04/30/2020 PLANS OK TO SUBMIT - COMM 07/21/2020 COMPLETED Review Details
06/30/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 09/08/2021 COMPLETED Review Details
07/21/2020 COMMERCIAL - NEW 07/27/2020 COMPLETED Review Details
08/09/2022 REVISION - - 1ST 08/16/2022 COMPLETED Review Details
08/30/2022 REVISION - - 1ST 09/23/2022 COMPLETED Review Details
09/27/2021 RESUBMITTAL 10/25/2021 COMPLETED Review Details
10/11/2022 REVISION - - 1ST 10/18/2022 COMPLETED Review Details
10/10/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/13/2023 APPROVED Review Details
12/08/2022 COMMERCIAL REVIEW - FULL v.2 12/09/2022 REQUIRES RESUBMIT Review Details
12/12/2022 COMMERCIAL REVIEW - FULL v.1 03/22/2023 APPROVED Review Details
11/06/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/06/2023 REQUIRES RESUBMIT Review Details
07/28/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/04/2023 APPROVED Review Details
08/07/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/08/2023 REQUIRES RESUBMIT Review Details
08/21/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 08/21/2023 APPROVED Review Details
11/29/2022 COMMERCIAL REVIEW - FULL v.1 11/29/2022 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T20CM02722
Permit Status: Complete
Permit Description: NEW HOTEL
Date Description Comments
04/30/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
04/29/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
04/29/2022 SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED.
04/29/2022 This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm
04/29/2022 SHOP DRAWINGS REQUIRED FOR SWIMMING POOL - SEPARATE PERMIT AS DESIGN/BUILD - CLASS "C" SEMI-PUBLIC PER ISPSC 2018 SECTION 202
04/29/2022 SHOP DRAWINGS REQUIRED FOR NFPA 13 FIRE SPRINKLER SYSTEM/CLASS 1 STANDPIPES.
04/29/2022 SHOP DRAWINGS REQUIRED FOR IRRIGATION SPRINKLER SYSTEM
04/29/2022 SHOP DRAWINGS REQUIRED FOR FIRE ALARM SYSTEM.
04/29/2022 SHOP DRAWINGS REQUIRED FOR INTERIOR SIGNS/GRAPHICS.
04/29/2022 SHOP DRAWINGS REQUIRED FOR TRACTION MRL (MACHINE ROOM LESS) ELEVATOR (W/TWO WAY COMMUNICATION PER IBC 1009.8).
04/29/2022 SHOP DRAWINGS REQUIRED FOR EMERGENCY RESPONDER RADIO COVERAGE - TESTED & INSTALLED PER PFS SECTION 510; FIRE DEPARTMENT POLICY 510 AND 2018 PBC 403.4.5.
04/29/2022 SHOP DRAWINGS REQUIRED FOR COVERED PARKING CANOPIES.
04/29/2022 SPECIAL INSPECTION IS REQUIRED FOR STRUCTURAL STEEL: 1705.2 AND TABLE 1705.2 & AISC 360 CHAPTER N.
04/29/2022 SPECIAL INSPECTION IS REQUIRED FOR WOOD: SECTION 1705.5.
04/29/2022 SPECIAL INSPECTION IS REQUIRED FOR SOILS: SECTION 1705.6 AND TABLE 1705.6 (PERIODIC)
10/12/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/29/2022 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS.
08/04/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
08/04/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM02722
Permite Description: NEW HOTEL
Total Outstanding Inspections - 30
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - HCBU - Sustainability N/A Not Ready
10/26/2022 COT - HCPL - Backwater Valve N/A Not Ready
10/26/2022 COT - HCPL - Sewer N/A Not Ready
10/26/2022 COT - HCEL - Construction Power N/A Not Ready
10/26/2022 COT - HCEL - Outdoor Lighting N/A Not Ready
10/26/2022 COT - HCBU - Preslab N/A Not Ready
10/26/2022 COT - HCME - Kitchen Hood N/A Not Ready
10/26/2022 COT - HCPL - Plumbing Above Ceiling N/A Not Ready
10/26/2022 COT - HCBU - Exterior Clips/Sheathing N/A Not Ready
10/26/2022 COT - HCPL - Rough Soil N/A Not Ready
10/26/2022 COT - HCBU - Excavation/Rebar/Zoning N/A Not Ready
10/26/2022 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Not Ready
11/15/2022 COT - HCEL - Electrical Intermediate N/A Re-inspection required
10/26/2022 COT - HCPL - Plumbing Intermediate N/A Not Ready
10/26/2022 COT - HCEL - Electrical Underground N/A Not Ready
10/26/2022 COT - HCBU - Framing N/A Not Ready
10/26/2022 COT - HCBU - Interior Shear Bracing N/A Not Ready
10/26/2022 COT - HCPL - Gas Pressure Test N/A Not Ready
05/24/2023 COT - HCEL - Electrical Above Ceiling N/A Not Ready
05/24/2023 COT - HCBU - Building Above Ceiling N/A Not Ready
12/13/2022 COT - HCME - Mechanical Above Ceiling N/A Partial Pass partial approval for dryer vents on 2nd floor ok to insulate
10/26/2022 COT - HCEL - Electrical Progress N/A Not Ready
10/26/2022 COT - HCPL - Plumbing Progress N/A Not Ready
07/19/2023 COT - HCPL - Plumbing Final N/A Partial Pass completed 2nd floor room finals except 218 and 220, 3rd and 4th corridors
07/19/2023 COT - HCEL - Electrical Final N/A Partial Pass completed 2nd floor room finals except 218 and 220, 3rd and 4th corridors
07/19/2023 COT - HCME - Mechanical Final N/A Partial Pass completed 2nd floor room finals except 218 and 220, 3rd and 4th corridors
07/25/2023 ENGR Engineering Final N/A Partial Pass Level 4TCO for occupancy is good
08/01/2023 COT - HCBU - Building Final N/A Partial Pass okay for TCO level 4
08/10/2023 COT - HCBU - CofO N/A Not Ready
10/26/2022 COT - FCON - Fire - Final N/A Not Ready OK for level 2 TCO Levels 2-4 on the permit
T22FC00123 john

Completed Inspections

Permit Status: Complete
Permit Number: T20CM02722
Permit Description: NEW HOTEL
Total Completed Inspections - 25
Date Description Inspector Results Comments
05/27/2022 COT - HCPL - Yard Water Line Passed {Activity date: 05/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
07/07/2022 COT - HCBU - Roof Nailing Passed {Activity date: 07/07/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 07/06/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 06/03/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, 3RD FLOOR DECK NAILING COMPLETE} ; {Activity date: 05/25/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 4TH FLOOR DECK NAILING OK TO PROCEED.
}
10/07/2022 COT - HCPL - Plumbing Roof Drains Passed {Activity date: 10/07/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved, primary and overflows} ; {Activity date: 09/26/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval wet test good on primary drains lacking one with whole at A & B wings, overflows not inspected.} ; {Activity date: 09/20/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready}
10/26/2022 COT - FCON - Underground Flush Passed Approved per the FC permit. Closing for inspectors.
10/26/2022 FCON – OH Piping & Hydro Passed Approved per the FC permit. Closing for inspectors.
10/26/2022 COT - FCON - Underground Pressure Passed Approved per the FC permit. Closing for inspectors.
12/28/2022 COT - HCBU - Masonry Pregrout Passed
02/24/2023 COT - HCEL - Electrical Underground Passed
02/28/2023 BULD - Electrical Clearance Passed
04/07/2023 COT - HCBU - Interior Shear Bracing Passed
05/23/2023 COT - BULD - SWG Clearance Passed
05/23/2023 COT - HCPL - Gas Pressure Test Passed
06/14/2023 COT - HCEL - Electrical Above Ceiling Passed
06/16/2023 COT - FCON - Sprinkler - Final Passed Approved per the FC permit. Closing for inspectors.
07/25/2023 COT - HCBU - Building Progress Passed
07/25/2023 COT - HCEL - Electrical Progress Passed
07/25/2023 COT - HCPL - Plumbing Progress Passed
07/25/2023 COT - HCME - Mechanical Progress Passed
08/02/2023 COT - FCON - Alarm - Final Passed need monitoring permit. (Approved per the FC permit. Closing for inspectors.8/2/23)
08/02/2023 COT - HCEL - Electrical Final Passed
08/02/2023 COT - HCME - Mechanical Final Passed
08/02/2023 ENGR Engineering Final Passed GOOD FOR C. O.
08/14/2023 COT - HCBU - Building Final Passed recommend C/O
08/14/2023 COT - HCBU - CofO Passed
09/22/2023 COT - FCON - Fire - Final Passed