Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Building Above Ceiling
Permit Number - T20CM02722
Inspection Description - COT - HCBU - Building Above Ceiling
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - HCBU - Building Above Ceiling | Not Ready | ||
04/28/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | B wing 4th floor ok to install ceiling tiles | |
05/05/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | 5-5-23: Mechanical ductwork and registers plus Electrical conduits, junction boxes, and lights in grid ceiling on Wing A of 4th Floor are installed completely. Okay to install grid ceiling tiles. | |
05/08/2023 | COT - HCBU - Building Above Ceiling | Not Ready | ||
05/16/2023 | COT - HCBU - Building Above Ceiling | Not Ready | ||
05/18/2023 | COT - HCBU - Building Above Ceiling | Not Ready | ||
05/22/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | third floor ok to close ceiling | |
05/24/2023 | COT - HCBU - Building Above Ceiling | Not Ready | ||
05/25/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | for 2nd floor | |
06/05/2023 | COT - HCBU - Building Above Ceiling | Not Ready | ||
06/08/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for 1st floor corridor | |
06/14/2023 | COT - HCBU - Building Above Ceiling | Partial Pass | partial approval for offices in back of house and corridors ducts returns for dampers |