Permit: T19CM09337
Permit Details
Apply Date:
12/19/2019
Applicant:
N/A
Description:
RESTAURANT
Contractors:
- HAWORTH CORPORATION , THE
Permit Reviews
Permit Number - T19CM09337
Permit Status: C of o
Permit Description: RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/05/2020 | RESUBMITTAL - TI ALL | 05/18/2020 | COMPLETED |
| 04/29/2020 | RESUBMITTAL | 05/20/2020 | COMPLETED |
| 05/20/2020 | RESUBMITTAL | 06/03/2020 | COMPLETED |
| 12/19/2019 | PLANS OK TO SUBMIT - COMM | 12/26/2019 | COMPLETED |
| 12/26/2019 | COMMERCIAL - NEW | 03/05/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM09337
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/19/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM09337
Permit Description: RESTAURANT
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/09/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | All three are approved. |
| 07/09/2020 | SITE - SEWER | ESTEVENS | Approved | All three are approved. |
| 07/09/2020 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | All three are approved. |
| 07/15/2020 | ELECTRIC - UFER | ESTEVENS | Approved | Both are approved. |
| 07/15/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | Both are approved. |
| 07/30/2020 | ROOF NAILING | ESTEVENS | Approved | Approved. |
| 08/20/2020 | FRAMING | WGALLAGHER | Approved | Approved |
| 08/28/2020 | U VALUE FOR WINDOW | ESTEVENS | Approved | N/A |
| 08/28/2020 | STUCCO MESH | ESTEVENS | Approved | N/A |
| 08/28/2020 | SHEET ROCK NAILING | ESTEVENS | Approved | Approved. |
| 09/24/2020 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ap |
| 10/01/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 10/01/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Ap |
| 10/01/2020 | PLUMBING - ABOVE CEILING | DQUINN | Approved | Ap |
| 10/01/2020 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | Ap |
| 10/06/2020 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Underground SES, lighting, irrigation and menu boards ok to backfill. |
| 12/10/2020 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO-PANELS A, B |
| 12/10/2020 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Clear eco for switch gear serving panels A B |
| 12/16/2020 | GAS CLEARANCE | DQUINN | Approved | CODE |
| 12/16/2020 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Ap Clear gas |
| 12/22/2020 | BUILDING - PROGRESS | DQUINN | Approved | 1090 |
| 12/22/2020 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | 1090 |
| 12/22/2020 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | 1090 |
| 12/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | 1090 |
| 12/22/2020 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | 2090 |
| 12/22/2020 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | 2090 |
| 12/22/2020 | ELECTRIC - PROGRESS | DQUINN | Approved | Ap |
| 12/22/2020 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | 2090 |
| 12/22/2020 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 12/22/2020 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 12/22/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | 3090 |
| 12/22/2020 | PLUMBING - ROOF DRAINS | DQUINN | Approved | 3090 |
| 12/22/2020 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 12/22/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | 4090 |
| 12/22/2020 | MECHANICAL - HOODS | DQUINN | Approved | 4090 |
| 12/22/2020 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 12/22/2020 | FIRE - FINAL | wmotto1 | Approved | 1. Just waiting for the Operational permit to get approved and paid for. |
| 12/22/2020 | FIRE - KITCHEN EXH HOOD FINAL | wmotto1 | Approved | |
| 12/23/2020 | BUILDING - FINAL | DQUINN | Approved | pa When all other entities are approved, Ap 1090, close permit, and issue c of o. |
| 12/24/2020 | CERTIFICATE OF OCCUPANCY | ESTEVENS | Approved | Partial. Pending other inspections. |
| 12/30/2020 | ENGINEERING - FINAL | BBENEDON | Approved | APPROVED |
| 01/06/2021 | HEALTH DEPT - FINAL 724-7908 | RSALDAT1 | Approved | HEALTH DEPT DOCS RECIEVED. |
| 02/25/2021 | FIRE - ALARM FINAL | jfordney | Approved |