Permit: T19CM07637
Permit Details
Status:
Final
Type:
COMMERCIAL OTHER
Address:
6721 S RENAISSANCE DR
Address NEW:
6721 S RENAISSANCE DR
Apply Date:
10/17/2019
Applicant:
JACA DESIGN LLC
Description:
TI: ELECTRICAL ONLY
Permit Reviews
Permit Number - T19CM07637
Permit Status: Final
Permit Description: TI: ELECTRICAL ONLY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/10/2020 | REVISION - - 1ST | 01/13/2020 | COMPLETED |
| 02/28/2020 | REVISION - - 2ND | 03/04/2020 | COMPLETED |
| 06/18/2020 | REVISION - - 2ND | 07/20/2020 | COMPLETED |
| 08/18/2020 | REVISION - - 2ND | 09/09/2020 | COMPLETED |
| 09/09/2020 | REVISION - - 2ND | 12/04/2020 | COMPLETED |
| 10/17/2019 | COMMERCIAL - TI | 10/18/2019 | COMPLETED |
| 10/18/2019 | RESUBMITTAL | 11/12/2019 | COMPLETED |
| 11/12/2019 | RESUBMITTAL | 11/14/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07637
Permit Status: Final
Permit Description: TI: ELECTRICAL ONLY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/17/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM07637
Permit Description: TI: ELECTRICAL ONLY
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/02/2020 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 03/02/2020 | ELECTRIC - UFER | TVALENCIA | Approved | |
| 10/08/2020 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 10/08/2020 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved |
| 10/08/2020 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Not Applicable |
| 10/08/2020 | ELECTRIC - TEMPORARY SERVICE | DMUNIZ | Approved | Not applicable |
| 10/08/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 10/14/2020 | GAS CLEARANCE | WGALLAGHER | Approved | CODE |
| 10/14/2020 | BUILDING - PROGRESS | WGALLAGHER | Approved | Not a required inspection |
| 10/14/2020 | BUILDING ABOVE CEILING | WGALLAGHER | Approved | Not applicable |
| 10/14/2020 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | Approved ok for clearance |
| 10/14/2020 | FRAMING | WGALLAGHER | Approved | Approved 2 restrooms |
| 11/24/2020 | TEP CLEARANCE - PM | DMUNIZ | Approved | not applicable |
| 11/24/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 11/24/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
| 11/24/2020 | PLUMBING - FINAL | DMUNIZ | Approved | |
| 11/24/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 11/24/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 12/21/2020 | FIRE - ALARM FINAL | MRoss | Approved | |
| 12/23/2020 | BUILDING - FINAL | DMUNIZ | Approved | APPROVED |
| 12/23/2020 | CERTIFICATE OF OCCUPANCY | DMUNIZ | Approved | 1090 |
| 12/23/2020 | FIRE - FINAL | MRoss | Approved | |
| 12/23/2020 | FIRE SPKLR - FINAL | MRoss | Approved |