Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Apply Date:
04/30/2019
Applicant:
Description:
SFR DRHT308018 T18-M0052

Permit Reviews

Permit Number - T19CM03062
Permit Status: Expired
Permit Description: SFR DRHT308018 T18-M0052
Start Date Submittal Complete Date Status  
04/30/2019 RESIDENTIAL - BLDG/ZONING-WALKTHRU 04/30/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM03062
Permit Status: Expired
Permit Description: SFR DRHT308018 T18-M0052
Total Outstanding Activity Conditions - 4
Date Name
04/30/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
04/30/2019 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
04/30/2019 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/30/2019 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.

Completed Inspections

Permit Status: Expired
Permit Number: T19CM03062
Permit Description: SFR DRHT308018 T18-M0052
Total Completed Inspections - 23
Date Description Inspector Results Comments
05/16/2019 COT - RSPL - Yard Water Line Passed {Activity date: 05/16/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - } ; {Activity date: 05/14/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by CBELL1 - 1- Work is incomplete}
05/16/2019 COT - RSPL - Sewer Passed {Activity date: 05/16/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - } ; {Activity date: 05/14/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by CBELL1 - 1- Work is incomplete}
05/16/2019 COT - RSPL - Rough Soil Passed {Activity date: 05/16/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - } ; {Activity date: 05/14/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by CBELL1 - 1- Work is incomplete}
05/16/2019 COT - RSPL - Gas Pressure Test Passed {Activity date: 05/16/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - }
05/22/2019 COT - RSBU - Preslab Passed {Activity date: 05/22/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - make sure to have site plan on site included with your drawings or may result in a failed inspection as we need to verify setbacks.} ; {Activity date: 05/20/2019; Status: Not ready for Inspection; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Contractor called and cancelled the inspection request.}
05/22/2019 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 05/22/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - clean debris out of footings and make sure to maintain clearances around rebar.} ; {Activity date: 05/20/2019; Status: Not ready for Inspection; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Contractor called and cancelled the inspection request.}
06/04/2019 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 06/04/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - }
06/10/2019 COT - RSBU - Roof Nailing Passed {Activity date: 06/10/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - } ; {Activity date: 06/04/2019; Status: Not ready for Inspection; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - please provide trust calx for upstairs. Only floor joist calx on site which those were checked. Please provide a secured ladder to inspect roof nailing.}
06/10/2019 COT - RSEL - Electrical Underground Passed {Activity date: 06/10/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
06/19/2019 COT - RSEL - Grounding/Bonding Passed {Activity date: 06/19/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by DMERANZ1 - } ; {Activity date: 05/22/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - rebar installed}
06/19/2019 PDSD Building Division - TEP PM Clearance Passed {Activity date: 06/19/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by DMERANZ1 - CODE ECO}
06/19/2019 COT - RSEL - Construction Power Passed {Activity date: 06/19/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by DMERANZ1 - ECO} ; {Activity date: 06/11/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Ufer ground conductor has not been landed. Please check work for completion prior to calling in for inspection request.} ; {Activity date: 06/10/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by CBELL1 - 1- Ufer ground conductor is not landed.}
06/26/2019 RSME - Mechanical Progress Passed {Activity date: 06/26/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Shall provide a clean out at the base of the 2 inch waste stack.
2- ABS pipe is not approved material for blocking of horizontal piping.
3- Shall provide Shield plates at 3 inch soil stack.
4- Range electric conductor not secured and sheathing torn.
5- Shall secure the closet flange to floor.
Inspection stop.}
07/09/2019 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 07/09/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by DMERANZ1 - } ; {Activity date: 07/05/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by VFLORES1 - } ; {Activity date: 07/01/2019; Status: Denied; Inspector: DQUINN; Comment: Entered by DMERANZ1 - 1- ABS pipe is not approved material for blocking and support on horizontal waste and soil piping.
2- Shall secure and support horizontal water lines every 32 inches.
3- Shall support and block all horizontal waste and vent piping.} ; {Activity date: 06/26/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - }
07/09/2019 COT - LCBU - Framing Passed {Activity date: 07/09/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by DMERANZ1 - } ; {Activity date: 07/05/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by VFLORES1 - } ; {Activity date: 07/01/2019; Status: Denied; Inspector: DQUINN; Comment: Entered by DMERANZ1 - 1- ABS pipe is not approved material for blocking and support on horizontal waste and soil piping.
2- Shall secure and support horizontal water lines every 32 inches.
3- Shall support and block all horizontal waste and vent piping.} ; {Activity date: 06/28/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by DMERANZ1 - 1/2” ab’s 64” oc all #2 shear walls
Pending all trades} ; {Activity date: 06/26/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - }
07/09/2019 COT - LCPL - Plumbing Intermediate Passed {Activity date: 07/09/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by DMERANZ1 - } ; {Activity date: 07/05/2019; Status: Denied; Inspector: TVALENCIA; Comment: Entered by VFLORES1 - 1- See comments from previous inspection
2- Water line has penetrated through the top of the Second floor TGI} ; {Activity date: 07/01/2019; Status: Denied; Inspector: DQUINN; Comment: Entered by DMERANZ1 - 1- ABS pipe is not approved material for blocking and support on horizontal waste and soil piping.
2- Shall secure and support horizontal water lines every 32 inches.
3- Shall support and block all horizontal waste and vent piping.}
07/17/2019 COT - HCBU - Interior Shear Bracing Passed {Activity date: 07/17/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - please have drawings on site at time of inspection or it may result in a failed inspection.}
08/30/2019 COT - RSEL - Outdoor Lighting Passed {Activity date: 08/30/2019; Status: Approved; Inspector: ESTEVENS; Comment: Entered by DMERANZ1 - }
08/30/2019 COT - RSPL - Plumbing Final Passed {Activity date: 08/30/2019; Status: Approved; Inspector: ESTEVENS; Comment: Entered by DMERANZ1 - }
08/30/2019 RSPL - Plumbing Progress Passed {Activity date: 08/30/2019; Status: Approved; Inspector: ESTEVENS; Comment: Entered by DMERANZ1 - }
08/30/2019 COT - RSEL - Electrical Final Passed {Activity date: 08/30/2019; Status: Approved; Inspector: ESTEVENS; Comment: Entered by DMERANZ1 - }
09/04/2019 COT - RSME - Mechanical Final Passed {Activity date: 09/04/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/30/2019; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by DMERANZ1 - Unable to access air handler in attic. No ladder.} ; {Activity date: 04/30/2019; Status: Prior to Final Inspectn; Inspector: PMARTIN1; Comment: Entered by PMARTIN1 - ISSUED WITH PCRWRD CONDITIONS:

NO PHYSICAL CONNECTION TO THE PUBLIC SEWER SYSTEM UNTIL THE PUBLIC SEWER G-2016-041 IS ACCEPTED AND RELEASED BY PCRWRD

NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PUBLIC SEWER G-2016-041 IS ACCEPTED AND RELEASED BY PCRWRD}
09/04/2019 RSBU - Building Final Passed {Activity date: 09/04/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/30/2019; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by DMERANZ1 - Pending other inspections.}