Permit: T18CM09810
Permit Details
Apply Date:
12/17/2018
Applicant:
N/A
Description:
HEALTH CLUB
Contractors:
- EPSTEIN CONSTRUCTION L L C
Permit Reviews
Permit Number - T18CM09810
Permit Status: C of o
Permit Description: HEALTH CLUB
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/19/2019 | 3RD PARTY REVIEW - COMMERCIAL TI | 02/19/2019 | COMPLETED |
| 02/19/2019 | POST 3RD PARTY REVIEW | 03/04/2019 | COMPLETED |
| 03/04/2019 | POST 3RD PARTY REVIEW | 03/08/2019 | COMPLETED |
| 04/26/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 05/08/2019 | COMPLETED |
| 06/17/2019 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 06/17/2019 | COMPLETED |
| 06/17/2019 | POST 3RD PARTY REVIEW | 06/18/2019 | COMPLETED |
| 12/17/2018 | PLANS OK TO SUBMIT - COMM | 12/17/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09810
Permit Status: C of o
Permit Description: HEALTH CLUB
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/17/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM09810
Permit Description: HEALTH CLUB
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2019 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | |
| 03/19/2019 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | |
| 04/02/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 04/05/2019 | ROOF NAILING | RCHANDLER | Approved | |
| 05/24/2019 | STUCCO MESH | MRAMBER | Approved | |
| 06/11/2019 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | |
| 06/18/2019 | ELECTRIC - CABLE DROP | MRAMBER | Approved | ECO OK TO CLEAR |
| 06/28/2019 | TEP CLEARANCE - PM | MRAMBER | Approved | CODE ECO |
| 06/28/2019 | ELECTRIC - UFER | MRAMBER | Approved | |
| 07/11/2019 | OUTDOOR LIGHTING FINAL | GWEST | Approved | |
| 07/12/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
| 07/12/2019 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | clear gas |
| 07/23/2019 | U VALUE FOR WINDOW | MRAMBER | Approved | |
| 07/23/2019 | FIRE INTERMEDIATE | jvincent | Approved | |
| 07/23/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 08/12/2019 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | approval is for rough soil for pool trench drains |
| 08/16/2019 | MECHANICAL - ABOVE CEILING | RCHANDLER | Approved | |
| 08/16/2019 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | |
| 08/16/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
| 08/16/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
| 08/16/2019 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | |
| 08/16/2019 | PLUMBING - PRE SLAB | RCHANDLER | Approved | Trench drains. |
| 08/16/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 08/23/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 08/23/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 08/23/2019 | FRAMING | RCHANDLER | Approved | |
| 08/23/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 09/09/2019 | FIRE - FINAL | MRoss | Approved | |
| 09/09/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 09/09/2019 | FIRE - ALARM FINAL | MRoss | Approved | |
| 09/10/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 09/10/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 09/10/2019 | BUILDING ABOVE CEILING | RCHANDLER | Approved | |
| 09/10/2019 | SHEET ROCK NAILING | RCHANDLER | Approved | |
| 09/10/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
| 09/10/2019 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | |
| 09/13/2019 | NPPO - FINAL | RLEDONNE | Approved | |
| 09/13/2019 | SIGN - FINAL | RLEDONNE | Approved | |
| 09/13/2019 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 09/16/2019 | BUILDING - FINAL | RCHANDLER | Approved | |
| 09/16/2019 | RIGHT OF WAY - FINAL | MVV | Approved | No work in right of way. |