Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
2975 S KINO PW
Address NEW:
2975 S KINO PW
Apply Date:
11/14/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
CAR WASH
Architects:
  • A23 STUDIOS
Contractors:
  • MW MORRISSEY CONSTRUCTION LLC

Permit Reviews

Permit Number - T18CM09059
Permit Status: C of o
Permit Description: CAR WASH
Start Date Submittal Complete Date Status  
01/29/2019 POST 3RD PARTY REVIEW 03/12/2019 COMPLETED Review Details
03/12/2019 POST 3RD PARTY REVIEW 04/05/2019 COMPLETED Review Details
07/09/2019 3RD PARTY REVIEW - REVISION/OTHER 07/09/2019 COMPLETED Review Details
07/09/2019 POST 3RD PARTY REVIEW 07/09/2019 COMPLETED Review Details
07/11/2019 3RD PARTY REVIEW - REVISION/OTHER 07/11/2019 COMPLETED Review Details
07/11/2019 POST 3RD PARTY REVIEW 07/12/2019 COMPLETED Review Details
08/23/2019 3RD PARTY REVIEW - REVISION/OTHER-2ND 08/23/2019 COMPLETED Review Details
10/01/2019 REVISION - - 4TH 10/02/2019 COMPLETED Review Details
11/14/2018 PLANS OK TO SUBMIT - COMM 11/14/2018 COMPLETED Review Details
11/16/2018 3RD PARTY REVIEW - COMMERCIAL 12/27/2018 COMPLETED Review Details
12/27/2018 POST 3RD PARTY REVIEW 01/29/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM09059
Permit Status: C of o
Permit Description: CAR WASH
Total Outstanding Activity Conditions - 1
Date Name
11/14/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM09059
Permit Description: CAR WASH
Total Completed Inspections - 40
Date Description Inspector Results Comments
04/25/2019 ELECTRIC - UFER GWEST Approved UFER with #4 GEC
05/14/2019 STEM WALL/RETAINING WALL AKLEINSORGE Approved Interior stem wall between car wash and mechanical room, ok to pour
06/05/2019 PLUMBING - YARD WTR LINE/TEST RCAMACHO Approved
06/05/2019 PLUMBING - PRE SLAB RCAMACHO Approved
06/05/2019 BUILDING PRE-SLAB RCAMACHO Approved
07/31/2019 PLUMBING - ROUGH, SOIL AKLEINSORGE Approved 2" piping for reverse osmosis system from building to holding tanks, ok to backfill
07/31/2019 ROOF NAILING AKLEINSORGE Approved Obs over barrel trusses on north/south sides of wash tunnel
07/31/2019 EXT METAL CLIPS/EXT SHEATHING AKLEINSORGE Approved Exterior sheathing for north/south towers and bump out on east/west sides of building
08/02/2019 TEP CLEARANCE - PM RCHANDLER Approved CODE ECO
08/02/2019 ELECTRIC - CABLE DROP RCHANDLER Approved ECO
08/14/2019 SHEET ROCK NAILING MHASSAN Approved
08/14/2019 STUCCO MESH MHASSAN Approved
08/26/2019 PLUMBING - GAS PRESSURE TEST RCHANDLER Approved Clearance SWG. OK to set meter.
08/26/2019 PLUMBING - MD GAS/PRECONST MTG RCHANDLER Approved
08/26/2019 PLUMBING - ABOVE CEILING RCHANDLER Approved
09/06/2019 ELECTRIC - UNDERGROUND TVALENCIA Approved
09/16/2019 MECHANICAL - INTERMEDIATE ESTEVENS Approved
09/16/2019 BUILDING ABOVE CEILING ESTEVENS Approved
09/16/2019 ELECTRIC - ABOVE CEILING ESTEVENS Approved
09/16/2019 MECHANICAL - ABOVE CEILING ESTEVENS Approved
09/27/2019 GAS CLEARANCE RCHANDLER Approved
09/27/2019 PLUMBING - GAS PRESS TEST FNL RCHANDLER Approved Clearance SWG. OK to connect.
09/27/2019 ELECTRIC - OUTDOOR LIGHTING RCHANDLER Approved
09/27/2019 REINFORCED MASONRY PRE-GROUT RCHANDLER Approved
09/27/2019 MECHANICAL - FINAL RCHANDLER Approved
09/27/2019 EXCAVATION/LAYOUT REBAR & ZON RCHANDLER Approved
09/27/2019 U VALUE FOR WINDOW RCHANDLER Approved
10/04/2019 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER DISINFECTION REPORT COMPLETED
10/10/2019 NPPO - FINAL BBENEDON Approved
10/15/2019 SIGN - FINAL BBENEDON Approved
10/15/2019 LANDSCAPE - FINAL BBENEDON Approved Will inspect landscaping under the development package permit
10/16/2019 OUTDOOR LIGHTING FINAL TVALENCIA Approved
10/16/2019 ELECTRIC - INTERMEDIATE TVALENCIA Approved
10/17/2019 PLUMBING - INTERMEDIATE TVALENCIA Approved APPROVED PER 3090 APPROVAL
10/17/2019 FRAMING TVALENCIA Approved APPROVED PER 1090 APPROVAL
10/17/2019 ELECTRIC - FINAL TVALENCIA Approved
10/17/2019 FIRE - FINAL jvincent Approved
11/06/2019 BUILDING - FINAL TVALENCIA Approved
11/06/2019 RIGHT OF WAY - FINAL BBENEDON Approved
11/06/2019 ENGINEERING - FINAL BBENEDON Approved