Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/27/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
09/23/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Canceled by contractor | |
08/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | canopy footings OK | |
08/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | vacuum enclosure footings OK | |
07/15/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Steel reinforcement provided in Canopy footings. | |
06/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | no new work | |
06/18/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | light pole bases OK to pour | |
06/05/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Pole bases not complete | |
06/04/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | maintenance bay OK except trash pit. | |
06/03/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Car was tunnel, remove all loose base course against trench forms and rebar before concrete placement, ok to pour concrete | |
05/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Trash pit footing in center of building, ok to pour. | |
04/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Trench footing per detail 109 pending plates | |
04/26/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | All perimeter footing an footing interior at Far East. OK to pour. Interior large H footing will be called in for Cthulhu and steel next week |
|
04/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Will call when complete. |