Permit: T18CM09059

Parcel: 132131010


Addresses:

2975 S KINO PW

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
07/31/2019 PLUMBING - ROUGH, SOIL Approved 2" piping for reverse osmosis system from building to holding tanks, ok to backfill
07/25/2019 PLUMBING - ROUGH, SOIL Partial Approval Water reclamation piping and 3 tanks. Overflow line to sand and oil tank at end hook up.

Tracer wires in place, all piping pressure tested.

6" piping for rain water catcher extended to catch basin.
06/05/2019 PLUMBING - ROUGH, SOIL Partial Approval APPROVED BY MIKE HASSAN BUT REOPENED FOR REINSPECTION
06/04/2019 PLUMBING - ROUGH, SOIL Partial Approval no new work
06/03/2019 PLUMBING - ROUGH, SOIL Not ready for Inspection No new work at this time
05/28/2019 PLUMBING - ROUGH, SOIL Partial Approval OK within footprint of building
05/20/2019 PLUMBING - ROUGH, SOIL Partial Approval Sewer trench from oil water separate to south side and northeast side of building
05/14/2019 PLUMBING - ROUGH, SOIL Partial Approval Men’s/women’s bathrooms, mop sink, and drinking fountain, ok to backfill
05/06/2019 PLUMBING - ROUGH, SOIL Partial Approval site sewer from property line to oil water separator ok