Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 09/27/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
|
| 08/26/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Correction Required |
Previous corrections not completed. |
| 08/16/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
vacuum enclosures OK to grout and are structurally fine, however there is no approved sketch on these enclosures, please have ASK stamped and included in the approved drawings. |
| 07/03/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
South and west walls of car wash: Final lift, ok to grout |
| 07/01/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
mechanical room ok to top out, tunnel west and north ok to grout 4th lift. Make sure verticals penetrate bond beam on top out. |
| 06/26/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
top out on center wall and north wall OK to grout, also fourth lift on east wall OK to grout. |
| 06/25/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
third lift on car wash tunnel OK to grout. |
| 06/20/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
3rd lift ok to grout on 4 east side mechanical room walls |
| 06/18/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
second lift on car wash tunnel OK to grout |
| 06/14/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK to grout second lift mechanical room |
| 06/12/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1st lift |