Permit: T18CM09059
Permit Details
Apply Date:
11/14/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
CAR WASH
Architects:
- A23 STUDIOS
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T18CM09059
Permit Status: C of o
Permit Description: CAR WASH
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/29/2019 | POST 3RD PARTY REVIEW | 03/12/2019 | COMPLETED |
03/12/2019 | POST 3RD PARTY REVIEW | 04/05/2019 | COMPLETED |
07/09/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 07/09/2019 | COMPLETED |
07/09/2019 | POST 3RD PARTY REVIEW | 07/09/2019 | COMPLETED |
07/11/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 07/11/2019 | COMPLETED |
07/11/2019 | POST 3RD PARTY REVIEW | 07/12/2019 | COMPLETED |
08/23/2019 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 08/23/2019 | COMPLETED |
10/01/2019 | REVISION - - 4TH | 10/02/2019 | COMPLETED |
11/14/2018 | PLANS OK TO SUBMIT - COMM | 11/14/2018 | COMPLETED |
11/16/2018 | 3RD PARTY REVIEW - COMMERCIAL | 12/27/2018 | COMPLETED |
12/27/2018 | POST 3RD PARTY REVIEW | 01/29/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09059
Permit Status: C of o
Permit Description: CAR WASH
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/14/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM09059
Permit Description: CAR WASH
Total Completed Inspections - 40
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/25/2019 | ELECTRIC - UFER | GWEST | Approved | UFER with #4 GEC |
05/14/2019 | STEM WALL/RETAINING WALL | AKLEINSORGE | Approved | Interior stem wall between car wash and mechanical room, ok to pour |
06/05/2019 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | |
06/05/2019 | PLUMBING - PRE SLAB | RCAMACHO | Approved | |
06/05/2019 | BUILDING PRE-SLAB | RCAMACHO | Approved | |
07/31/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | 2" piping for reverse osmosis system from building to holding tanks, ok to backfill |
07/31/2019 | ROOF NAILING | AKLEINSORGE | Approved | Obs over barrel trusses on north/south sides of wash tunnel |
07/31/2019 | EXT METAL CLIPS/EXT SHEATHING | AKLEINSORGE | Approved | Exterior sheathing for north/south towers and bump out on east/west sides of building |
08/02/2019 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE ECO |
08/02/2019 | ELECTRIC - CABLE DROP | RCHANDLER | Approved | ECO |
08/14/2019 | SHEET ROCK NAILING | MHASSAN | Approved | |
08/14/2019 | STUCCO MESH | MHASSAN | Approved | |
08/26/2019 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | Clearance SWG. OK to set meter. |
08/26/2019 | PLUMBING - MD GAS/PRECONST MTG | RCHANDLER | Approved | |
08/26/2019 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | |
09/06/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
09/16/2019 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
09/16/2019 | BUILDING ABOVE CEILING | ESTEVENS | Approved | |
09/16/2019 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
09/16/2019 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | |
09/27/2019 | GAS CLEARANCE | RCHANDLER | Approved | |
09/27/2019 | PLUMBING - GAS PRESS TEST FNL | RCHANDLER | Approved | Clearance SWG. OK to connect. |
09/27/2019 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | |
09/27/2019 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | |
09/27/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
09/27/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
09/27/2019 | U VALUE FOR WINDOW | RCHANDLER | Approved | |
10/04/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
10/10/2019 | NPPO - FINAL | BBENEDON | Approved | |
10/15/2019 | SIGN - FINAL | BBENEDON | Approved | |
10/15/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | Will inspect landscaping under the development package permit |
10/16/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
10/16/2019 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | |
10/17/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | APPROVED PER 3090 APPROVAL |
10/17/2019 | FRAMING | TVALENCIA | Approved | APPROVED PER 1090 APPROVAL |
10/17/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
10/17/2019 | FIRE - FINAL | jvincent | Approved | |
11/06/2019 | BUILDING - FINAL | TVALENCIA | Approved | |
11/06/2019 | RIGHT OF WAY - FINAL | BBENEDON | Approved | |
11/06/2019 | ENGINEERING - FINAL | BBENEDON | Approved |