Permit: T18CM05426
Permit Details
Apply Date:
07/12/2018
Applicant:
JENNIFER KIMURA
Description:
SHELL BLDG
Contractors:
- NITTI BUILDERS LLC
Permit Reviews
Permit Number - T18CM05426
Permit Status: Expired
Permit Description: SHELL BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/12/2018 | COMMERCIAL - NEW | 07/12/2018 | COMPLETED |
07/12/2018 | COMMERCIAL - NEW | 09/05/2018 | COMPLETED |
09/05/2018 | RESUBMITTAL | 10/11/2018 | COMPLETED |
10/11/2018 | RESUBMITTAL | 10/19/2018 | COMPLETED |
10/19/2018 | RESUBMITTAL | 11/08/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM05426
Permit Status: Expired
Permit Description: SHELL BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/12/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T18CM05426
Permite Description: SHELL BLDG
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/26/2018 | ZONING - FINAL | N/A | Prior to Final Inspectn | Verify construction trailer has been removed from adjacent property prior to final and c of o. |
Completed Inspections
Permit Status: Expired
Permit Number: T18CM05426
Permit Description: SHELL BLDG
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/23/2019 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
01/29/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
02/28/2019 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | underground from transformer to pedestal and to main sub panel ok to backfill |
04/09/2019 | BUILDING PRE-SLAB | RCAMACHO | Approved | canceled |
05/28/2019 | ROOF NAILING | MHASSAN | Approved | |
06/17/2019 | BUILDING - PROGRESS | GWEST | Approved | |
06/28/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | approval is for remaining pour back strip 30’ near large opening SE corner, and remaining 150’ from fire riser room south. |
08/20/2019 | PLUMBING - GAS PRESSURE TEST | AKLEINSORGE | Approved | 6 gas lines stubbed out near northwest corner of building, under pressure and acceptable |
08/21/2019 | PLUMBING - ROOF DRAINS | MHASSAN | Approved | overflows continue to fail test at bottom 90. Please add additional support at the top of those 90s so this won’t continue to happen. |
08/30/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
08/30/2019 | SITE - SEWER | DMUNIZ | Approved | |
09/03/2019 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | 1- Electric above the ceiling is okay between grid lines A,2,8,10 & 14 only. |
10/09/2019 | ELECTRIC - UNDERGROUND | JCLAXTON | Approved | 10 mains, 1 secondary. |
11/13/2019 | TEP CLEARANCE - AM | TVALENCIA | Approved | meter # 1 CODE ECO |
11/13/2019 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | Clear electric eco meter # 1 only |
11/19/2019 | ELECTRIC - OUTDOOR LIGHTING | JCLAXTON | Approved | Ok to proceed |
11/19/2019 | ELECTRIC - PROGRESS | JCLAXTON | Approved | All lighting done, all emergency lighting interior, exterior all working. |
11/19/2019 | ELECTRIC - INTERMEDIATE | JCLAXTON | Approved | |
12/06/2019 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
12/06/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
12/06/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
12/06/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
12/16/2019 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
12/16/2019 | FIREWALL/FIREBARRIER/FIRESTOP | DMUNIZ | Approved | |
12/16/2019 | FRAMING | DMUNIZ | Approved | |
12/16/2019 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | |
12/16/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
12/17/2019 | ENGINEERING - FINAL | BBENEDON | Approved | Complete work shown on DP |
12/19/2019 | FIRE - FINAL | JPEELDAVIS | Approved | |
12/19/2019 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
12/19/2019 | FIRE - FINAL | JPEELDAVIS | Approved | OK FOR TCO TO OCCUPY Need to verify all venting & operations including the fire pump room Need to verify the gate operation Need to install KNOX cap on the Stortz |
12/23/2019 | BUILDING - FINAL | WGALLAGHER | Approved | Waiting on zoning approval |
01/07/2020 | PLUMBING - FINAL | WGALLAG1 | Approved | PER 1090 APPROVAL |