Permit: T18CM05426

Parcel: 140418480


Addresses:

6850 S BROSIUS AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T18CM05426

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
06/28/2019 EXCAVATION/LAYOUT REBAR & ZON Approved approval is for remaining pour back strip 30’ near large opening SE corner, and remaining 150’ from fire riser room south.
06/26/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Closure pour for west side, from last overhead door to 10’ south of FDC risers in NW corner, ok for concrete placement
06/17/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Open line item up if closed as more to go.
Rebar mat and dowels fro man door south to west wall ribbon north to north wall
06/13/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection this appears to be for the pour back strip along the west side of the building. Clearances not maintained, clean up debris, complete work on PVC piping and backfill, missing formwork on northern side. Need to see detail on drawing Jobsite trailer locked up at 10am.
06/12/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Slab closure pour: East side of building between Grid 2 to 13 and Grid 14 to 15 and south end between Gird A to D.5 and dock levelers floor only along west side of building. Ok to pour, clean trash from area before placement and epoxy missing rebar in tilt planes in southeast corner. Special inspection will need to be done for epoxy installed rebar.
03/28/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Tilt panels 3 thru 13 ok to pour
01/31/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GL A 15 ok to pour
01/30/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GL F from 9-15 & GL 15 from E-F per detail 2/S2.0
See highlighted S1.0 & S1.1 plan
01/29/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval from grid lines 1 through 10 on F West side. From grid lines 8 through 10 on A Eastside. See highlighted drawing on site
01/28/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Footing on North side and East from grid lines 1-8
01/23/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval all interior spot footings OK