Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 01/07/2020 |
BUILDING PRE-SLAB |
|
Approved |
PER 1090 APPROVAL |
| 04/09/2019 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
canceled |
| 03/07/2019 |
BUILDING PRE-SLAB |
|
Approved |
last section gridline 6 to 9 |
| 03/06/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Between Grids A to F / 9 to 12 |
| 02/27/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Grid lines a-f and 12-15 |
| 02/26/2019 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
Need more rebar to complete |
| 02/20/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Middle slab ok to pour |
| 02/13/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
GL A-F from 1 to 6 only |
| 02/12/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
North 1/3 of slab OK to pour |
| 02/08/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
Mid 1/3 of slab ok to pour |
| 02/07/2019 |
BUILDING PRE-SLAB |
|
Partial Approval |
North slab section OK to pour |
| 02/04/2019 |
BUILDING PRE-SLAB |
|
Not ready for Inspection |
|