Permit: T17CM02634
Permit Details
Apply Date:
04/05/2017
Applicant:
N/A
Description:
SITE UTILITY PLAN
Contractors:
- BRASFIELD AND GORRIE L L C ,
Permit Reviews
Permit Number - T17CM02634
Permit Status: Final
Permit Description: SITE UTILITY PLAN
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/05/2017 | PLANS OK TO SUBMIT - COMM | 04/05/2017 | COMPLETED |
04/05/2017 | COMMERCIAL - NEW | 04/26/2017 | COMPLETED |
05/17/2017 | RESUBMITTAL | 06/01/2017 | COMPLETED |
06/07/2017 | RESUBMITTAL | 06/15/2017 | COMPLETED |
11/02/2018 | REVISION - - 1ST | 12/05/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T17CM02634
Permit Status: Final
Permit Description: SITE UTILITY PLAN
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/05/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM02634
Permit Description: SITE UTILITY PLAN
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/10/2017 | ELECTRIC - PROGRESS | RCAMACHO | Approved | 20 EACH 5" CONDUIT FROM APPROX. GRID LINE N 80 WEST ONLY |
10/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | CANCELED |
12/19/2017 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | PRECON WITH TONY (SUN MECHANICAL) TEST FACILITY |
12/20/2017 | SITE - SEWER | RCAMACHO | Approved | AFTER HOURS APA ACCOUNT $165.00 FROM BACKWATER VALVE AT FIRE PUMP TO 1ST CLEANOUT WEST SOUTH OF MULTI PURPOSE BUILDING |
12/27/2017 | PLUMBING - YARD WTR LINE/TEST | mramber1 | Approved | fire line to be inspected by F.D. |
12/28/2017 | ELECTRIC - UNDERGROUND | rbaldwin | Approved | 20-5" conduit approx 60' at tep |
12/29/2017 | MECHANICAL - UNDERGROUND | rbaldwin | Approved | 4" stub ne corner T's to valve ok to insulate |
04/10/2018 | BUILDING PRE-SLAB | RBALDWIN | Approved | 5 VAULT LIDS WEST SIDE ATF |
04/13/2018 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | CANCELED |
10/15/2018 | MECHANICAL - PROGRESS | RCAMACHO | Approved | |
03/27/2019 | PLUMBING - GAS PRESS TEST FNL | RCAMACHO | Approved | See permit T17CM03512 |
03/27/2019 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | See permit T17CM03512 |
03/27/2019 | MECHANICAL - FINAL | RCAMACHO | Approved | |
03/27/2019 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | |
03/27/2019 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | |
04/16/2019 | FIRE - FINAL | JPEELDAVIS | Approved | |
06/18/2019 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | based on acceptance of authority to discharge document that’s her. |
06/18/2019 | PLUMBING - PROGRESS | BSTEVENS | Approved | based on acceptance of authority to discharge document that’s her. |
10/04/2019 | PLUMBING - FINAL | TVALENCIA | Approved | |
10/04/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
10/04/2019 | BUILDING - FINAL | TVALENCIA | Approved |