Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
Permit Number - T17CM02634
Inspection Description - ELECTRIC - UNDERGROUND
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/27/2019 | ELECTRIC - UNDERGROUND | Approved | ||
04/19/2018 | ELECTRIC - UNDERGROUND | Partial Approval | APPROX 320' OF 2-1" CONDUITS FEEDIING LIGHT POLES ON W SIDE ATF | |
04/18/2018 | ELECTRIC - UNDERGROUND | Partial Approval | APPROX 500' OF 1" BETWEEN LIGHT POLES ON ESAT SIDE ATF | |
04/17/2018 | ELECTRIC - UNDERGROUND | Partial Approval | LIGHT POLE BSES COMPLETE ON SITE | |
04/10/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 2 SETS OF 26-4" FROM ATS VAULTS HEADING NORTH APPROX 100" | |
04/04/2018 | ELECTRIC - UNDERGROUND | Partial Approval | STUB UP AT 2 SWITCH GEARS AND 2 TRANSFORMERS WEST SIDE ATF | |
04/02/2018 | ELECTRIC - UNDERGROUND | Partial Approval | STUB UP AT CONTROL BLD IN ELECTRIC FIELD | |
03/29/2018 | ELECTRIC - UNDERGROUND | Cancelled | ||
03/28/2018 | ELECTRIC - UNDERGROUND | Not ready for Inspection | ||
03/23/2018 | ELECTRIC - UNDERGROUND | Not ready for Inspection | ||
03/22/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 4-1" FROM WAST SIDE MPB TO LIGHT POLE | |
03/21/2018 | ELECTRIC - UNDERGROUND | Partial Approval | STUB UPS AT CUP 20-4",10-4",24-3", 8-2" &3-11/2" | |
03/19/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 12-4" conduits tie in to mo6 vault 10- 4' CONDUITS CONTINUATION OF CLASSIFIED TO PARKING LOT AT MO6 VAULT | |
03/16/2018 | ELECTRIC - UNDERGROUND | Partial Approval | app 85' of 22-4" conduits continuation to mo6 vault | |
03/14/2018 | ELECTRIC - UNDERGROUND | Partial Approval | approx 90' of 22-4" at com bank to mo6, 32-3",6-11/2", 18-2" 1-4" at cup ok to cover | |
03/12/2018 | ELECTRIC - UNDERGROUND | Partial Approval | app 30' of 10-2" for pv at east side mpb approx 160' 2-3/4" from mpb to pump on east side | |
03/09/2018 | ELECTRIC - UNDERGROUND | Partial Approval | approx 140' 10-4" com conduits from road crossing heading south @atf 18-4" complete from 918 vault to vaults west side atf | |
03/08/2018 | ELECTRIC - UNDERGROUND | Partial Approval | ||
03/07/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 4 light pole footings and grounding at nw mpb | |
03/06/2018 | ELECTRIC - UNDERGROUND | Partial Approval | tie in to mpb com vaults ok to cover | |
03/05/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 4 light pole footings and grounding north side mpb, 1" conduit feeding same poles far east parking lot light pole foooting and grounding, 40' 18-4" com conduit continuation east from vault 918 | |
03/02/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 32-4" from 918 cim vault app 50' to south 5 light pole footings and grounding east side mpb 1" conduit at east mpb road crossing app 60" 1" conduit between east 2 light poles north side mpb | |
03/01/2018 | ELECTRIC - UNDERGROUND | Partial Approval | approx 60' pf 18- 4" conduits west side atf vaults heading east | |
02/28/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 90' 10-4" comm conduits at mpb road crossing, 2 sets of 4-5" 60' &120 from medium voltage vaults to services south side mpb, 300' 1" between light poles east side mpb | |
02/27/2018 | ELECTRIC - UNDERGROUND | Not ready for Inspection | ||
02/23/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 20' of 4-2" 480 conduits to life safety vault atf 4-5" conduit to medium voltage vault | |
02/14/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 2- 4' secondary lines from transformer to service. approx 120' 3/4" between 2 north site light poles | |
02/09/2018 | ELECTRIC - UNDERGROUND | Not ready for Inspection | ||
02/08/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 8-5",8-4" 10-2" conduits from MBE duct bank to medium voltage and life safety vaults | |
02/07/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 2-4" approx 80' to vault se corner mpb | |
02/06/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 2-4" conduits approx 320' east side mpb | |
02/05/2018 | ELECTRIC - UNDERGROUND | Cancelled | ||
01/25/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 20- 5" conduits tie in at duct bank at TEP vaults north of K12 | |
01/22/2018 | ELECTRIC - UNDERGROUND | Not ready for Inspection | CANCELED | |
01/18/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 8X5", 6X2", 2X4", 4X2" AND 1X3"DUCT BANK EAST OF VAULTS WEST OF ATF TO SWITCHGEAR MPB DUCT BANK | |
01/11/2018 | ELECTRIC - UNDERGROUND | Partial Approval | CUP FUTURE EQUIPMENT 8X5" CONDUIT, 4X4" CONDUIT AND 8X2" CONDUIT 4X5" CONDUIT FROM ELECTRICAL VAULTS TO ATF BUILDING GROM VAULT TO VAULT1500 KV WEST OF ATF |
|
01/08/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 20-5" CONDUIT NORTH OF TEST FACILITIES DUCT BANK | |
01/03/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 20-5" CONDUIT DUCT BANK NORTH OF TEST FACILITY 100' | |
12/28/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 20-5" conduit approx 60' at tep | |
12/27/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 20-5" = 50' along road west | |
12/27/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 20-5" conduits appox 20' at t&p duct bank, 10-5" conduits @ ses vaults, 2-5" conduits approx 60' at location 917 | |
12/26/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 20-5" PVC conduit approx 40' west along road ok to slurry | |
12/18/2017 | ELECTRIC - UNDERGROUND | Not ready for Inspection | CANCELED | |
12/15/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 2EACH 4" CONDUIT NORTH OF K-12 FENCE THRU VAUOLT TO VISITOR CENTER ONLY 16 EACH 5" CONDUIT SOUTH OF ROAD 60' AFTER BEND 4 EACH 5" CONDUIT SAME AREA 60' FOR FUTURE TO RAYTHEON |
|
12/13/2017 | ELECTRIC - UNDERGROUND | Not ready for Inspection | NO WORK | |
12/06/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 16 PIECES 5" CONDUIT DUCT BANK TIE INTO TEP VAULT SOUTH EACH WAY | |
11/21/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 30' OF 5" CONDUIT 10 PIECES DUCT BANK EAST OF 917 | |
11/20/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 80' DUCT BANK 10 PIECES 5" NORTH OF 917 ONLY | |
11/16/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 16 PIECES 5" CONDUIT DUCT BANK APPROX. 20' FROM SOUTH TEP VAULT ONLY | |
11/15/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 10 EACH 5' CONDUIT AT DUCT BANK TIED INTO 919A VAULT EAST SIDE 10 EACH 5' CONDUIT DUCT BANK TIED INTO 919 B VAULTEAST SIDE |
|
11/14/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 20'- 16 PIECES 5" CONDUIT NORTH OF 11/16 INSPECTRION BY TEMP FENCE | |
11/13/2017 | ELECTRIC - UNDERGROUND | Partial Approval | DUCT BANK 16 PIECES 5" CONDUIT APPROX. 60' SOUTH OF LAST INSPECTION 22 EACH POLE LIGHT BASES EAST END OF MULTI PURPOSE BUILDING PARKING LOT ONLY SEE RFI FOR ADDITION OF VERTICAL STEEL |
|
11/06/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 140' OF 5" CONDUIT 16 PIECES EAST OF MULTI PURPOSE BUILDING PARKING LOT PENDING RFI | |
10/26/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 4 EACH 5" CONDUIT NORTH OF 9/17 10 EACH 5" CONDUIT RUNNING EAST DIRECTION 1 SECTION ONLY |
|
10/19/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 20 EACH 5" CONDUIT TIED INTO VAULTS SE/SA AND 20 EACH INTO SE/SB 7- 5" CONDUIT TIE BREAKER OK TO COVER AND POUR |
|
10/17/2017 | ELECTRIC - UNDERGROUND | Partial Approval | multi purpose parking, lot lights and future solar UG conduit ok | |
10/10/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 20 EACH 5" CONDUIT FROM APPROX. GRID LINE N 80 WEST ONLY | |
10/09/2017 | ELECTRIC - UNDERGROUND | Partial Approval | BEFORE HOURS APA ACCOUNT $165.00 8 EACH 4" CONDUIT 10 EACH 2" CONDUIT 8 EACH 5" CONDUIT ALL AT ROAD CROSSING ONLY CUP WEST DUCT BANK EAST AND WEST 5" CONDUIT 18 EACH ONLY |
|
09/29/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 8EACH 5" CONDUIT FROM NORTH VAULT TO BEND OK TO ENCASE ONLY | |
09/26/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 18-6" conduit approx 50' from street south 80' ok to encase | |
08/10/2017 | ELECTRIC - UNDERGROUND | Not ready for Inspection | CANCELED |