Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - UNDERGROUND
Permit Number - T17CM02634
Inspection Description - MECHANICAL - UNDERGROUND
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/15/2018 | MECHANICAL - UNDERGROUND | Approved | ||
08/10/2018 | MECHANICAL - UNDERGROUND | Partial Approval | IVRS - Inspection :* COMPLETION OF UNDERGROUND PENDING TEST FROM STREET VALVE TO HEAT EXCHANGER |
|
08/09/2018 | MECHANICAL - UNDERGROUND | Partial Approval | WRAP AND INSULATION 4 COUPLINGS FROM PREVIOUS INSPECTION DATA CENTER EXCEPT AT RISERS INTO HEAT EXCHANGER RESTRAINING BOLTS AT LAST 2 COUPLINGS AT RISERS OK TO INSULATE AND WRAP |
|
08/08/2018 | MECHANICAL - UNDERGROUND | Partial Approval | RESTRAINING BOLTS 5 JOINTS COUPLINGS 2 EACH AT 4" LINES FROM EXISTING TO RISERS AT DATA CENTER TO BE TESTED AT LATER DATE OK TO INSULATE AND WRAP JOINTS | |
08/07/2018 | MECHANICAL - UNDERGROUND | Not ready for Inspection | IVRS - Inspection :* | |
04/04/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 200PSI TEST ON ENTIRE UNDERGROUND SYSTEM OK | |
03/28/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 3/27 120 OF 2-4" LINES FROM16" TO STUB UPS OK TO INSULATE. INSULATION APPROVED3/28 | |
03/22/2018 | MECHANICAL - UNDERGROUND | Partial Approval | OK TO BACKFILL FROM TIE IN TO VALVES ON WEST SIDE ATF | |
03/21/2018 | MECHANICAL - UNDERGROUND | Partial Approval | CONCRETE SUPPORT FOR 4" VALVES | |
03/20/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 2-16" ELBOWS 2-16=X4" TEES NW CORNER ATF OK TO INSULATE | |
03/16/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 4-16" joints west side atb tie in heading west ok to insulate | |
03/13/2018 | MECHANICAL - UNDERGROUND | Partial Approval | next 4 16" joints heading north insulation ok next 2 16" joints heading north ok to insulate | |
03/09/2018 | MECHANICAL - UNDERGROUND | Partial Approval | next 4 16" joints heading north ok to insulate | |
03/02/2018 | MECHANICAL - UNDERGROUND | Partial Approval | insulation on next 2 16" joints headig north | |
02/23/2018 | MECHANICAL - UNDERGROUND | Partial Approval | insulation on 4' lines to control room, 2-16" couplings, 2 valves and 2 12" vertical elbows west side atf | |
02/22/2018 | MECHANICAL - UNDERGROUND | Partial Approval | ||
02/21/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 2=12" lines from 16' towards atf 4" line from16" to control room ok to insulate | |
02/14/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 1-16" t to 4" on east line west side atf | |
02/12/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 2- 16" 90's and 1 coupleing on east line heading north ok to insulate | |
02/07/2018 | MECHANICAL - UNDERGROUND | Partial Approval | ||
02/06/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 2-16" joints heading east on west side of atf | |
02/05/2018 | MECHANICAL - UNDERGROUND | Partial Approval | insulation on 2 elbows,2 couplings and 2 risers on west side atf | |
02/02/2018 | MECHANICAL - UNDERGROUND | Partial Approval | w side atf 2- 16" elbows ok to insulate, 4- 16" joints w side atf insulation ok | |
02/01/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 2 16" lines west side of cut heading north at atf 2 couplings and 2 elbows ok to insulate | |
01/31/2018 | MECHANICAL - UNDERGROUND | Cancelled | ||
01/22/2018 | MECHANICAL - UNDERGROUND | Not ready for Inspection | CANCELED | |
01/19/2018 | MECHANICAL - UNDERGROUND | Not ready for Inspection | ||
01/18/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 2EACH 8" LINES UP TO MPB NORTH END VALVES AND RISER SPRAY FOAMED AND COUPLINGS INSULATED 2EACH 4" RISERS SOUTH END OF MPB OK TO INSULATE TO BE TESTED AT A LATER DATE |
|
01/17/2018 | MECHANICAL - UNDERGROUND | Partial Approval | IVRS - Inspection :* | |
01/11/2018 | MECHANICAL - UNDERGROUND | Partial Approval | 4" VALVES AND RISER NE CORNER MPB OK TO INSULATE AND WRAP INSULATION AND SPRAY FOAM WITH CONCRETE UNDER VALVES EAST END OF MPB OK TO COVER TO BE TESTED AT A LATER DATE |
|
01/09/2018 | MECHANICAL - UNDERGROUND | Partial Approval | TERMINATION OF 12" LINE INSULATION AND WRAP TO "T" SW CORNER OF MPB VALVES AT 4" PIPE OK TO INSULATE AND WRAP | |
01/03/2018 | MECHANICAL - UNDERGROUND | Partial Approval | MECH JOINTS INSULATED AND WRAPPED TO VALVES NORTH OF MULTI PURPOSE BUILDING 1 EACH 2 JOINTS 12" LINE INSULATED AND WRAPPED SOUTH OF VALVE LOCATED EAST OF MULTI PURPOSE BUILDING TO BE TESTED AT A LATER DATE |
|
12/29/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 4" stub ne corner T's to valve ok to insulate | |
12/28/2017 | MECHANICAL - UNDERGROUND | Partial Approval | ne corner multi purpose next joint, 2 air relief valves n side multi purpose, 4" air handler ne multi purpose | |
12/21/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 5 COUPLINGS 12" LINES EAST OF MULTI PURPOSE BUILDING INSULATED AND WRAPPED 2 EACH VALVES AND 4" COUPL;INGS WITH RESTRAINING BOLTS OF TO INSULATE AND WRAP TO RISERS NW CORNER MULTI PURPOSE BUILDING TO BE TESTED AT LATER DATE |
|
12/20/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 5 EACH 12" COUPLINGS EAST OF MULTI PURPOSE BUILDING RESTRAINING BOLTS OK TO INSULATE AND WRAP TO BE TESTED AT A LATER DATE 8 EACH 12" COUPLINGS EAST OF "T" NORTH OF MULTI PURPOSE BUILDING OK TO INSULATE AND WRAP RESTRAINING BOLTS |
|
12/15/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 6" PIPE TO VALVES RESTRAINING BOLTS OK TO INSULATE AND WRAP 12" PIPE TO 1ST COUPLINGAFTER VALVE OK TO INSULATE AND WRAP NORTH OF MULTI PURPOSE BUILDING |
|
12/13/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 6 COUPLINGS EAST OF VALVE INSULATED AND WRAPPED 7TH COUPLING RESTRAINING BOLTS OK TO WRAP AND INSULATE |
|
12/12/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 6 COUPLINGS EAST OF VALVE NORTH OF MULTI PURPOSE BUILDING RESTRAINING BOLTS OK TO INSULATE AND WRAP | |
12/08/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 1 EACH COUPLING UP TO VALVE NORTH OF MULTI PURPOSE BUILDING RESTRAINIG BOLTS OK TO INSULATE AND WRAP | |
12/07/2017 | MECHANICAL - UNDERGROUND | Partial Approval | AFTER HOURS APA ACCOUNT $165.00 JOINTS FROM 12/6 INSPECTION INSULATED AND WRAPPED NEXT COUPLING RESTRAINING BOLTSOK TO INSULATE AND WRAP NORTH OF MULTI PURPOSE BUILDING RISERS SPRAY FOAMED FROM 12/6 INSPECTION WEST OF MPB |
|
12/06/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 3 COUPLINGS NORTH OF MULTI PURPOSE BUILDING OK TO INSULATE AND WRAP RISERS WEST OF MPB AT TIE IN |
|
12/05/2017 | MECHANICAL - UNDERGROUND | Partial Approval | COUPLINGS FROM 12/4 INSPECTION INSULATED AND WRAPPED LAST COUPLING BEFORE 90AND 90 RETRAINING BOLTS OK TO INSULATE AND WRAP WEST OF MULTIPURPOSE BUILDING |
|
12/04/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 3 JOINTS WEST OF MULTI PURPOSE BUILDING INSULATED AND SHRINK WRAPPED 1 JOINT COUPLING NORTH OF SAME AREA OK TO INSULATE AND WRAP |
|
12/01/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 3 COUPLINGS 60' WITH RESTRAINING BOLTS OK TO INSULATE AND WRAP 30' FROM 90 WEST IF MULTI PURPOSE BUILDING | |
11/30/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 85' OF 8" LINE EAST OF MULTI PURPOSE BUILDING UP TO "T" ONLY | |
11/29/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 4 COUPLING JOINTS AND 90'S 2 EACH WEST OF MULTI PURPOSE BUILDING RESTRAINING BOLTS OK TO INSULATE AND WRAP TO BE TESTED AT A LATER DATE |
|
11/21/2017 | MECHANICAL - UNDERGROUND | Partial Approval | INSULATION AND WRAP FROM PREVIOUS OK TO BE TESTED AT A LATER DATE |
|
11/20/2017 | MECHANICAL - UNDERGROUND | Partial Approval | GRID LINE E FROM 90 TO 90 TO GRID LINE E.5 TO CAPS RESTRAINING BOLTS AT 2 90'S AND 1 COUPLING OK TO INSULATE AND WRAP | |
11/16/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 4 EACH COUPLINGS WITH RESTRAINING BOLTS TO 90'S FROM GRID LINE 1D TO 1E OK TO INSULATE AND WRAP 4" LINE TO BE TESTED AT A LATER DATE | |
11/15/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 2 EACH 4' COUPLINGS AT EXTERIOR OF GRID LINES 1D INSULATED AND WRAPPED TO BE TESTED AT A LATER DATE | |
11/14/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 80' west of 4" valves | |
11/14/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 4" PIPE JOINTS AT GRID LINE 1C EXTERIOR INSULATED AND SHRINK WRAPPED AT 45 NEXT 2 COUP[LINGS RESTRAINING BOLTS OK TO INSULATE AND WRAP EXTERIOR OF GRID LINE 1D TO BE TESTED AT A LATER DATE |
|
11/13/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 4 EACH 4" JPINTS INSULATED AND WRAPPED AT GRID LINE 1B EXTERIOR OF MULTI PURPOSE BUILDING 2 EACH COUPLING RESTRAINING BOLTS GRID LINE C EXTERIOR OF MPB OK TO INSULATE AND WRAP TO BR TESTED AT A LATER DATE |
|
11/09/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 2 EACH 4" LINESNSOUTH OF MULTIPURPOSE BUILDING WEST OF VALVES 3 COUPLINGS INSULATED AND WRAPPED NEXT 2 COUPLINGS WEST RESTRAINING BOLTS OK TO INSULATE AND SHRINK WRAP VALVES CONCRETE POUT BACK OK |
|
11/06/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 4 JOINTS FROM 12" PIPE FROM 11/2 INSPECTION INSULATED AND WRAPPED TO BE TESTED AT A LATER DATE | |
11/03/2017 | MECHANICAL - UNDERGROUND | Not ready for Inspection | WORK NOT COMPLETE | |
11/03/2017 | MECHANICAL - UNDERGROUND | Partial Approval | AFTER HOURS APA ACCOUNT $165.00 NEXT 2 COUPLING JOINTS NORTH AND EAST OF MULTI PURPOSE BUILDING RESTRAINING BOLTS OK T INSULATE AND WRAP ONLY CAP AND SLEEVE AT VALVE BY BUILDING 916 ONLY |
|
11/02/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 2 JOINTS 12" PIPE EAST OF MULTI PUROSE BUILDING RESTRAINING BOLTS OK TO INSULATE AND WRAP ONLY | |
11/01/2017 | MECHANICAL - UNDERGROUND | Not ready for Inspection | cancelled | |
11/01/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 4 EACH 12" JOINTS NORTH OF ROAD INSULATED AND SHRINK WRAPPED ONLY | |
10/30/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 4 JOINTS NORTH OF ROAD WITH VALVES OK TO INSULATE AND SHRINK WRAP ONLY PIPES ENCASED IN CONCRETE AT WASH ONLY |
|
10/24/2017 | MECHANICAL - UNDERGROUND | Partial Approval | ALL PIPE INSULATED AND ALL JOPINTS SPRAY FOAMED AT WASH ONLY | |
10/21/2017 | MECHANICAL - UNDERGROUND | Partial Approval | SECTIONS AT ROADWAY INSULATION AND SHRINK WRAP OK TO BURY | |
10/20/2017 | MECHANICAL - UNDERGROUND | Partial Approval | AFTER HOURS APA ACCOUNT $165.00 RESTRAINING BOLTS COUPLINGS FROM VALVE SOUTH OF ROAD TO NORTH SIDE OF ROAD OK TO INSULATE AND SHRINK WRAP ONLY. TO BE TESTED AT A LATER DATE |
|
10/20/2017 | MECHANICAL - UNDERGROUND | Not ready for Inspection | NO NEW WORK DONE | |
10/19/2017 | MECHANICAL - UNDERGROUND | Partial Approval | SPRAY FOAM AT VALVES SOUTH OF ROAD ONLY SPRAY FOAM 90'S AND 22'S SOUTH OF WASH ONLY |
|
10/18/2017 | MECHANICAL - UNDERGROUND | Partial Approval | RESTRAIMING BOLTS AT VALVES SOUTH OF ROADWAY TO 1ST COUPLING NORTH ONLY | |
10/11/2017 | MECHANICAL - UNDERGROUND | Partial Approval | COUPLINGS 5 AND 6 FROM 90 EAST INSULATION AND SHRINK WRAP OK | |
10/09/2017 | MECHANICAL - UNDERGROUND | Partial Approval | FROM 90 TO 4 JOINTS EAST INSULATED AND SHRINK WRAPPED RESTRAINING BOLTWSN5TH AND 6TH COUPLING EAST OK TO INSULATE AND WERAP ONLY |
|
10/06/2017 | MECHANICAL - UNDERGROUND | Partial Approval | CANCELED BY RICH | |
10/05/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 3RD COUPLING INSULATED AND SHRINK WRAP FROM 3RD COUPEND T OF CHILLERS RESTRAINING BOLTS OK TO INSULATE AND WRAP FROM 3RD COUPLINGTO 90 TO 4 COUPLINGS EAST AT NORTH |
|
10/03/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 2ND COUPLING FROM 90 NORTH INSULATED AND SHRINK WRAPPED 3RD COUPLING RETSTRAINING BOLTS OK TO INSULATE AND SHRINK WRAP ONLY |
|
10/02/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 30' NORTH OF TIE IN 1ST AND 2ND JOINTS RETAINING BOLTS OK TO INSULATE AND SHRINK WRAP WITH 90 TO BE TSTES AT A LATER DATE |
|
09/27/2017 | MECHANICAL - UNDERGROUND | Partial Approval | 16" PIPE TO 1ST JOINT AFTER VALVES TO BE TESTED AT LATER DATE INSULATION AND SHRINK WRAP OK TO COVER |
|
09/26/2017 | MECHANICAL - UNDERGROUND | Partial Approval | TO BE TESTED BY ENGINEER OF RECORD | |
09/22/2017 | MECHANICAL - UNDERGROUND | Partial Approval | SHRINK WRAP OK TO COVER FROM PREVIOUS INSPECTION UP TO DUCTILE IRON ONLY | |
09/21/2017 | MECHANICAL - UNDERGROUND | Partial Approval | FROM 20' OF 45 TO DUCTILE IRON UNDER WASH ONLY TO BE TESTED AT A LATER DATE OK TO INSULATE AND WRAP PIPE |
|
09/12/2017 | MECHANICAL - UNDERGROUND | Partial Approval | OK TO SHADE PIPE FROM GRID LINE L TO E . ALL SHRINK WRAP OK TO COVER TO BE TESTED AT A LATER DATE | |
09/08/2017 | MECHANICAL - UNDERGROUND | Partial Approval | OK TO SHADE PIPE GRID LINE P TO L ALL SHRINK WRAP OK RESTRAINING BOLTS FROM GRID LINE L TO PASSED A 20' FROM 45 OK TO INSULATE AND WRAP TO BE TESTED AT LATER DATE |
|
09/05/2017 | MECHANICAL - UNDERGROUND | Partial Approval | RESTRAINING BOLTS 1ST 5 JOINTS BOTH PIPES OK TO INSSULATE AND SHRINK WRAP FROM GRID LINE P TO L TEST FACILITY TO BE TESTED AT LATER DATE |