Permit: T17CM02634

Parcel: 14043013B


Addresses:

1151 E HERMANS RD


Inspection Status: Approved

Inspection History: MECHANICAL - UNDERGROUND

Permit Number - T17CM02634

Inspection Description - MECHANICAL - UNDERGROUND

Inspection Status - Approved

Date Description Inspector Results Comments
08/15/2018 MECHANICAL - UNDERGROUND Approved
08/10/2018 MECHANICAL - UNDERGROUND Partial Approval IVRS - Inspection :*
COMPLETION OF UNDERGROUND PENDING TEST FROM STREET VALVE TO HEAT EXCHANGER
08/09/2018 MECHANICAL - UNDERGROUND Partial Approval WRAP AND INSULATION 4 COUPLINGS FROM PREVIOUS INSPECTION DATA CENTER EXCEPT AT RISERS INTO HEAT EXCHANGER
RESTRAINING BOLTS AT LAST 2 COUPLINGS AT RISERS OK TO INSULATE AND WRAP
08/08/2018 MECHANICAL - UNDERGROUND Partial Approval RESTRAINING BOLTS 5 JOINTS COUPLINGS 2 EACH AT 4" LINES FROM EXISTING TO RISERS AT DATA CENTER TO BE TESTED AT LATER DATE OK TO INSULATE AND WRAP JOINTS
08/07/2018 MECHANICAL - UNDERGROUND Not ready for Inspection IVRS - Inspection :*
04/04/2018 MECHANICAL - UNDERGROUND Partial Approval 200PSI TEST ON ENTIRE UNDERGROUND SYSTEM OK
03/28/2018 MECHANICAL - UNDERGROUND Partial Approval 3/27 120 OF 2-4" LINES FROM16" TO STUB UPS OK TO INSULATE. INSULATION APPROVED3/28
03/22/2018 MECHANICAL - UNDERGROUND Partial Approval OK TO BACKFILL FROM TIE IN TO VALVES ON WEST SIDE ATF
03/21/2018 MECHANICAL - UNDERGROUND Partial Approval CONCRETE SUPPORT FOR 4" VALVES
03/20/2018 MECHANICAL - UNDERGROUND Partial Approval 2-16" ELBOWS 2-16=X4" TEES NW CORNER ATF OK TO INSULATE
03/16/2018 MECHANICAL - UNDERGROUND Partial Approval 4-16" joints west side atb tie in heading west ok to insulate
03/13/2018 MECHANICAL - UNDERGROUND Partial Approval next 4 16" joints heading north insulation ok next 2 16" joints heading north ok to insulate
03/09/2018 MECHANICAL - UNDERGROUND Partial Approval next 4 16" joints heading north ok to insulate
03/02/2018 MECHANICAL - UNDERGROUND Partial Approval insulation on next 2 16" joints headig north
02/23/2018 MECHANICAL - UNDERGROUND Partial Approval insulation on 4' lines to control room, 2-16" couplings, 2 valves and 2 12" vertical elbows west side atf
02/22/2018 MECHANICAL - UNDERGROUND Partial Approval
02/21/2018 MECHANICAL - UNDERGROUND Partial Approval 2=12" lines from 16' towards atf 4" line from16" to control room ok to insulate
02/14/2018 MECHANICAL - UNDERGROUND Partial Approval 1-16" t to 4" on east line west side atf
02/12/2018 MECHANICAL - UNDERGROUND Partial Approval 2- 16" 90's and 1 coupleing on east line heading north ok to insulate
02/07/2018 MECHANICAL - UNDERGROUND Partial Approval
02/06/2018 MECHANICAL - UNDERGROUND Partial Approval 2-16" joints heading east on west side of atf
02/05/2018 MECHANICAL - UNDERGROUND Partial Approval insulation on 2 elbows,2 couplings and 2 risers on west side atf
02/02/2018 MECHANICAL - UNDERGROUND Partial Approval w side atf 2- 16" elbows ok to insulate, 4- 16" joints w side atf insulation ok
02/01/2018 MECHANICAL - UNDERGROUND Partial Approval 2 16" lines west side of cut heading north at atf 2 couplings and 2 elbows ok to insulate
01/31/2018 MECHANICAL - UNDERGROUND Cancelled
01/22/2018 MECHANICAL - UNDERGROUND Not ready for Inspection CANCELED
01/19/2018 MECHANICAL - UNDERGROUND Not ready for Inspection
01/18/2018 MECHANICAL - UNDERGROUND Partial Approval 2EACH 8" LINES UP TO MPB NORTH END VALVES AND RISER SPRAY FOAMED AND COUPLINGS INSULATED
2EACH 4" RISERS SOUTH END OF MPB OK TO INSULATE TO BE TESTED AT A LATER DATE
01/17/2018 MECHANICAL - UNDERGROUND Partial Approval IVRS - Inspection :*
01/11/2018 MECHANICAL - UNDERGROUND Partial Approval 4" VALVES AND RISER NE CORNER MPB OK TO INSULATE AND WRAP
INSULATION AND SPRAY FOAM WITH CONCRETE UNDER VALVES EAST END OF MPB OK TO COVER TO BE TESTED AT A LATER DATE
01/09/2018 MECHANICAL - UNDERGROUND Partial Approval TERMINATION OF 12" LINE INSULATION AND WRAP TO "T" SW CORNER OF MPB VALVES AT 4" PIPE OK TO INSULATE AND WRAP
01/03/2018 MECHANICAL - UNDERGROUND Partial Approval MECH JOINTS INSULATED AND WRAPPED TO VALVES NORTH OF MULTI PURPOSE BUILDING
1 EACH 2 JOINTS 12" LINE INSULATED AND WRAPPED SOUTH OF VALVE LOCATED EAST OF MULTI PURPOSE BUILDING TO BE TESTED AT A LATER DATE
12/29/2017 MECHANICAL - UNDERGROUND Partial Approval 4" stub ne corner T's to valve ok to insulate
12/28/2017 MECHANICAL - UNDERGROUND Partial Approval ne corner multi purpose next joint, 2 air relief valves n side multi purpose, 4" air handler ne multi purpose
12/21/2017 MECHANICAL - UNDERGROUND Partial Approval 5 COUPLINGS 12" LINES EAST OF MULTI PURPOSE BUILDING INSULATED AND WRAPPED
2 EACH VALVES AND 4" COUPL;INGS WITH RESTRAINING BOLTS OF TO INSULATE AND WRAP TO RISERS NW CORNER MULTI PURPOSE BUILDING
TO BE TESTED AT LATER DATE
12/20/2017 MECHANICAL - UNDERGROUND Partial Approval 5 EACH 12" COUPLINGS EAST OF MULTI PURPOSE BUILDING RESTRAINING BOLTS OK TO INSULATE AND WRAP TO BE TESTED AT A LATER DATE
8 EACH 12" COUPLINGS EAST OF "T" NORTH OF MULTI PURPOSE BUILDING OK TO INSULATE AND WRAP RESTRAINING BOLTS
12/15/2017 MECHANICAL - UNDERGROUND Partial Approval 6" PIPE TO VALVES RESTRAINING BOLTS OK TO INSULATE AND WRAP
12" PIPE TO 1ST COUPLINGAFTER VALVE OK TO INSULATE AND WRAP NORTH OF MULTI PURPOSE BUILDING
12/13/2017 MECHANICAL - UNDERGROUND Partial Approval 6 COUPLINGS EAST OF VALVE INSULATED AND WRAPPED
7TH COUPLING RESTRAINING BOLTS OK TO WRAP AND INSULATE
12/12/2017 MECHANICAL - UNDERGROUND Partial Approval 6 COUPLINGS EAST OF VALVE NORTH OF MULTI PURPOSE BUILDING RESTRAINING BOLTS OK TO INSULATE AND WRAP
12/08/2017 MECHANICAL - UNDERGROUND Partial Approval 1 EACH COUPLING UP TO VALVE NORTH OF MULTI PURPOSE BUILDING RESTRAINIG BOLTS OK TO INSULATE AND WRAP
12/07/2017 MECHANICAL - UNDERGROUND Partial Approval AFTER HOURS APA ACCOUNT $165.00
JOINTS FROM 12/6 INSPECTION INSULATED AND WRAPPED
NEXT COUPLING RESTRAINING BOLTSOK TO INSULATE AND WRAP NORTH OF MULTI PURPOSE BUILDING
RISERS SPRAY FOAMED FROM 12/6 INSPECTION WEST OF MPB
12/06/2017 MECHANICAL - UNDERGROUND Partial Approval 3 COUPLINGS NORTH OF MULTI PURPOSE BUILDING OK TO INSULATE AND WRAP
RISERS WEST OF MPB AT TIE IN
12/05/2017 MECHANICAL - UNDERGROUND Partial Approval COUPLINGS FROM 12/4 INSPECTION INSULATED AND WRAPPED
LAST COUPLING BEFORE 90AND 90 RETRAINING BOLTS OK TO INSULATE AND WRAP WEST OF MULTIPURPOSE BUILDING
12/04/2017 MECHANICAL - UNDERGROUND Partial Approval 3 JOINTS WEST OF MULTI PURPOSE BUILDING INSULATED AND SHRINK WRAPPED
1 JOINT COUPLING NORTH OF SAME AREA OK TO INSULATE AND WRAP
12/01/2017 MECHANICAL - UNDERGROUND Partial Approval 3 COUPLINGS 60' WITH RESTRAINING BOLTS OK TO INSULATE AND WRAP 30' FROM 90 WEST IF MULTI PURPOSE BUILDING
11/30/2017 MECHANICAL - UNDERGROUND Partial Approval 85' OF 8" LINE EAST OF MULTI PURPOSE BUILDING UP TO "T" ONLY
11/29/2017 MECHANICAL - UNDERGROUND Partial Approval 4 COUPLING JOINTS AND 90'S 2 EACH WEST OF MULTI PURPOSE BUILDING RESTRAINING BOLTS OK TO INSULATE AND WRAP
TO BE TESTED AT A LATER DATE
11/21/2017 MECHANICAL - UNDERGROUND Partial Approval INSULATION AND WRAP FROM PREVIOUS OK
TO BE TESTED AT A LATER DATE
11/20/2017 MECHANICAL - UNDERGROUND Partial Approval GRID LINE E FROM 90 TO 90 TO GRID LINE E.5 TO CAPS RESTRAINING BOLTS AT 2 90'S AND 1 COUPLING OK TO INSULATE AND WRAP
11/16/2017 MECHANICAL - UNDERGROUND Partial Approval 4 EACH COUPLINGS WITH RESTRAINING BOLTS TO 90'S FROM GRID LINE 1D TO 1E OK TO INSULATE AND WRAP 4" LINE TO BE TESTED AT A LATER DATE
11/15/2017 MECHANICAL - UNDERGROUND Partial Approval 2 EACH 4' COUPLINGS AT EXTERIOR OF GRID LINES 1D INSULATED AND WRAPPED TO BE TESTED AT A LATER DATE
11/14/2017 MECHANICAL - UNDERGROUND Partial Approval 80' west of 4" valves
11/14/2017 MECHANICAL - UNDERGROUND Partial Approval 4" PIPE JOINTS AT GRID LINE 1C EXTERIOR INSULATED AND SHRINK WRAPPED AT 45
NEXT 2 COUP[LINGS RESTRAINING BOLTS OK TO INSULATE AND WRAP EXTERIOR OF GRID LINE 1D
TO BE TESTED AT A LATER DATE
11/13/2017 MECHANICAL - UNDERGROUND Partial Approval 4 EACH 4" JPINTS INSULATED AND WRAPPED AT GRID LINE 1B EXTERIOR OF MULTI PURPOSE BUILDING
2 EACH COUPLING RESTRAINING BOLTS GRID LINE C EXTERIOR OF MPB OK TO INSULATE AND WRAP
TO BR TESTED AT A LATER DATE
11/09/2017 MECHANICAL - UNDERGROUND Partial Approval 2 EACH 4" LINESNSOUTH OF MULTIPURPOSE BUILDING
WEST OF VALVES 3 COUPLINGS INSULATED AND WRAPPED NEXT 2 COUPLINGS WEST RESTRAINING BOLTS OK TO INSULATE AND SHRINK WRAP
VALVES CONCRETE POUT BACK OK
11/06/2017 MECHANICAL - UNDERGROUND Partial Approval 4 JOINTS FROM 12" PIPE FROM 11/2 INSPECTION INSULATED AND WRAPPED TO BE TESTED AT A LATER DATE
11/03/2017 MECHANICAL - UNDERGROUND Not ready for Inspection WORK NOT COMPLETE
11/03/2017 MECHANICAL - UNDERGROUND Partial Approval AFTER HOURS APA ACCOUNT $165.00
NEXT 2 COUPLING JOINTS NORTH AND EAST OF MULTI PURPOSE BUILDING RESTRAINING BOLTS OK T INSULATE AND WRAP ONLY
CAP AND SLEEVE AT VALVE BY BUILDING 916 ONLY
11/02/2017 MECHANICAL - UNDERGROUND Partial Approval 2 JOINTS 12" PIPE EAST OF MULTI PUROSE BUILDING RESTRAINING BOLTS OK TO INSULATE AND WRAP ONLY
11/01/2017 MECHANICAL - UNDERGROUND Not ready for Inspection cancelled
11/01/2017 MECHANICAL - UNDERGROUND Partial Approval 4 EACH 12" JOINTS NORTH OF ROAD INSULATED AND SHRINK WRAPPED ONLY
10/30/2017 MECHANICAL - UNDERGROUND Partial Approval 4 JOINTS NORTH OF ROAD WITH VALVES OK TO INSULATE AND SHRINK WRAP ONLY
PIPES ENCASED IN CONCRETE AT WASH ONLY
10/24/2017 MECHANICAL - UNDERGROUND Partial Approval ALL PIPE INSULATED AND ALL JOPINTS SPRAY FOAMED AT WASH ONLY
10/21/2017 MECHANICAL - UNDERGROUND Partial Approval SECTIONS AT ROADWAY INSULATION AND SHRINK WRAP OK TO BURY
10/20/2017 MECHANICAL - UNDERGROUND Partial Approval AFTER HOURS APA ACCOUNT $165.00
RESTRAINING BOLTS COUPLINGS FROM VALVE SOUTH OF ROAD TO NORTH SIDE OF ROAD OK TO INSULATE AND SHRINK WRAP ONLY. TO BE TESTED AT A LATER DATE
10/20/2017 MECHANICAL - UNDERGROUND Not ready for Inspection NO NEW WORK DONE
10/19/2017 MECHANICAL - UNDERGROUND Partial Approval SPRAY FOAM AT VALVES SOUTH OF ROAD ONLY
SPRAY FOAM 90'S AND 22'S SOUTH OF WASH ONLY
10/18/2017 MECHANICAL - UNDERGROUND Partial Approval RESTRAIMING BOLTS AT VALVES SOUTH OF ROADWAY TO 1ST COUPLING NORTH ONLY
10/11/2017 MECHANICAL - UNDERGROUND Partial Approval COUPLINGS 5 AND 6 FROM 90 EAST INSULATION AND SHRINK WRAP OK
10/09/2017 MECHANICAL - UNDERGROUND Partial Approval FROM 90 TO 4 JOINTS EAST INSULATED AND SHRINK WRAPPED
RESTRAINING BOLTWSN5TH AND 6TH COUPLING EAST OK TO INSULATE AND WERAP ONLY
10/06/2017 MECHANICAL - UNDERGROUND Partial Approval CANCELED BY RICH
10/05/2017 MECHANICAL - UNDERGROUND Partial Approval 3RD COUPLING INSULATED AND SHRINK WRAP
FROM 3RD COUPEND T OF CHILLERS RESTRAINING BOLTS OK TO INSULATE AND WRAP FROM 3RD COUPLINGTO 90 TO 4 COUPLINGS EAST AT NORTH
10/03/2017 MECHANICAL - UNDERGROUND Partial Approval 2ND COUPLING FROM 90 NORTH INSULATED AND SHRINK WRAPPED
3RD COUPLING RETSTRAINING BOLTS OK TO INSULATE AND SHRINK WRAP ONLY
10/02/2017 MECHANICAL - UNDERGROUND Partial Approval 30' NORTH OF TIE IN 1ST AND 2ND JOINTS RETAINING BOLTS OK TO INSULATE AND SHRINK WRAP WITH 90
TO BE TSTES AT A LATER DATE
09/27/2017 MECHANICAL - UNDERGROUND Partial Approval 16" PIPE TO 1ST JOINT AFTER VALVES
TO BE TESTED AT LATER DATE
INSULATION AND SHRINK WRAP OK TO COVER
09/26/2017 MECHANICAL - UNDERGROUND Partial Approval TO BE TESTED BY ENGINEER OF RECORD
09/22/2017 MECHANICAL - UNDERGROUND Partial Approval SHRINK WRAP OK TO COVER FROM PREVIOUS INSPECTION UP TO DUCTILE IRON ONLY
09/21/2017 MECHANICAL - UNDERGROUND Partial Approval FROM 20' OF 45 TO DUCTILE IRON UNDER WASH ONLY TO BE TESTED AT A LATER DATE
OK TO INSULATE AND WRAP PIPE
09/12/2017 MECHANICAL - UNDERGROUND Partial Approval OK TO SHADE PIPE FROM GRID LINE L TO E . ALL SHRINK WRAP OK TO COVER TO BE TESTED AT A LATER DATE
09/08/2017 MECHANICAL - UNDERGROUND Partial Approval OK TO SHADE PIPE GRID LINE P TO L ALL SHRINK WRAP OK
RESTRAINING BOLTS FROM GRID LINE L TO PASSED A 20' FROM 45 OK TO INSULATE AND WRAP TO BE TESTED AT LATER DATE
09/05/2017 MECHANICAL - UNDERGROUND Partial Approval RESTRAINING BOLTS 1ST 5 JOINTS BOTH PIPES OK TO INSSULATE AND SHRINK WRAP
FROM GRID LINE P TO L TEST FACILITY TO BE TESTED AT LATER DATE