Permit: T16CM01914
Permit Details
Apply Date:
03/14/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
OFFICE
Architects:
- BOLLARD, MARK EDWARD
Contractors:
- B F L CONSTRUCTION CO INC ,
Permit Reviews
Permit Number - T16CM01914
Permit Status: C of o
Permit Description: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/15/2017 | 3RD PARTY REVIEW - REVISION/OTHER | 02/15/2017 | COMPLETED |
03/14/2016 | PLANS OK TO SUBMIT - COMM | 03/14/2016 | COMPLETED |
03/15/2016 | 3RD PARTY REVIEW - COMMERCIAL | 04/21/2016 | COMPLETED |
04/21/2016 | POST 3RD PARTY REVIEW | 06/08/2016 | COMPLETED |
06/08/2016 | POST 3RD PARTY REVIEW | 06/14/2016 | COMPLETED |
06/14/2016 | POST 3RD PARTY REVIEW | 07/27/2016 | COMPLETED |
09/09/2016 | 3RD PARTY REVIEW - REVISION/OTHER | 09/15/2016 | COMPLETED |
10/14/2016 | 3RD PARTY REVIEW - REVISION/OTHER | 11/16/2016 | COMPLETED |
12/07/2016 | 3RD PARTY REVIEW - REVISION/OTHER | 12/12/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM01914
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/14/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM01914
Permit Description: OFFICE
Total Completed Inspections - 50
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/16/2016 | NPPO - FINAL | RLEDONNE | Approved | WALKED SITE WITH GC. WENT OVER NPPO. |
08/23/2016 | BUILDING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* 1- ATTENDED A PRE CON MEETING WITH bfl SUPERINTENDENT ON FLOW OF THE INSPECTION REQUESTS. 2- SHALL PROVIDE A SEPARATE DEDICATED ADDRESS OS SUIT NUMBERS FOR THE NEW BUILDING. |
09/16/2016 | PLUMBING - SEWER HCS CONNECT | JMILITEL | Approved | IVRS - Inspection :* |
10/26/2016 | STEM WALL/RETAINING WALL | JMILITE1 | Approved | OK TO POUR RETAINING WALL UP TO OPENING. |
11/08/2016 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* 1- DWV WATER TEST PROVIDED. 2- THIS INSPECTION IS FOR THE ROUGH UNDERGROUND PLUMBING SYSTEM LOCATED IN BASEMENT FLOOR LEVEL AND NOTED ON PLAN. |
11/08/2016 | ENGINEERING - FINAL | RLEDONNE | Approved | CALL FOR SWPPP ON DP16-0020. SWPPP NO CONCERNS AT THIS TIME. |
11/16/2016 | ELECTRIC - UNDERGROUND | JMILITE1 | Approved | |
11/16/2016 | BUILDING PRE-SLAB | JMILITE1 | Approved | OK TO POUR BASEMENT SLAB EXCEPT AT ENTRANCE INTO BASEMENT PENDING SPECIAL INSPECTION. |
12/28/2016 | EXCAVATION/LAYOUT REBAR & ZON | JMILITE1 | Approved | OK TO POUR 4 COLUMN FOOTINGS AT NORTH END OF BLDG. PENDING SPECIAL INSPECTION. |
12/29/2016 | REINFORCED MASONRY PRE-GROUT | JMILITE1 | Approved | OK TO GROUT SOUTH STAIRWELL TO 29'4" |
03/08/2017 | ELECTRIC - UFER | JMILITE1 | Approved | |
05/26/2017 | FIRE SPKLR - OH PIPING & HYDRO | JMILITE1 | Approved | PROVIDE BREAKAWAY JOINTS AT FIRE DAMPERS IN 1ST FLOOR PER DUCTMATE INSTRUCTIONS. |
06/14/2017 | PLUMBING - PROGRESS | JMILITE1 | Approved | |
06/22/2017 | ELECTRIC - CONSTRUCTION POWER | JMILITE1 | Approved | |
06/22/2017 | ELECTRIC - TEMP POWER FOR TEST | JMILITE1 | Approved | |
06/22/2017 | ELECTRIC - CABLE DROP | JMILITE1 | Approved | OK COMM. ECO |
06/23/2017 | TEP CLEARANCE - AM | JMILITELLO | Approved | ECO |
07/05/2017 | PLUMBING - INTERMEDIATE | JMILITE1 | Approved | OK TO COVER 1ST AND 2ND FLOOR PLUMBING. |
10/02/2017 | MECHANICAL - PROGRESS | JMILITE1 | Approved | |
10/02/2017 | PLUMBING - ROOF DRAINS | JMILITE1 | Approved | |
10/02/2017 | ELECTRIC - PROGRESS | JMILITE1 | Approved | |
10/02/2017 | FRAMING | JMILITE1 | Approved | |
10/02/2017 | ROOF NAILING | JMILITE1 | Approved | |
10/02/2017 | EXT METAL CLIPS/EXT SHEATHING | JMILITE1 | Approved | |
10/09/2017 | ELECTRIC - OUTDOOR LIGHTING | TVALENC1 | Approved | 1- GROUND CONDUCTORS PROVIDED FOR THE TWO LIGHT POLES. 2- STEEL REINFORCEMENT FOR LIGHT POLES PROVIED, OKAY FOR CONCRETE. |
10/17/2017 | MECHANICAL - INTERMEDIATE | JMILITE1 | Approved | IVRS - Inspection :* |
11/03/2017 | PLUMBING - GAS PRESSURE TEST | TVALENC1 | Approved | 1- GAS LINE PRESSURE TEST FOR THE GAS LINE LOCATED ON EAST EXTERIOR WALL FROM BASEMENT TO SECOND FLOOR CEILING IS OKAY TO COVER. |
12/21/2017 | ELECTRIC - INTERMEDIATE | NORTH | Approved | 3 LITE POLE BASES WEST SIDE |
12/21/2017 | BUILDING ABOVE CEILING | NORTH | Approved | AREA C LEVEL 2 |
12/21/2017 | MECHANICAL - ABOVE CEILING | NORTH | Approved | 2ND FLOOR |
12/21/2017 | ELECTRIC - ABOVE CEILING | NORTH | Approved | 2ND FLOOR |
12/21/2017 | SHEET ROCK NAILING | NORTH | Approved | BASEMENT SOUTH SIDE OK TO ROCH SOFFETS |
12/21/2017 | BUILDING ABOVE CEILING | NORTH | Approved | FIRE CAULK SERVER ROOM SOUTH SIDE |
01/24/2018 | PLUMBING - GAS PRESS TEST FNL | TVALENC1 | Approved | IVRS - Inspection :* CLEAR GAS METER |
02/07/2018 | GAS CLEARANCE | TVALENCIA | Approved | |
04/11/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
04/13/2018 | ELECTRIC - FINAL | BSTEVENS | Approved | |
04/13/2018 | MECHANICAL - HYDRONIC PIPING | BSTEVENS | Approved | |
04/13/2018 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | |
04/13/2018 | PLUMBING - ABOVE CEILING | BSTEVENS | Approved | |
04/13/2018 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
04/13/2018 | U VALUE FOR WINDOW | BSTEVENS | Approved | |
06/14/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
06/14/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
07/11/2018 | MECHANICAL - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
07/11/2018 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
07/11/2018 | BUILDING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
07/11/2018 | SIGN - FINAL | RLEDONNE | Approved | |
07/11/2018 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
07/13/2018 | RIGHT OF WAY - FINAL | JC/IM | Approved |