Permit: T16CM01914

Parcel: 11011174J


Addresses:

2480 N ARCADIA AV

Inspection Status: Approved

Inspection History: STEM WALL/RETAINING WALL

Date Description Inspector Results Comments
10/02/2017 STEM WALL/RETAINING WALL Approved
01/17/2017 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :* east retaining wall, ok
01/04/2017 STEM WALL/RETAINING WALL Partial Approval OK TO GROUT SOUTH STAIRWELL TO 32' AND TOPOFF AND NORTH STAIRWELL TO 29'4".
OK TO POUR TUNNELL ROOF PENDING SPECIAL INSPECTION.
10/26/2016 STEM WALL/RETAINING WALL Partial Approval OK TO POUR RETAINING WALL UP TO OPENING.
10/25/2016 STEM WALL/RETAINING WALL Partial Approval OK TO GROUT 2ND LIFT 4'-8' ATELEVATOR SHAFT AND 1ST 4' LIFT AT NORTH STAIRWELL.
10/24/2016 STEM WALL/RETAINING WALL Partial Approval CHECKED REINFORCING STEEL AT RETAINING WALL FROM GRID LINE E FROM 11-13A.
OK TO GROUT 1ST LIFT AT BASEMENT FLOOR ELEVATOR.
10/21/2016 STEM WALL/RETAINING WALL Partial Approval OK TO GROUT STEM WALL AT ELEVATOR SHAFT 0-4'.
OK TO GROUT STEM WALL AT NORTH STAIRWELL 0-22".
CHECKED REINFORCING STEEL IN RETAINING WALL FROM GRID LINE D10 TO E AND 10 T0 11 ON GRID LINE E.
10/13/2016 STEM WALL/RETAINING WALL Partial Approval OK TO POUR STEM WALL FROM GRID LINE C.1 TO NORTH TUNNEL WALL PENDING SPECIAL INSPECTION.
10/11/2016 STEM WALL/RETAINING WALL Partial Approval REINFORCING STEEL AT RETAINING WALL GRID LINE 10/A.3 TO C.
REINFORCING STEEL AT GRID LINES C TO END OF NORTH TUNNEL WALL.
10/10/2016 STEM WALL/RETAINING WALL Partial Approval checked reinforcng steel in retaining wall grid line a-3 10 - 11.
10/07/2016 STEM WALL/RETAINING WALL Partial Approval CHECKED REINFORCING STEEL IN RETAINING WALLS AT GRIG LINE 13 NORTH OF C AND AT A3 NOTED ON PLANS.
10/06/2016 STEM WALL/RETAINING WALL Partial Approval IVRS - Inspection :*

1- STEEL REBAR MAT FOR THE NORTH AND EAST RETAINING WALL LOCATED AT STAIRWELL S-100 AS NOTED ON PLAN.
09/28/2016 STEM WALL/RETAINING WALL Not ready for Inspection WORK INCOMPLETE FOR INSPECTION.