Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T16CM01914
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/02/2017 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
| 05/31/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- STEEL REBAR REINFORCEMENT FOR EQUIPMENT PAD IS OKAY COR CONCRETE. | |
| 04/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 04/18/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OKTO POUR 3 GENERATOR PADS AND ELEC. PADS AT MECH. YARD. | |
| 04/04/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR NORTH APPROACH SLAB PENDING SPECIAL INSPECTION. | |
| 04/03/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 03/07/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR MECHANICAL YARD FOOTINGS. UFER OK. |
|
| 02/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1- STEEL REBAR FOR THE CF1 LOCATED AT THE SOUTH END OF BLDG.ARE OKAY FOR CONCRETE. |
|
| 01/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR FINAL FOOTING AT EAST RETAINING WALL PENDING SPECIAL INSPECTION. | |
| 12/28/2016 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR 4 COLUMN FOOTINGS AT NORTH END OF BLDG. PENDING SPECIAL INSPECTION. | |
| 11/04/2016 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR 6 COLUMN FOOTINGS. | |
| 10/03/2016 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL 5A-13/E-D | |
| 09/30/2016 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL 13.0/G.O-D.O, A.3/10.0-12.5, 10.0/A.3-6.8. AND ALL NORTH EAST STAIR FOOTER. | |
| 09/28/2016 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | WORK INCOMPLETE FOR INSPECTION |