Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T15CM07917
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
1300 E TUCSON MARKETPLACE BL
Address NEW:
1300 E TUCSON MARKETPLACE BL
Apply Date:
11/13/2015
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW THEATRE
Contractors:
- COLORADO STRUCTURES INC ,
Permit Reviews
Permit Number - T15CM07917
Permit Status: C of o
Permit Description: NEW THEATRE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/29/2016 | RESUBMITTAL - TI ALL | 02/24/2016 | COMPLETED |
| 04/27/2016 | REVISION - - 1ST | 04/29/2016 | COMPLETED |
| 04/29/2016 | REVISION - - 1ST | 05/11/2016 | COMPLETED |
| 05/11/2016 | REVISION - - 1ST | 05/16/2016 | COMPLETED |
| 11/16/2015 | PLANS OK TO SUBMIT - COMM | 11/16/2015 | COMPLETED |
| 11/16/2015 | COMMERCIAL - NEW | 12/17/2015 | COMPLETED |
| 12/24/2015 | RESUBMITTAL - TI ALL | 01/29/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM07917
Permit Status: C of o
Permit Description: NEW THEATRE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/13/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM07917
Permit Description: NEW THEATRE
Total Completed Inspections - 49
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/18/2016 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDUA | Approved | |
| 03/21/2016 | SITE - SEWER | MRAMBER | Approved | IVRS - Inspection :* |
| 03/21/2016 | PLUMBING - SEWER HCS CONNECT | MRAMBER | Approved | IVRS - Inspection :* |
| 04/18/2016 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 07/25/2016 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | IVRS - Inspection :* |
| 07/27/2016 | FIRE SPKLR - UG PIPING FLUSH | jvincent | Approved | approved by CB |
| 08/30/2016 | ELECTRIC - CONSTRUCTION POWER | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/21/2016 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | IVRS - Inspection :* |
| 09/21/2016 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
| 09/21/2016 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
| 09/21/2016 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 09/21/2016 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/30/2016 | STUCCO MESH | MRAMBER | Approved | |
| 10/18/2016 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 10/19/2016 | GAS CLEARANCE | MRAMBER | Approved | |
| 10/25/2016 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | BUILDING ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | STEM WALL/RETAINING WALL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | ELECTRIC - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | ELECTRIC - TEMPORARY SERVICE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 10/27/2016 | NPPO - FINAL | RLEDONNE | Approved | |
| 10/28/2016 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved | |
| 11/02/2016 | FIRE SPKLR - FINAL | jvincent | Approved | |
| 11/02/2016 | FIRE SPKLR - OH PIPING & HYDRO | jvincent | Approved | |
| 11/02/2016 | RIGHT OF WAY - FINAL | rolson | Approved | |
| 11/03/2016 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/03/2016 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/03/2016 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/03/2016 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/03/2016 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 11/03/2016 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 11/08/2016 | FIRE - ALARM FINAL | jvincent | Approved | |
| 11/08/2016 | FIRE - FINAL | jvincent | Approved | |
| 11/09/2016 | PLUMBING - BACK WATER VALVE | MRAMBER | Approved | |
| 11/09/2016 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
| 11/09/2016 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | |
| 11/09/2016 | ELECTRIC - FINAL | MRAMBER | Approved | |
| 11/09/2016 | SIGN - FINAL | RLEDONNE | Approved | |
| 11/29/2016 | ENGINEERING - FINAL | CTREVIL | Approved | SITE IMPROVEMENTS FOR DEVELOPMENT PACKAGE ARE COMPLETE AROUND THIS BUILDING |