Permit: T15CM07917
Permit Details
Apply Date:
11/13/2015
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW THEATRE
Contractors:
- COLORADO STRUCTURES INC ,
Permit Reviews
Permit Number - T15CM07917
Permit Status: C of o
Permit Description: NEW THEATRE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/29/2016 | RESUBMITTAL - TI ALL | 02/24/2016 | COMPLETED |
04/27/2016 | REVISION - - 1ST | 04/29/2016 | COMPLETED |
04/29/2016 | REVISION - - 1ST | 05/11/2016 | COMPLETED |
05/11/2016 | REVISION - - 1ST | 05/16/2016 | COMPLETED |
11/16/2015 | PLANS OK TO SUBMIT - COMM | 11/16/2015 | COMPLETED |
11/16/2015 | COMMERCIAL - NEW | 12/17/2015 | COMPLETED |
12/24/2015 | RESUBMITTAL - TI ALL | 01/29/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM07917
Permit Status: C of o
Permit Description: NEW THEATRE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/13/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM07917
Permit Description: NEW THEATRE
Total Completed Inspections - 49
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/18/2016 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDUA | Approved | |
03/21/2016 | SITE - SEWER | MRAMBER | Approved | IVRS - Inspection :* |
03/21/2016 | PLUMBING - SEWER HCS CONNECT | MRAMBER | Approved | IVRS - Inspection :* |
04/18/2016 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
07/25/2016 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | IVRS - Inspection :* |
07/27/2016 | FIRE SPKLR - UG PIPING FLUSH | jvincent | Approved | approved by CB |
08/30/2016 | ELECTRIC - CONSTRUCTION POWER | RCAMACHO | Approved | IVRS - Inspection :* |
09/21/2016 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | IVRS - Inspection :* |
09/21/2016 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
09/21/2016 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
09/21/2016 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
09/21/2016 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | IVRS - Inspection :* |
09/30/2016 | STUCCO MESH | MRAMBER | Approved | |
10/18/2016 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | IVRS - Inspection :* |
10/19/2016 | GAS CLEARANCE | MRAMBER | Approved | |
10/25/2016 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | BUILDING ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | STEM WALL/RETAINING WALL | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | ELECTRIC - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | ELECTRIC - TEMPORARY SERVICE | MRAMBER | Approved | IVRS - Inspection :* |
10/27/2016 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
10/27/2016 | NPPO - FINAL | RLEDONNE | Approved | |
10/28/2016 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved | |
11/02/2016 | FIRE SPKLR - FINAL | jvincent | Approved | |
11/02/2016 | FIRE SPKLR - OH PIPING & HYDRO | jvincent | Approved | |
11/02/2016 | RIGHT OF WAY - FINAL | rolson | Approved | |
11/03/2016 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
11/03/2016 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
11/03/2016 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
11/03/2016 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
11/03/2016 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
11/03/2016 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
11/08/2016 | FIRE - ALARM FINAL | jvincent | Approved | |
11/08/2016 | FIRE - FINAL | jvincent | Approved | |
11/09/2016 | PLUMBING - BACK WATER VALVE | MRAMBER | Approved | |
11/09/2016 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
11/09/2016 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | |
11/09/2016 | ELECTRIC - FINAL | MRAMBER | Approved | |
11/09/2016 | SIGN - FINAL | RLEDONNE | Approved | |
11/29/2016 | ENGINEERING - FINAL | CTREVIL | Approved | SITE IMPROVEMENTS FOR DEVELOPMENT PACKAGE ARE COMPLETE AROUND THIS BUILDING |