Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: BUILDING ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2016 |
BUILDING ABOVE CEILING |
|
Approved |
IVRS - Inspection :* |
| 10/25/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 10/20/2016 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 09/30/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 09/30/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
lobby ok to drop tiles |
| 09/27/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 09/23/2016 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 09/20/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
auditorium #7 ok |
| 09/13/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 09/13/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
audiotorium #8 ok |
| 08/24/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 08/24/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
theatre 14 ok |
| 08/22/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 08/22/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
rms 12, 13, ok, room 14 grid wire not properly installed |
| 08/18/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
theatre 11 ok |
| 08/08/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 08/01/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 08/01/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
RMS 5 AND 6 ONLY |
| 07/19/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |
| 07/19/2016 |
BUILDING ABOVE CEILING |
|
Partial Approval |
RMS 1,2 AND 3 ONLY |