Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Permit Number - T15CM07917

Inspection Description - BUILDING PRE-SLAB

Inspection Status - Approved

Date Description Inspector Results Comments
09/21/2016 BUILDING PRE-SLAB Approved IVRS - Inspection :*
09/07/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
09/07/2016 BUILDING PRE-SLAB Partial Approval 11, 12, 13, rebar and elec int ok at seating area
08/12/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
08/12/2016 BUILDING PRE-SLAB Partial Approval 01015-rooms 5&6 ok
08/09/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
08/09/2016 BUILDING PRE-SLAB Partial Approval theatre 3 & 4 ok
08/08/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
08/08/2016 BUILDING PRE-SLAB Partial Approval AUD 1 AND 2 ONLY
08/05/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
08/05/2016 BUILDING PRE-SLAB Partial Approval auditorium elevation except 1st 2 elevations
07/25/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
07/25/2016 BUILDING PRE-SLAB Partial Approval footer at entry ok, slab at entry ok
07/22/2016 BUILDING PRE-SLAB Not ready for Inspection
06/09/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
06/09/2016 BUILDING PRE-SLAB Partial Approval 1-stem wall at S. scullery wall ok.
2-4 alcove preslabs ok
06/06/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
06/06/2016 BUILDING PRE-SLAB Partial Approval 4 alcove footers ok
05/18/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
05/12/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
04/28/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
04/27/2016 BUILDING PRE-SLAB Cancelled IVRS - RI canceled
04/25/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
04/19/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
04/18/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
04/14/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
04/12/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
04/11/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
04/08/2016 BUILDING PRE-SLAB Cancelled IVRS - RI canceled
04/05/2016 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/24/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
03/21/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
03/17/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*