Permit: T12CM07328
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
8980 E TANQUE VERDE RD
Address NEW:
8980 E TANQUE VERDE RD
Apply Date:
11/16/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Architects:
- DAVID PARKER
Contractors:
- MANZANO CONSTRUCTION COMPANY LLC
Permit Reviews
Permit Number - T12CM07328
Permit Status: C of o
Permit Description: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/15/2013 | RESUBMITTAL | 02/01/2013 | COMPLETED |
| 11/16/2012 | COMMERCIAL - NEW | 11/16/2012 | COMPLETED |
| 11/16/2012 | COMMERCIAL - NEW | 12/20/2012 | COMPLETED |
| 12/14/2012 | RESUBMITTAL - TI ALL | 01/15/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM07328
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/16/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM07328
Permit Description: RETAIL
Total Completed Inspections - 47
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/26/2013 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | |
| 02/27/2013 | STEM WALL/RETAINING WALL | JMILITEL | Approved | PROVIDE 3 REBARS AT EACH CORNER OK TO POUR RETAINING ALL FOOTING OK FOR LST LIFT |
| 03/19/2013 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 04/18/2013 | PLUMBING - YARD WTR LINE/TEST | JMILITEL | Approved | IVRS - Inspection :* |
| 04/23/2013 | SITE - SEWER | JMILITEL | Approved | IVRS - Inspection :* |
| 04/23/2013 | PLUMBING - SEWER HCS CONNECT | JMILITEL | Approved | IVRS - Inspection :* |
| 04/29/2013 | ROOF NAILING | JMILITEL | Approved | IVRS - Inspection :* |
| 04/30/2013 | PLUMBING - ROOF DRAINS | JMILITEL | Approved | IVRS - Inspection :* |
| 04/30/2013 | PLUMBING - PRE SLAB | JMILITEL | Approved | IVRS - Inspection :* |
| 05/01/2013 | PLUMBING - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 05/01/2013 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 05/21/2013 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 05/30/2013 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | 200 PSI for 2 hours Approved |
| 06/27/2013 | ELECTRIC - TEMPORARY SERVICE | JMILITEL | Approved | IVRS - Inspection :* |
| 06/27/2013 | ELECTRIC - UNDERGROUND | JMILITEL | Approved | IVRS - Inspection :* |
| 06/27/2013 | ELECTRIC - UFER | JMILITEL | Approved | IVRS - Inspection :* |
| 06/27/2013 | EXT METAL CLIPS/EXT SHEATHING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/27/2013 | REINFORCED MASONRY PRE-GROUT | JMILITEL | Approved | IVRS - Inspection :* |
| 06/27/2013 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | IVRS - Inspection :* |
| 06/28/2013 | FIRE SPKLR - UG PIPING FLUSH | WMOTTO | Approved | |
| 07/09/2013 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
| 07/29/2013 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 07/29/2013 | PLUMBING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 07/29/2013 | BUILDING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 07/29/2013 | U VALUE FOR WINDOW | JMILITEL | Approved | IVRS - Inspection :* |
| 07/29/2013 | SIGN - FINAL | RLEDONNE | Approved | |
| 08/05/2013 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 08/05/2013 | OUTDOOR LIGHTING FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 08/05/2013 | ELECTRIC - OUTDOOR LIGHTING | JMILITEL | Approved | IVRS - Inspection :* |
| 08/05/2013 | ELECTRIC - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 08/05/2013 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 08/05/2013 | BUILDING ABOVE CEILING | JMILITEL | Approved | PROVIDE BEADED COLLARS ON ALL CEILING DIFFUSERS & SUPPORT TO STRUCTURE. PLANS REQUIRE METAL DRAW BANDS ON FLEX DUCTS. WILL CHECK ON FINAL. OK FOR CEILING TILES. OK FOR F.F. & E. |
| 08/05/2013 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 08/16/2013 | RIGHT OF WAY - FINAL | PW | Approved | |
| 08/27/2013 | FIRE - ALARM FINAL | CSCHULTZ | Approved | |
| 08/27/2013 | FIRE SPKLR - OH PIPING & HYDRO | CSCHULTZ | Approved | 200 PSI for 2 hours and placement APPROVED |
| 09/11/2013 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
| 09/11/2013 | FIRE - FINAL | CSCHULTZ | Approved | |
| 09/13/2013 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 09/17/2013 | MECHANICAL - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 09/17/2013 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 09/18/2013 | BUILDING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 09/24/2013 | NPPO - FINAL | DROBERTS | Approved | |
| 09/24/2013 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 09/24/2013 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 09/26/2013 | ZONING - FINAL | DROBERTS | Approved | OK PER PHONE CALL, EASEMENT CONDITIONS HAVE BEEN CLEARED |
| 09/26/2013 | FRAMING | BBENEDON | Approved |